Question
Chapter 15, Problem 3CS
Summary Introduction
Case summary:
The case deals about the store that manufactures old Oregon tables. There are four employees (Person T, Person G, Person L, and Person C) who deal with the operations such as preparation, assembly, finishing, and packaging. Each one would deal with a specific operation. However, all the four are able to do all the four operations. Person R is hired to perform major duties and help when the employees are absent. The time taken by each employee to perform every task is as follows:
Preparation | Assembly | Finishing | Packaging | |
Person T | 100 | 60 | 90 | 25 |
Person G | 80 | 80 | 60 | 10 |
Person L | 110 | 90 | 80 | 10 |
Person C | 120 | 70 | 100 | 25 |
Person R | 110 | 80 | 100 | 10 |
To determine: The fastest way to manufacture the tables using original crew if Person C is moved to either finishing or preparation.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
QUESTION 5a. A Chef bakes and decorates cakes in a two-stage process. The cakes are baked and once cooledthey are then decorated based on the clients’ requirements. The Chef received seven orders forfully decorated cakes and has documented the orders with respective processing times for bakingand decorating, as shown in Table 7 that follows:.Table 7. Cake Job Orders received by the Chef with the respective processing times for Baking andDecoratingCake Job Order Baking Processing Time Decorating Processing TimeA 2 1B 8 5C 4 6D 9 7E 7 8F 9 6G 3 5
(i) Using Johnson’s Rule, determine the optimum sequence for processing the cake joborders through the baking and decorating stages.
Q. 3
What is the total makespan from Question 1?
Question 1: Four floral arranging jobs are to be carried out across three stations: A (Arrange), B (Bag), C (crop) shown. The station sequences and job times in minutes are shown below, along with the due dates for each job. Using an "earliest due date" job dispatching priority rule, which, if any, of the jobs in will be late?
Answer was Job 4
Group of answer choices
a. 100
b. 130
c. 150
d. 170
e. 200
Question 5
Tasty Tim’s
Tasty Tim’s is a specialty taco restaurant. The following tasks are required for the successful assembly of a Tasty taco (times are in seconds per taco):
Chop and trim meat – 30
Chop vegetables – 20
Grill meat – 240
Grill vegetables – 180
Prepare toppings
- Lettuce - 10
- Tomato - 15
- Guacamole - 40
Assemble taco
- Add meat - 5
- Add vegetables - 5
- Add cheese - 5
- Add toppings - 10
Wrap taco - 20
During the lunch hour, Tasty Tim’s encounters demand for 120 tacos.
In an ideal world, how many workers should Tim hire to make tacos?
Chapter 15 Solutions
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Ch. 15 - Prob. 1DQCh. 15 - Prob. 2DQCh. 15 - Prob. 3DQCh. 15 - Prob. 4DQCh. 15 - Prob. 5DQCh. 15 - Prob. 6DQCh. 15 - Prob. 7DQCh. 15 - Prob. 8DQCh. 15 - Prob. 9DQCh. 15 - Prob. 10DQ
Ch. 15 - Prob. 11DQCh. 15 - Prob. 12DQCh. 15 - Prob. 13DQCh. 15 - Prob. 1PCh. 15 - Prob. 2PCh. 15 - Prob. 3PCh. 15 - Prob. 4PCh. 15 - Prob. 5PCh. 15 - Prob. 6PCh. 15 - Prob. 7PCh. 15 - Prob. 8PCh. 15 - Prob. 9PCh. 15 - Prob. 10PCh. 15 - Prob. 15PCh. 15 - Prob. 16PCh. 15 - Prob. 17PCh. 15 - Prob. 18PCh. 15 - Prob. 19PCh. 15 - Prob. 20PCh. 15 - Prob. 21PCh. 15 - Prob. 22PCh. 15 - Prob. 23PCh. 15 - Prob. 26PCh. 15 - Prob. 27PCh. 15 - Prob. 1CSCh. 15 - Prob. 2CSCh. 15 - Prob. 3CSCh. 15 - Prob. 4CSCh. 15 - Prob. 1.1VCCh. 15 - Prob. 1.2VCCh. 15 - Prob. 1.3VCCh. 15 - Prob. 2.1VCCh. 15 - Prob. 2.2VCCh. 15 - Prob. 2.3VCCh. 15 - Prob. 2.4VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Question: Consider the following linear program: Max Z = 2*x + 3*y subject to 3*x + 4*y >= 12 3*x + 2*y >= 9 y>= 1 x,y >= 0 The number of feasible corner points is: 0 1 2 3 None of the other answers are correct.arrow_forwardQUESTION TWO (a) The following tasks are to be completed on vehicles at a service station: To A B с D E F A 139 112 110 132 112 B 139 122 105 109 110 From C 112 122 117 126 108 D 110 105 117 134 111 E 132 109 126 134 118 F 112 110 108 111 118 She plans to start her journey from city A and to return back to this city after visiting all the cities without visiting any city more than once. i. Find the sequence of the cities for her visit programme for minimum total distance travelled. ii. What is the total distance travelled? (b) State the dual of the following and solve the same by the simplex method: Maximize Z=4x₂ + 2x₂ subject to 2x+3x₂ + 5x₂ 22, 3x₁ + x₂ +7x, ≤ 3, x₂ + 4x₂ + 6x₂ ≤5, x₁,x₂20,x, unrestrictedarrow_forwardQUESTION 5 (SCHEDULING: CYCLICAL SCHEDULING) 15.26 Daniel's Barber Shop at Newark Airport is open 7 days a week but has fluctuating demand. Daniel Ball is inter- ested in treating his barbers as well as he can with steady work and preferably 5 days of work with two consecutive days off. His analysis of his staffing needs resulted in the following plan. Schedule Daniel's staff with the minimum number of barbers. DAY MON. TUE. WED. THU. FRI. SAT. SUN. 6 5 5 5 6 4 3 Barbers neededarrow_forward
- Question 6 Tasty Tim’s Tasty Tim’s is a specialty taco restaurant. The following tasks are required for the successful assembly of a Tasty taco (times are in seconds per taco): Chop and trim meat – 30 Chop vegetables – 20 Grill meat – 240 Grill vegetables – 180 Prepare toppings - Lettuce - 10 - Tomato - 15 - Guacamole - 40 Assemble taco - Add meat - 5 - Add vegetables - 5 - Add cheese - 5 - Add toppings - 10 Wrap taco - 20 During the lunch hour, Tasty Tim’s encounters demand for 120 tacos. During off-peak afternoon hours, demand at Tasty Tim’s drops to 40 tacos each hour. How many employees should Tim schedule to work during the afternoon? Again, ignore any effects of idle time or inefficiency due to poor line balancing.arrow_forwardWork teams usually do not have the authority to assign roles within the team. Question 2 options: True Falsearrow_forwardQUESTION 5 A schedule for two processors has been created for the following project which has a finishing time of 30. A(6) B(11) Start C(1) F(5) G(4) D(9) FO ● H(5) E(8) ● Which is the following statements is applicable to the schedule? O A. The schedule is optimal because the finishing time is equal to the critical time. O B. The schedule is optimal because the finishing time is equal to the average time. End ● O C. The schedule is not optimal because the finishing time is greater than the critical time. O D. The schedule is not optimal because the finishing time is greater than the average time. O E. The schedule is not optimal because the finishing time is greater than both the average time and the critical time. O F. The schedule is optimal because the finishing time is less than the critical time. O G. The schedule is optimal because the finishing time is less than the average time. OH. The schedule is not optimal because the finishing time is less than the critical time. OI. The…arrow_forward
- Question one: Suppose a radiology department uses FCFS to determine how to sequence patient x-rays. Assuming these data are representative, compare between FCFS and other scheduling rules should the radiology department be using and why Processing Time (Minutes) Due Time (Minutes from Now) Patient A 35 140 B 15 180 35 360 D 25 290 E 30 420 F 25 20 G 35 180 H 30 290 20 110 K 25 150 L 15 270 M 30 390 20 220 20 400 P 10 330 Q 10 80 R 15 230 20 370arrow_forwardQuestion A.Full explain this question and text typing work only We should answer our question within 2 hours takes more time then we will reduce Rating Dont ignore this line Fastarrow_forwardQuestion: Pistons for automotive engines can be formed either by casting or forging technique. Traditional cast pistons are considered good enough by most engine tuners and builders when it comes to standard setups. They suffer no significant drawback in terms of compression and service life. Performance enthusiasts and custom engine builders prefer the use of forged pistons because they are more durable and easily customised to any configuration, which is essential for engine tuning. Cast pistons are made with the use of large, specialised equipment made up of a mould where the molten aluminium alloy is poured to create the piston shape. Forged pistons employ a single-cast billet of the alloy which is stamped into the required shape using a die. The shape of the die determines the size and shape of the piston. The productivity rates for both methods are different. How do i calculate this?: In this Question, we assume that one unit piston weighs 1.54kg. To calculate the cost per part…arrow_forward
- Question No. 3 Muhammad Khan supervises a group of seven project engineers. His unit is experiencing a heavy workload, as the demand for different versions of one of his firm's computer components is growing. Khan finds that he doesn't have time to follow up on all design details for each version. Up until now he has tried to do this all by himself. Two of the engineers have shown interest in helping him coordinate work on the various designs. As a consultant, how would you advise Khan in terms of delegating work to them?arrow_forwardSpecial Relativity (Time Dilation) Question: According to the theory of special relativity, time dilation means: a) Moving clocks tick faster than stationary ones b) Time slows down for objects moving at high speeds relative to an observer c) Time speeds up as objects move closer to the speed of light d) The time experienced by all observers is the same regardless of their motion.arrow_forwardQuestion one: Suppose a radiology department uses FCFS to determine how to sequence patient x-rays. Assuming these data are representative, compare between FCFS and other scheduling rules should the radiology department be using and why Processing Time (Minutes) Due Time (Minutes from Now) Patient A 35 140 B 180 15 35 360 25 290 E 30 420 25 20 G 35 80 30 290 20 110 K 25 15 150 270 M 30 390 20 220 20 400 10 330 10 80 R 15 230 20 370 当 五犯 LEzlolalolclnarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.