Operations Management: Sustainability and Supply Chain Management (12th Edition)
12th Edition
ISBN: 9780134130422
Author: Jay Heizer, Barry Render, Chuck Munson
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 15, Problem 2P
Summary Introduction
To draw: The Gantt chart for the given information.
Introduction: The Gantt chart is the kind of chart that is used to represent the amount of job done within a particular period. It is used to graphically represent the amount of job planned and done in a certain period.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
First Printing and Copy Center has 4 jobs to be scheduled. Production scheduling personnel are reviewing the Gantt chart at the end of day
4.
Job
D
was scheduled to begin early on day
2
and take
7.5
days. As of now (the review point after day
4),
it is 2 days ahead of schedule.
Job
E
should begin on day
1
and take
4
days. It was on time.
Job
F
was to begin on day
2,
but maintenance forced a delay of
0.5
day.
The job should now take
5
full days. It is now on schedule.
Job
G
is a day behind schedule. It started at the beginning of day
2
and should require
7
days to complete.
Add the actual progress to the Gantt schedule shown on the right (on which the planned timings have been already plotted as blue lines).
Using the line drawing tool, plot the actual progress showing the actual start and the expected finish on top of (overlapping) the maroon dashed line provided just above the job number for each of the tasks.
Ron Satterfield's excavation company uses both Gantt scheduling charts and Gantt load charts. Today, which is the end
of day 7, Ron is reviewing the Gantt chart depicting these schedules:
Day
Job #151 was scheduled to begin on day 3 and to take 6 days. It got started on time and is 1 day ahead of schedule.
Job #177 was scheduled to begin on day 1 and take 4 days. It is currently on time.
Job #179 was scheduled to start on day 7 and take 2 days. It actually got started on day 6 and is progressing according
to plan.
Job #211 was scheduled to begin on day 5, but missing equipment delayed it until day 6. It is progressing as expected
and should take 3 days.
Job #215 was scheduled to begin on day 4 and take 5 days. It got started on time but has since fallen behind 2 days.
Job 12 3 4 56 789 10 11
--
151
177 +
This exercise contains only part a.
179
a) Add the actual progress to the Gantt schedule shown on the right (on which the planned timings have been already
plotted). Using the line…
Ron Satterfield's excavation company uses both Ganit scheduling charts and Gantt load charts. Today,
which is the end of day 7, Ron is reviewing the Gantt chart depicting these schedules:
Job #151 was scheduled to begin on day 3 and to take 5 days. It got started on time and is 1 day ahead of
schedule.
Job #177 was scheduled to begin on day 1 and take 4 days. It is currently on time.
Job #179 was scheduled to start on day 6 and take 2 days. It actually got started on day 5 and is
progressing according to plan.
Job #211 was scheduled to begin on day 5, but missing equipment delayed it until day 6. It is progressing
as expected and should take 3 days.
Job #215 was scheduled to begin on day 5 and take 5 days. It got started on time but has since fallen
behind 1 day.
This exercise contains only part a
a) Add the actual progress to the Gantt schedule shown on the right (on which the planned timings have
been already plotted as blue lines).
Using the line drawing tool, plot the actual…
Chapter 15 Solutions
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Ch. 15 - Prob. 1DQCh. 15 - Prob. 2DQCh. 15 - Prob. 3DQCh. 15 - Prob. 4DQCh. 15 - Prob. 5DQCh. 15 - Prob. 6DQCh. 15 - Prob. 7DQCh. 15 - Prob. 8DQCh. 15 - Prob. 9DQCh. 15 - Prob. 10DQ
Ch. 15 - Prob. 11DQCh. 15 - Prob. 12DQCh. 15 - Prob. 13DQCh. 15 - Prob. 1PCh. 15 - Prob. 2PCh. 15 - Prob. 3PCh. 15 - Prob. 4PCh. 15 - Prob. 5PCh. 15 - Prob. 6PCh. 15 - Prob. 7PCh. 15 - Prob. 8PCh. 15 - Prob. 9PCh. 15 - Prob. 10PCh. 15 - Prob. 15PCh. 15 - Prob. 16PCh. 15 - Prob. 17PCh. 15 - Prob. 18PCh. 15 - Prob. 19PCh. 15 - Prob. 20PCh. 15 - Prob. 21PCh. 15 - Prob. 22PCh. 15 - Prob. 23PCh. 15 - Prob. 26PCh. 15 - Prob. 27PCh. 15 - Prob. 1CSCh. 15 - Prob. 2CSCh. 15 - Prob. 3CSCh. 15 - Prob. 4CSCh. 15 - Prob. 1.1VCCh. 15 - Prob. 1.2VCCh. 15 - Prob. 1.3VCCh. 15 - Prob. 2.1VCCh. 15 - Prob. 2.2VCCh. 15 - Prob. 2.3VCCh. 15 - Prob. 2.4VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Ron Satterfield's excavation company uses both Gantt scheduling charts and Gantt load charts. Today, which is the end of day 7, Ron is reviewing the Gantt chart depicting these schedules: Job #151 was scheduled to begin on day 3 and to take 7 days. It got started on time and is 1 day ahead of schedule. Job #177 was scheduled to begin on day 3 and take 5 days. It is currently on time. Job #179 was scheduled to start on day 6 and take 3 days. It actually got started on day 5 and is progressing according to plan. Job #211 was scheduled to begin on day 5, but missing equipment delayed it until day 6. It is progressing as expected and should take 3 days. Job #215 was scheduled to begin on day 4 and take 5 days. It got started on time but has since fallen behind 2 days. This exercise contains only part a. a) Add the actual progress to the Gantt schedule shown on the right (on which the planned timings have been already plotted as blue lines). Using the line drawing tool, plot the actual…arrow_forwarda-b) Using Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order Job V 1 2 3 4 5 6 7 NDX W Y c) For the schedule developed using Johnson's rule, the total length of time taken to complete the seven printing and binding jobs (including binding) = hours (enter your response as a whole number). W The following set of seven jobs is to be processed through two work centers at George Heinrich's printing company. The sequence is first printing, then binding. Processing time at each of the work centers is shown in the following table: Job >>> W X > N T U V Y Printing (hours) Binding (hours) 4 12 8 693556 7 14 2 10 1 13arrow_forwardOn Monday morning, Baxter Industries has the following jobs waiting for processing in two departments, milling, and drilling, in that order. Time Required (hours) Job Mill Drill 216 7 6 327 4 10 462 6 3 519 5 8 258 8 7 617 9 10 Develop a minimum makespan schedule using Johnson's rule. The schedule using Johnson's rule is - - - - - . Choose the correct Gantt chart with the minimum makespan schedule.arrow_forward
- On Monday morning, Baxter Industries has the following jobs waiting for processing in two departments, milling, and drilling, in that order. Time Required (hours) Job Mill Drill 216 7 11 327 6 10 462 8 4 519 5 8 258 3 5 617 12 15 Develop a minimum makespan schedule using Johnson's rule. The schedule using Johnson's rule is - - - - - . Choose the correct Gantt chart with the minimum makespan schedule. The correct graph is .arrow_forwardUsing Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order Job 1 ▼ B C E F A D Part 2 2 ▼ F C A D B E Part 3 3 ▼ A B D F C E Part 4 4 ▼ E D C B F A Part 5 5 ▼ F C D A E B Part 6 6 ▼ D C F B E A Part 7 For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation) = enter your response here hours (enter your response as a whole number). ... Question content area right Part 1 Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows: Job Operation 1 (hours) Operation 2 (hours) A 4 8 B 10 5 C 3 11 D…arrow_forwardOPERATION MANAGEMENTarrow_forward
- Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.arrow_forwardUsing the FCFS rule for scheduling, the sequence is ▼ 1-3-2 3-1-2 1-2-3 2-1-3 2-3-1 3-2-1 . Part 2 For the schedule developed using the FCFS rule, the total length of time taken to complete the three suits (including delivery) = enter your response here hours (enter your response as a whole number). Part 3 Using Johnson's rule for 2-machine scheduling, the sequence is ▼ 3-1-2 1-2-3 2-1-3 3-2-1 2-3-1 1-3-2 . Part 4 For the schedule developed using the Johnson's rule, the total length of time taken to complete the three suits (including delivery) = enter your response here hours (enter your response as a whole number). Part 5 Of the two developed schedules, ▼ Johnson's the FCFS rule gets the schedule finished sooner. ... Question content area right Part 1 Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing…arrow_forwardThe following table contains information regarding jobs that are to be scheduled through one machine: Job Processing Time (Days) Due date A 4 20 B 12 30 C 2 15 D 11 16 E 10 18 F 3 5 G 6 9 Qus 1: Find the FCFS Schedule? Qus 2: Find the SOT Schedule? Qus 3:Find the DDate Schedule? Qus 4: What are the mean flow time and average lateness for each of the schedule above? Qus 5: Which priority rule is appropriate for job scheduling? Justify your answer.arrow_forward
- sniparrow_forwardUsing Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order Job 1 C 2 B 3 E 4 A 5 D 6 F For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation) = nothing hours (enter your response as a whole number).arrow_forwardA nursing home must schedule nurses in a manner that balances providing adequate patient care while keeping costs down. From historical records, administrators can project the minimum number of nurses to have on hand during each day/time slot. This data is shown below. Shift Time Slot Minimum number of nurses needed 1 12 am-4 10 2 4 am-8 6 3 8 am-12 8 4 12 pm-4 12 5 4 pm-8 10 6 8 pm-12 14 Nurses must start work at the beginning of one of the four-hour shifts (starting as early as 12 am midnight or as late as 8pm evening) and work for eight hours. Nurses who begin working at 8 pm will work until 4 am the next morning. Formulate and solve the nurse-scheduling problem so as to minimize excess stagging while satisfying minimum staffing requrements. What is the value of total excess staffing?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY