Concept explainers
Given the following information on job times and due dates, determine the optimal processing sequence using (1) FCFS, (2) SPT, (3) EDD, and (4) CR. For each method, find the average job flow time and the average job tardiness. Jobs are listed in order of arrival.
1)
To determine: Sequence of jobs based on decision rule First Come First Served (FCFS).
Introduction: First Come First Served is the scheduling rule, which helps to arrange the sequence in the order. Here, the first come would be served first.
Answer to Problem 17P
Explanation of Solution
Given information:
Job | Job time (hours) | Due date (hours) |
a | 3.5 | 7 |
b | 2.0 | 6 |
c | 4.5 | 18 |
d | 5.0 | 22 |
e | 2.5 | 4 |
f | 6.0 | 20 |
Determine the sequence using FCFS:
According to FCFS, the first come would be served first. Hence, the jobs should be sequenced in the order as per its arrival.
Hence, the sequence of jobs using FCFS is a-b-c-d-e.
2)
To determine: Sequence of jobs based on decision rule Shortest Processing Time (SPT).
Introduction: Shortest Processing Tine is the scheduling rule, which helps to arrange the sequence in the order. Here, job with the shortest duration would be served first. Then, the process would be going on from shortest to largest duration.
Answer to Problem 17P
Explanation of Solution
Given information:
Job | Job time (hours) | Due date (hours) |
a | 3.5 | 7 |
b | 2.0 | 6 |
c | 4.5 | 18 |
d | 5.0 | 22 |
e | 2.5 | 4 |
f | 6.0 | 20 |
Determine the sequence using SPT:
According to SPT, the job that has the shortest processing would be served first and it goes on as the processing time increase. Duration should be assembled in the ascending order
Hence, the sequence of jobs using SPT is b-e-a-c-d-f.
3)
To determine: Sequence of jobs based on decision rule Earliest Due Date (EDD).
Introduction: Earliest Due Date is the scheduling rule, which helps to arrange the sequence in the order. Here, job with the earliest due date would be served first. Then, the process would be going on from earliest due date to latest due date.
Answer to Problem 17P
Explanation of Solution
Given information:
Job | Job time (hours) | Due date (hours) |
a | 3.5 | 7 |
b | 2.0 | 6 |
c | 4.5 | 18 |
d | 5.0 | 22 |
e | 2.5 | 4 |
f | 6.0 | 20 |
Determine the sequence using EDD:
According to EDD, the job that has the earliest due date would be served first and it goes on as the due date increases. The job should be arranged based on due date. Due date should be assembled in the ascending order
Hence, the sequence of jobs using EDD is e-b-a-c-f-d.
4)
To determine: Sequence of jobs based on decision rule critical ratio.
Introduction: Critical ratio is kind of scheduling rule that helps to identify that, the task or job is on the correct track. It would help to identify if the task is behind or ahead of the schedule.
Answer to Problem 17P
Explanation of Solution
Given information:
Job | Job time (hours) | Due date (hours) |
a | 3.5 | 7 |
b | 2.0 | 6 |
c | 4.5 | 18 |
d | 5.0 | 22 |
e | 2.5 | 4 |
f | 6.0 | 20 |
Determine the sequence using critical ratio:
Initial critical ratio should be determined at day 0:
Job | Job time (hours) | Due date (hours) | Critical ratio |
a | 3.5 | 7 | 2. |
b | 2.0 | 6 | 3 |
c | 4.5 | 18 | 4 |
d | 5.0 | 22 | 4.4 |
e | 2.5 | 4 | 1.6 |
f | 6.0 | 20 | 3.33 |
Critical ratio for Job a:
It is can be determined by dividing the value attained by subtracting the completion day of previous job from the due date of current job with the processing time.
Note: The procedure continues for all the jobs.
Job e has the lowest critical ratio. Thus, it will be completed first. Hence, Job e would be completed first in the sequence of jobs.
Determine the critical ratio after the completion of Job a:
As the processing time of job a is 2.5 hours, completion day of completed day would be 2.5.
Job | Job time (hours) | Due date (hours) | Critical ratio |
a | 3.5 | 7 | 1.29 |
b | 2.0 | 6 | 1.75 |
c | 4.5 | 18 | 3.44 |
d | 5.0 | 22 | 3.90 |
e | |||
f | 6.0 | 20 | 2.90 |
Critical ratio for Job a:
It is can be determined by dividing the value attained by subtracting the completion day of completed job from the due date of current job with the processing time.
Note: The procedure continues for all the jobs.
Job a has the lowest critical ratio. Hence, Job a would be completed next in the sequence of jobs after Job e.
Determine the critical ratio after the completion of Job e and Job a:
As the processing time of job e is 2.5 hours and Job a is 3.5, completion day of completed day would be 6 (2.5+3.5).
Job | Job time (hours) | Due date (hours) | Critical ratio |
a | |||
b | 2.0 | 6 | 0 |
c | 4.5 | 18 | 2.67 |
d | 5.0 | 22 | 3.20 |
f | 6.0 | 20 | 2.33 |
Critical ratio for Job b:
It is can be determined by dividing the value attained by subtracting the completion day of completed job from the due date of current job with the processing time.
Note: The procedure continues for all the jobs.
Job b has the lowest critical ratio. Hence, Job b would be completed next in the sequence of jobs after Job e and Job a.
Determine the critical ratio after the completion of Job e, Job a, and Job b:
As the processing time of job e is 2.5 hours, Job a is 3.5, and Job b is 2. Completion day of completed day would be 8 (2.5+3.5+2).
Job | Job time (hours) | Due date (hours) | Critical ratio |
a | |||
b | |||
c | 4.5 | 18 | 2.22 |
d | 5.0 | 22 | 2.80 |
f | 6.0 | 20 | 2.00 |
Critical ratio for Job c:
It is can be determined by dividing the value attained by subtracting the completion day of completed job from the due date of current job with the processing time.
Note: The procedure continues for all the jobs.
Job f has the lowest critical ratio. Hence, Job f would be completed next in the sequence of jobs.
Determine the critical ratio after the completion of Job e, Job a, Job b, and Job f:
As the processing time of job e is 2.5 hours, Job a is 3.5, Job b is 2, and Job f is 6.0. Completion day of completed day would be 14 (2.5+3.5+2+6).
Job | Job time (hours) | Due date (hours) | Critical ratio |
a | |||
b | |||
c | 4.5 | 18 | 2.22 |
d | 5.0 | 22 | 2.80 |
f |
Critical ratio for Job c:
It is can be determined by dividing the value attained by subtracting the completion day of completed job from the due date of current job with the processing time.
Note: The procedure continues for all the jobs.
Job c has the lowest critical ratio. Hence, Job c would be completed next in the sequence of jobs.
As Job d is the remaining job, it will be completed next.
Hence, the sequence of jobs using critical ratio is e-a-b-f-c-d.
Determine the average flow time and average tardiness:
First Come First Served:
Job | Job time (hours) | Due date (hours) | Flow time | Tardiness |
a | 3.5 | 7 | 3.5 | |
b | 2.0 | 6 | 5.5 | |
c | 4.5 | 18 | 10.0 | |
d | 5.0 | 22 | 15.0 | |
e | 2.5 | 4 | 17.5 | 13.5 |
f | 6.0 | 20 | 23.5 | 3.5 |
Total | 23.5 | 75.0 | 17.0 |
Supporting calculation:
Processing time and due date are given for each job. Flow time is the cumulative of the processing time.
Tardiness of Job a, Job, b, Job c, and Job d:
Flow time of Job a, Job b, Job c, and Job d is less than its respective due date. Hence, there would be no tardiness.
Tardiness of Job e:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job e is 13.5.
Tardiness of Job f:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job f is 3.5.
Average flow time:
It is calculated by dividing the total flow time and number of jobs.
Hence, average flow time is 12.5 hours.
Average tardiness:
It is calculated by dividing the total tardiness and number of jobs.
Hence, average tardiness is 2.83 hours
Shortest processing time:
Job | Job time (hours) | Due date (hours) | Flow time | Tardiness |
b | 2.0 | 6 | 2.0 | |
e | 2.5 | 4 | 4.5 | 0.5 |
a | 3.5 | 7 | 8.0 | 1.0 |
c | 4.5 | 18 | 12.5 | |
d | 5.0 | 22 | 17.5 | |
f | 6.0 | 20 | 23.5 | 3.5 |
Total | 23.5 | 68.0 | 5.0 |
Supporting calculation:
Processing time and due date are given for each job. Flow time is the cumulative of the processing time.
Tardiness of Job b, Job c, and Job d:
Flow time of Job b, Job c, and Job d is less than its respective due date. Hence, there would be no tardiness.
Tardiness of Job e:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job e is 0.5.
Tardiness of Job a:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job a is 1.
Tardiness of Job f:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job f is 3.5.
Average flow time:
It is calculated by dividing the total flow time and number of jobs.
Hence, average flow time is 11.33 hours.
Average tardiness:
It is calculated by dividing the total tardiness and number of jobs.
Hence, average tardiness is 0.83 hours
Earliest Due Date:
Job | Job time (hours) | Due date (hours) | Flow time | Tardiness |
e | 2.5 | 4 | 2.5 | |
b | 2.0 | 6 | 4.5 | |
a | 3.5 | 7 | 8.0 | 1.0 |
c | 4.5 | 18 | 12.5 | |
f | 6.0 | 20 | 18.5 | |
d | 5.0 | 22 | 23.5 | 1.5 |
Total | 23.5 | 69.5 | 2.5 |
Supporting calculation:
Processing time and due date are given for each job. Flow time is the cumulative of the processing time.
Tardiness of Job e, Job b, Job c, and Job f:
Flow time of Job e, Job b, Job c, and Job f is less than its respective due date. Hence, there would be no tardiness.
Tardiness of Job a:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job a is 1.
Tardiness of Job d:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job d is 1.5.
Average flow time:
It is calculated by dividing the total flow time and number of jobs.
Hence, average flow time is 11.58 hours.
Average tardiness:
It is calculated by dividing the total tardiness and number of jobs.
Hence, average tardiness is 0.42 hours
Critical ratio:
Job | Job time (hours) | Due date (hours) | Flow time | Tardiness |
e | 2.5 | 4 | 2.5 | |
a | 3.5 | 7 | 6.0 | |
b | 2.0 | 6 | 8.0 | 2.0 |
f | 6.0 | 20 | 14.0 | |
c | 4.5 | 18 | 18.5 | 0.5 |
d | 5.0 | 22 | 23.5 | 1.5 |
Total | 23.5 | 72.5 | 4.0 |
Supporting calculation:
Processing time and due date are given for each job. Flow time is the cumulative of the processing time.
Tardiness of Job e, Job a, and Job f:
Flow time of Job e, Job a, and Job f is less than its respective due date. Hence, there would be no tardiness.
Tardiness of Job b:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job b is 2.
Tardiness of Job c:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job c is 0.5.
Tardiness of Job d:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job d is 1.5.
Average flow time:
It is calculated by dividing the total flow time and number of jobs.
Hence, average flow time is 12.08 hours.
Average tardiness:
It is calculated by dividing the total tardiness and number of jobs.
Hence, average tardiness is 0.67 hours.
Want to see more full solutions like this?
Chapter 16 Solutions
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
- I need to forecast using a 3-Period-Moving-Average-Monthly forecasting model which I did but then I need to use my forecast numbers to generate a Master Production Schedule (MPS) I have to Start with actual sales (my own test data numbers) for August-2022 Oct-2022 i need to create MPS to supply demand starting November-2022 April 2023 I just added numbers without applying formulas to the mps on the right side of the spreadsheet because I do not know how to do it. The second image is the example of what it should look like. Thank You.arrow_forwardSolve the following Question 1. How do volume and variety affect the process selection and layout types? Discuss 2. How is the human resource aspect important to operation function? Discuss 3. Discuss the supply network design and its impact on the overall performance of the organization.arrow_forwardHelp with question?arrow_forward
- What are some good examples of bullet points on a resume for a Christian Elementary School?arrow_forwardWhat is an example of a cover letter for a Christian School Long-Term Substitute Teaching position?arrow_forwardThe supply chain is a conventional notion, but organizations are only really interested in making products that they can sell to customers. Provided they have reliable supplies of materials and reasonable transport for finished products, logistics is irrelevant. Do you think this is true? If yes, explain, and if no, clearly explain as well.arrow_forward
- working as a program operations managerarrow_forward12 X1, X230 1 x =0x2 write the Following linear Programming model by 1- general Form Canonical Forms Canonical formY 2- Standard Form Max Z=35X+ 4 X 2 +6 X3 ST. X+2X2-5x3 = 40 3X, + 6X2 + 7x 3 = 30 7x, +lox2 x3 = 50 X3 X 2 X 3 <0arrow_forwarda/ a Minimum cost assign each worker for one job at Jobs J1 12 33 WI 2 4 6 W2 5 W3 5 33 6 7arrow_forward
- وبة واضافة هذه القيمة الى القيم Ex: Assign each job for each worker at minimum total Cost عمل لكل عامل وبأقل كلفة ممكنة obs الأعمال Workors العمال J1 J2 J3 J4 W₁ 15 13 14 12 W2 11 12 15 13 W3 13 12 10 11 W4 15 17 14 16arrow_forwardThe average completion time (flow time) for the sequence developed using the FCFS rule = 11.75 days (round your response to two decimal places). The percentage utilization for the sequence developed using the FCFS rule = 42.55 % (enter your response as a percentage rounded to two decimal places). b) Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): An Alabama lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard's schedule. In what sequence would the jobs be ranked according to the decision rules on the left: Job Due Date A 212 B 209 C 208 D 210 Duration (days) 6 3 3 8 Sequence 1 Job B 2 3 4 A D The average tardiness (job lateness) for the sequence developed using the SPT rule = 5.00 days (round your response to two decimal places). The average completion time (flow time) for the sequence developed using the SPT rule = 10.25 days…arrow_forwardWith the aid of examples, fully discuss any five (5) political tactics used in organisations.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.