Textbook Question
Chapter 15, Problem 9P
Use the product structure diagram for item X shown below to determine:
- a. how many E’s are needed for each X.
- b. how many F’s are needed for each X.
- c. the LLC for item E.
- d. the LLC for item F.
- e. how many of each lower-level items (B through I) are needed to rill an order for 50 Xs.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Draw an approximate bill-of-materials (BOM) for a kid’s toy of your choice following these requirements: I would like to use the Jollibee plush Bee toy.
(a) clearly label the end item and each component,
(b) the BOM must contain no more than 20 items,
(c) the BOM must contain at least three levels (you may count the end-item level zero).
Heather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week 8. Subscripts indicate quantity required for each parent. Assume lot-for-lot ordering.
b. Choose correct time phased-structures
c. Develop a net material requirements plan for F (enter your responses as whole numbers).
Product A consists of two units of Subassembly B, three units of C, and one unit of D. B is composed of four units of E and three units of F. C is made of two units of H and three units of D. H is made of five units of E and two units of G.a. Construct a simple bill-of-materials (product structure tree).b. Construct a product structure tree using low-level coding.c. Construct an indented parts list.d. To produce 100 units of A, determine the number of units of B, C, D, E, F, G, and H required.
Chapter 15 Solutions
Operations and Supply Chain Management, 9th Edition WileyPLUS Registration Card + Loose-leaf Print Companion
Ch. 15 - Describe a production environment in which MRP...Ch. 15 - Explain with an example the difference between...Ch. 15 - What are the objectives, inputs, and outputs of an...Ch. 15 - How is a master production schedule created, and...Ch. 15 - What is the purpose of phantom bills, K-bills, and...Ch. 15 - What type of information is included in the item...Ch. 15 - Describe cycle counting. How does it improve...Ch. 15 - Describe the MRP process, including netting,...Ch. 15 - What are the inputs to capacity requirements...Ch. 15 - Discuss several assumptions of MRP and how they...
Ch. 15 - Explain how MRP could be applied to (a) the...Ch. 15 - How does MRP differ from ERP? Find a description...Ch. 15 - What are the capabilities of customer relationship...Ch. 15 - What ate the capabilities of supply chain...Ch. 15 - What is PLM? How does it relate to other business...Ch. 15 - Describe how the ERP systems from two different...Ch. 15 - Discuss the scope of ERP and difficulties in...Ch. 15 - Referring to the product structure diagram for...Ch. 15 - Construct a multilevel bill of material for...Ch. 15 - The classic One-Step step stool shown in the next...Ch. 15 - Draw a product structure diagram from the...Ch. 15 - Product A is assembled from two units of S1 and...Ch. 15 - The popular Racer Scooter comes in a variety of...Ch. 15 - Draw a product structure diagram from the bill of...Ch. 15 - Prob. 8PCh. 15 - Use the product structure diagram for item X shown...Ch. 15 - Kids World sells outdoor play equipment for...Ch. 15 - Complete the following MRP matrix for item A:Ch. 15 - Complete the following MRP matrix for Item X....Ch. 15 - Complete the MRP matrix below, then answer the...Ch. 15 - Alpha Corp. (a spinoff of Alpha Beta) makes...Ch. 15 - Just ERP Just Sofas (JS) had begun the year full...Ch. 15 - Just ERP Just Sofas (JS) had begun the year full...Ch. 15 - Just ERP Just Sofas (JS) had begun the year full...Ch. 15 - Just ERP Just Sofas (JS) had begun the year full...
Additional Business Textbook Solutions
Find more solutions based on key concepts
What is precedent, and how does it affect common law?
Business in Action (8th Edition)
4. Figure 1.1 outlines the operations, finance/accounting, and marketing functions of three organizations. Prep...
Operations Management
Create an Excel spreadsheet on your own that can make combination forecasts for Problem 18. Create a combinatio...
Operations Management: Processes and Supply Chains (11th Edition)
Define the terms total quality management, just-in-time, and reengineering. What do these terms have in common?
Operations Management, Binder Ready Version: An Integrated Approach
Create an Excel spreadsheet on your own that can make combination forecasts for Problem 18. Create a combinatio...
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
The best fits using exponential smoothing, trend analysis, and linear regression for the given data. Introducti...
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Maria wants to look into additional lists that could be suitable for her customers' requirements. Which three lists will she discover in the All lists window?arrow_forwarda. Given the following master schedule, fill in the projected available and availableto promise rows: b. A customer wants an order of 100 in period 4. What can you tell him?c. The customer from part (b) cancels his request, but then says he wants 120 in period 5.What do you tell him now?d. Sales has requested that you add an MPS of 200 in period 9 to cover their needs fora sales promotion. What do you tell them and why?e. What action (if any) should be taken in period 11? Why is it okay to take theaction?arrow_forwardProduct A is assembled from two units of S1 and threeunits of S2. S1 is made of one unit of C1, four units of C2,and one unit of C3. S2 is made of three units of C2 and twounits of C3.a. Draw a product structure diagram for product A.b. How many C3’s are needed to fill an order for 100 A’s?c. Assume no inventory on hand, products take one day to assemble, subassemblies take two days and compo-nents take three days. When should an order be re-leased for C3 if the 100 A’s are needed by day 7?arrow_forward
- Product A is assembled from two units of S1 and threeunits of S2. S1 is made of one unit of C1, four units of C2,and one unit of C3. S2 is made of three units of C2 and twounits of C3.a. Draw a product structure diagram for product A.b. How many C3’s are needed to fill an order for 100 A’s?c. Assume no inventory on hand, products take one day toassemble, subassemblies take two days and components take three days. When should an order be released for C3 if the 100 A’s are needed by day 7?arrow_forwardProduct A is an end item and is made from two units of B and four of C. B is made ofthree units of D and two of E. C is made of two units of F and two of E.A has a lead time of one week. B, C, and E have lead times of two weeks, and D andF have lead times of three weeks.a. Show the bill-of-materials (product structure tree).b. If 100 units of A are required in Week 10, develop the MRP planning schedule, specifyingwhen items are to be ordered and received. There are currently no units of inventoryon hand.arrow_forwardMRP II stands for:a) material resource planning.b) management requirements planning.c) management resource planning.d) material revenue planning.e) material risk planning.arrow_forward
- For the Toy Car table above, what are the Planned Order Receipts in the week of 8/31? For the Toy Car table above, what are the Planned Order Releases in the week of 9/21? For the Wheel Assembly table above, what are the Gross Requirements in the week of 9/7? For the Wheel Assembly table above, what is the Projected On-Hand Inventory in the week of 8/31? For the Wheel Assembly table above, what are the Net Requirements in the week of 8/24? For the Axle table above, what are the Gross Requirements in the week of 9/7? For the Axle table above, what are the Gross Requirements in the week of 9/14? For the Axle table above, what are the Planned Order Releases in the week of 8/17?arrow_forwardK The demand for subassembly S is 130 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 2 units of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 1 unit of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z. Click the icon to view the product structure and the time-phased product structure. Click the icon to view the on-hand inventory. Suppose that in addition to 130 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are needed for maintenance purposes. These units are needed in week 6. Additionally, a new order has been received for 80 units of S due in week 8. Modify the net material requirements plan to reflect these changes. Construct a new net material requirements plan (enter your responses as whole numbers).…arrow_forwardCan you assist me with Problem 7 errors. Thank you greatlyarrow_forward
- What considerations should be weighed when deciding whether to use a job order cost system or a process cost system under some particular production scenario?arrow_forward6) Product M is made of 2 units of N & 3 of P. N is made of 2 units of R & 4 units of S. R is made of 1 unit of S & 3 units of T. P is made of 2 units of T & 4 units of U. LT are 1 week except for level 2 items which is 2 weeks. On hand are: P = 50 and S = 125 units. a) Show the product structure tree. b) If 100 M are required at the start of week 7, develop a planning schedule showing when each item should be ordered and in what quantity? Use lot for lot except for R & U which uses multiples of 250.arrow_forwardSolution for Material Requirement Planningarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY