Textbook Question
Chapter 15, Problem 1P
Referring to the product structure diagram for product A, determine:
- a. how many Ks are needed for each A.
- b. how many Es are needed for each A.
- c. the low-level code for item E.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Product M is made of two units of N and two of P. N is made of two units of R and four units of S.
Ris made of one unit of S and three units of T. P is made of two units of T and four units of U.
a. Show the bill-of-materials (product structure tree).
b. If 100 Ms are required, how many units of each component are needed?
c. Show both a single-level parts list and an indented parts list.
Product M is made of two units of N and two of P. N is made of two units of R and four units of S. R is made of one unit of S and three units of T. P is made of two units of T and four units of U.
a. Show the bill-of-materials (product structure tree).
b. If 100 Ms are required, how many units of each component are needed?
c. Show both a single-level parts list and an indented parts list.
Describe how MRP might be used to plan for a change in design for a product
Chapter 15 Solutions
Operations and Supply Chain Management, 9th Edition WileyPLUS Registration Card + Loose-leaf Print Companion
Ch. 15 - Describe a production environment in which MRP...Ch. 15 - Explain with an example the difference between...Ch. 15 - What are the objectives, inputs, and outputs of an...Ch. 15 - How is a master production schedule created, and...Ch. 15 - What is the purpose of phantom bills, K-bills, and...Ch. 15 - What type of information is included in the item...Ch. 15 - Describe cycle counting. How does it improve...Ch. 15 - Describe the MRP process, including netting,...Ch. 15 - What are the inputs to capacity requirements...Ch. 15 - Discuss several assumptions of MRP and how they...
Ch. 15 - Explain how MRP could be applied to (a) the...Ch. 15 - How does MRP differ from ERP? Find a description...Ch. 15 - What are the capabilities of customer relationship...Ch. 15 - What ate the capabilities of supply chain...Ch. 15 - What is PLM? How does it relate to other business...Ch. 15 - Describe how the ERP systems from two different...Ch. 15 - Discuss the scope of ERP and difficulties in...Ch. 15 - Referring to the product structure diagram for...Ch. 15 - Construct a multilevel bill of material for...Ch. 15 - The classic One-Step step stool shown in the next...Ch. 15 - Draw a product structure diagram from the...Ch. 15 - Product A is assembled from two units of S1 and...Ch. 15 - The popular Racer Scooter comes in a variety of...Ch. 15 - Draw a product structure diagram from the bill of...Ch. 15 - Prob. 8PCh. 15 - Use the product structure diagram for item X shown...Ch. 15 - Kids World sells outdoor play equipment for...Ch. 15 - Complete the following MRP matrix for item A:Ch. 15 - Complete the following MRP matrix for Item X....Ch. 15 - Complete the MRP matrix below, then answer the...Ch. 15 - Alpha Corp. (a spinoff of Alpha Beta) makes...Ch. 15 - Just ERP Just Sofas (JS) had begun the year full...Ch. 15 - Just ERP Just Sofas (JS) had begun the year full...Ch. 15 - Just ERP Just Sofas (JS) had begun the year full...Ch. 15 - Just ERP Just Sofas (JS) had begun the year full...
Additional Business Textbook Solutions
Find more solutions based on key concepts
What is precedent, and how does it affect common law?
Business in Action (8th Edition)
4. Figure 1.1 outlines the operations, finance/accounting, and marketing functions of three organizations. Prep...
Operations Management
•• 4.12 Consider the following actual and forecast demand levels for Big Mac hamburgers at a local McDonald’s r...
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Consider the sales data for Computer Success given in Problem 7. Use a 3-month weighted moving average to forec...
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
What is precedent, and how does it affect common law?
Business in Action
The schedule Dr. Barr set up worked well at the clinic where she was a resident. What are some of the reasons w...
Operations Management, Binder Ready Version: An Integrated Approach
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Product A is assembled from two units of S1 and threeunits of S2. S1 is made of one unit of C1, four units of C2,and one unit of C3. S2 is made of three units of C2 and twounits of C3.a. Draw a product structure diagram for product A.b. How many C3’s are needed to fill an order for 100 A’s?c. Assume no inventory on hand, products take one day to assemble, subassemblies take two days and compo-nents take three days. When should an order be re-leased for C3 if the 100 A’s are needed by day 7?arrow_forwardProduct A is assembled from two units of S1 and threeunits of S2. S1 is made of one unit of C1, four units of C2,and one unit of C3. S2 is made of three units of C2 and twounits of C3.a. Draw a product structure diagram for product A.b. How many C3’s are needed to fill an order for 100 A’s?c. Assume no inventory on hand, products take one day toassemble, subassemblies take two days and components take three days. When should an order be released for C3 if the 100 A’s are needed by day 7?arrow_forwardConsider the following product structure (bill of material). One hundred and fifty (150) units of Product A are needed in week 10. Assuming no on-hand inventory of A exists, explode the bill of material, and use the following information to construct a net requirements plan for all the items. You must use the template provided by the instructor and provide all the information needed on the template. There are no scheduled receipts for all the items. Item On-hand Inventory Lead time (weeks) A 0 2 B 20 2 C 10 1 D 0 3 E 5 1 F 10 3 Item: LT= 1 2 3 4 5 6 7 8 9 10 11 12 Gross Requirements Scheduled Receipts Projected on Hand Net Requirements…arrow_forward
- As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs, and 4 clamps. The base is assembled from 1 clamp and 1 housing. Each clamp has 1 handle and 2 castings. Each housing has 1 bearing and 2 shafts. There is no inventory on hand. Part 2 a) Design a product structure noting the quantities for each item and show the low-level coding. Match each number in the structure below with the corresponding item. Number Item I Spring Subscript left parenthesis 2 right parenthesisSpring(2) II Housing Subscript left parenthesis 1 right parenthesisHousing(1) III Casting Subscript left parenthesis 2 right parenthesisCasting(2) IV Shaft Subscript left parenthesis 2 right parenthesisShaft(2) Bracket Base(1) Clamp(1) Handle(1) Clamp(4) Bearing(1) Handle(1) Casting(2) IIIIIIIV Part 3 b) Determine the…arrow_forwardAs the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 1 spring, and 3 clamps. The base is assembled from 2 clamp and 1 housing. Each clamp has 1 handle and 1 casting. Each housing has 2 bearing and 2 shaft. There is no inventory on hand. Part 2 a) Design a product structure noting the quantities for each item and show the low-level coding. Match each number in the structure below with the corresponding item. Number Item I Bracket II Spring Subscript left parenthesis 1 right parenthesis III Clamp Subscript left parenthesis 3 right parenthesis IV Bearing Subscript left parenthesis 2 rightarrow_forwardTo address some special requirements, the is given by private companies for customizing their products and components.arrow_forward
- The following table lists the components needed to assemble an end item. Assume there is no on-hand inventories. Item Direct Components End item A(4), B(5), C(4) A E(3), F(2) B D(3), E(5) C F(4) D E F E(4) If 3 units of the end item are to be assembled, how many units of component E are needed? Input should be an exact number.arrow_forwardHow to make an IPO chart (Input, Process, Output) for grading individual tests for 3 sections of a course- average in each class, average of 3 sections, calc curve, and applying to each class.arrow_forwardWhich core process includes the activities required to produce and deliver the service or product to the external customer? A. supplier relationship process B. order fulfillment process C. customer relationship process D. new service/product development processarrow_forward
- Bill of material (BOM) details all the sub-component, material, and parts used to make one product. There is a dinner party at your home of a few guests, and you are managing your kitchen. Develop a BOM of any main dish (main course) of your own choice in a tree format. (Hint: Select number of people that will be served with dinner and quantity of that main course to be prepared in appropriate units) Let us assume that you are managing the complete food for dinner, and the food will be served at 9:00 PM sharp. You have decided to serve one main course item, as mentioned in the previous part (a), one sweet dish of your choice, and salad. Prepare a lead-time tree for your complete project and explain the total lead-time from start preparation to serving the dinner for your guests. Secondly, what is the latest time you must start preparing your dinner?arrow_forwardThe documents that assist production, once the product is ready tolaunch into the market are:a) An assembly drawingb) The assembly chartc) The route sheetd) The work ordere) Engineering change notices (ECNs)f) Value analysis reviewg) All of the aboveh) Only (a) – (e)arrow_forward2arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY