Chapter 15, Problem 13P
Complete the following MRP matrix for Item X. Determine when orders should be released and the size of those orders.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Use the following MRP record to answer the question.
Item: LMN
Description:
Gross
requirements.
Scheduled
receipts
Projected
on hand
Date
Planned
receipts
30
Planned order
releases
Which one of the statements concerning item LMN is TRUE?
O A. The projected on - hand inventory in week 8 is 70 units.
B. The scheduled receipt of 80 units in week 3 should be expedited so that it is finished in week 2.
OC. The planned order release quantity in week 3 is 80 units.
O D. The planned receipt quantity in week 6 is 30 units.
1 2 3
60
80
4
Lot Size 80 units
Lead Time: 3 weeks
5
30
30
80
Discuss the meaning of MRP terms such as planned order release and the scheduled order receipt.
As an approach to inventory management, how does MRP differ from the approach taken, dealing witheconomic order quantities (EOQs)?
Chapter 15 Solutions
Operations and Supply Chain Management, 9th Edition WileyPLUS Registration Card + Loose-leaf Print Companion
Ch. 15 - Describe a production environment in which MRP...Ch. 15 - Explain with an example the difference between...Ch. 15 - What are the objectives, inputs, and outputs of an...Ch. 15 - How is a master production schedule created, and...Ch. 15 - What is the purpose of phantom bills, K-bills, and...Ch. 15 - What type of information is included in the item...Ch. 15 - Describe cycle counting. How does it improve...Ch. 15 - Describe the MRP process, including netting,...Ch. 15 - What are the inputs to capacity requirements...Ch. 15 - Discuss several assumptions of MRP and how they...
Ch. 15 - Explain how MRP could be applied to (a) the...Ch. 15 - How does MRP differ from ERP? Find a description...Ch. 15 - What are the capabilities of customer relationship...Ch. 15 - What ate the capabilities of supply chain...Ch. 15 - What is PLM? How does it relate to other business...Ch. 15 - Describe how the ERP systems from two different...Ch. 15 - Discuss the scope of ERP and difficulties in...Ch. 15 - Referring to the product structure diagram for...Ch. 15 - Construct a multilevel bill of material for...Ch. 15 - The classic One-Step step stool shown in the next...Ch. 15 - Draw a product structure diagram from the...Ch. 15 - Product A is assembled from two units of S1 and...Ch. 15 - The popular Racer Scooter comes in a variety of...Ch. 15 - Draw a product structure diagram from the bill of...Ch. 15 - Prob. 8PCh. 15 - Use the product structure diagram for item X shown...Ch. 15 - Kids World sells outdoor play equipment for...Ch. 15 - Complete the following MRP matrix for item A:Ch. 15 - Complete the following MRP matrix for Item X....Ch. 15 - Complete the MRP matrix below, then answer the...Ch. 15 - Alpha Corp. (a spinoff of Alpha Beta) makes...Ch. 15 - Just ERP Just Sofas (JS) had begun the year full...Ch. 15 - Just ERP Just Sofas (JS) had begun the year full...Ch. 15 - Just ERP Just Sofas (JS) had begun the year full...Ch. 15 - Just ERP Just Sofas (JS) had begun the year full...
Additional Business Textbook Solutions
Find more solutions based on key concepts
The following gives the number of paints of type B blood used at Woodlawn Hospital in the past 6 weeks. a. Fore...
Operations Management
•• 3.14 Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with t...
Operations Management: Sustainability and Supply Chain Management (12th Edition)
The best fits using exponential smoothing, trend analysis, and linear regression for the given data. Introducti...
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Create an Excel spreadsheet on your own that can make combination forecasts for Problem 18. Create a combinatio...
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
The schedule Dr. Barr set up worked well at the clinic where she was a resident. What are some of the reasons w...
Operations Management, Binder Ready Version: An Integrated Approach
Create an Excel spreadsheet on your own that can make combination forecasts for Problem 18. Create a combinatio...
Operations Management: Processes and Supply Chains (11th Edition)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Demonstrate how an ERP system can be used to enhance the estimation and interpretation of output metrics.arrow_forwardIn the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank-be certain to enter "0" wherever required.) ITEM 3 Gross requirements On-hand Net requirements Planned order receipt Planned order release Period Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases WEEK NUMBER 2 3 76 4 48 76 5 72 48 72arrow_forwardUse the following partially completed MRP record to answer the question. Item: XYZ Lot Size: L4L; ;EAD Time: 1 week Date 1 2 3 4 5 6 7 8 20 30 50 40 20 Scheduled Receipts Projected on Hand (80) Planned Receipts Planned Order Release What are the quantities of planned order releases for item XYZ for the first six weeks (weeks 1, 2, 3, 4, 5, and 6)?arrow_forward
- Examine the main components of an ERP system for a manufacturing company.arrow_forwardDevelop a material requirements plan for component H. Lead times for the end item and each component except B are one week. The lead time for B is three weeks. Sixty units of A are needed at the startof week 8. There are currently 15 units of B on hand and 130 of E on hand, and 50 units of H are inproduction and will be completed by the start of week 2. Lot-for-lot ordering will be used for all items.arrow_forwardExplain Four (4) main drawbacks of a traditional Material Requirements Planning (MRP) scheduling system. In your explanation include how these drawbacks improved with the development of the MRP II system?arrow_forward
- Jenny Malone works for the Columbus based Cummins Diesel Engine company. Jenny works in the production scheduling department and she is developing an MRP planning schedule for Item J. Please assist Jenny by developing the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. The lead time is one week. (Leave no cells blank - be certain to enter "0" in all open cells as required.) ITEM J Gross requirements On hand Net requirements Planned order receipt Planned order release Item J LT=1 Q = L4L 0 32 Period Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases 1 WEEK NUMBER 2 3 76 4 48 5 72 2 76 3 48 72arrow_forwardExamine and contrast MRP with order-point methods.arrow_forwardDiscuss the ERP lifecycle in detail?arrow_forward
- The bid process requires a set of functional criteria that are well-defined and documented. Even if a bid isn't required, explain why this is useful when choosing an ERP system.arrow_forwardYou are supposed to find the gross requirements for all of them.arrow_forwardPlease Simply fill out the chart answering the questionarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY