Textbook Question
Chapter 15, Problem 19E
A manufacturing cell within a value stream is structured with four processes and associated processing times (for one unit):
Molding: 6 minutes
Grinding: 5 minutes
Polishing: 5 minutes
Finishing: 4 minutes
How many units can the cell produce per hour (on a continuous running basis)?
- a. 3 units per hour
- b. 12 units per hour
- c. 15 units per hour
- d. 10 units per hour
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Consider the below diagram showing production process of Company XYZ:
Process A
1.25/hour
Process B
2.75/hour
Process C
Process D
0.5/ minute
3.25/ hour
What will be the rate of the production for the company?
a) 1.25 per hour
b) 3.25 per hour
c) 7.75 per hour
d) 30 per hour
(Chapter 4: Process Improvement) Consider a process consisting of three resources. Assume the
demand rate is 8 units/hour.
The process activities are always performed in the following sequence.
Resource 1 has a processing time of 5 minutes per unit.
Resource 2 has a processing time of 4 minutes per unit.
Resource 3 has a processing time of 6 minutes per unit.
Resource 1 is staffed by worker A and A's wage rate is $13 per hour.
Resource 2 is staffed by worker B and B's wage rate is $13 per hour.
Resource 3 is staffed by worker C and C's wage rate is $20 per hour.
If one additional worker could be hired, to which resource should this worker be assigned?
Calculate the new process capacity in units/hr.
O Assign the new worker to Resource 3. The process capacity is 12 units per hour.
O Assign the new worker to Resource 3. The process capacity is 10 units per hour.
O Assign the new worker to Resource 1. The process capacity is 20 units per hour.
O Assign the new worker to Resource 2. The…
The assembly-line activities are given as follows for the manufacturing of a product:
Performance
Time (mins)
Performance
Time (mins)
6
4
5
3
Task
A
B
с
D
Predecessors
A
B
B
Task
E
F
G
H
524 2
Predecessors
C
с
D, E, F
G
For a given 7-minute cycle time after allowances, the theoretical minimum number of workstations =
(round your response to the immediate higher whole number).
Chapter 15 Solutions
Cornerstones of Cost Management (Cornerstones Series)
Ch. 15 - Prob. 1DQCh. 15 - What are the five principles of lean thinking?Ch. 15 - Prob. 3DQCh. 15 - Prob. 4DQCh. 15 - Explain how lean manufacturing is able to produce...Ch. 15 - What role does a demand-pull system have on lean...Ch. 15 - Prob. 7DQCh. 15 - Prob. 8DQCh. 15 - What is the purpose of assigning facility costs to...Ch. 15 - Why are units shipped used to calculate the...
Ch. 15 - When will the average unit cost be useful for...Ch. 15 - Explain why changes in value-stream profitability...Ch. 15 - Prob. 13DQCh. 15 - Prob. 14DQCh. 15 - What is productivity measurement?Ch. 15 - Prob. 16DQCh. 15 - Prob. 17DQCh. 15 - Discuss the advantages and disadvantages of...Ch. 15 - Prob. 19DQCh. 15 - Prob. 20DQCh. 15 - What is profit-linked productivity measurement and...Ch. 15 - Prob. 22DQCh. 15 - What is the price-recovery component?Ch. 15 - Anderson Company has the following departmental...Ch. 15 - During the week of June 12, Harrison Manufacturing...Ch. 15 - In 20x2, Choctaw Company implements a new process...Ch. 15 - Refer to Cornerstone Exercise 15.3. Choctaw...Ch. 15 - Prob. 5ECh. 15 - Bienestar Inc., has the following departmental...Ch. 15 - Bienestar, Inc., implemented cellular...Ch. 15 - Henderson, Inc., has just created five order...Ch. 15 - Prob. 9ECh. 15 - Shorts Manufacturing, Inc., has implemented lean...Ch. 15 - The following Box Scorecard was prepared for a...Ch. 15 - Prob. 12ECh. 15 - Carsen Company produces handcrafted pottery that...Ch. 15 - Helena Company needs to increase its profits and...Ch. 15 - Helena Company needs to increase its profits and...Ch. 15 - Prob. 16ECh. 15 - Lean manufacturing is characterized by all but one...Ch. 15 - Lean manufacturing uses value streams to produce a...Ch. 15 - A manufacturing cell within a value stream is...Ch. 15 - Total productive efficiency is achieved when both...Ch. 15 - The following information is given for a...Ch. 15 - Sixty employees (all CPAs) of a local public...Ch. 15 - Sixty employees (all CPAs) of a local public...Ch. 15 - Bradford Company, a manufacturer of small tools,...Ch. 15 - Continuous improvement is the governing principle...Ch. 15 - Prob. 26PCh. 15 - Jadlow Company produces handcrafted leather...Ch. 15 - Prob. 28P
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- A manufacturing cell within a value stream has three processes and the following associated processing times: Drilling: 12 minutes Inserting: 6 minutes Finishing: 2 minutes How many units can the cell produce per hour (on a continuous running basis)? a. 10 units per hour b. 3 units per hour c. 5 units per hour d. 30 units per hourarrow_forwardBased on the attached image, compute the manufacturing cycle efficiency based on below data (to the nearest whole percentage)arrow_forwardDuring the most recent month at Schwab Corporation, queue time was 10.6 days, inspection time was 1.7 day, process time was 2.7 days, wait time was 12.5 days, and move time was 3.5 day. Required: a. Compute the throughput time. b. Compute the manufacturing cycle efficiency (MCE). c. What percentage of the production time is spent in non-value-added activities? d. Compute the delivery cycle time. a. Throughput time b. MCE c. Percentage of non-value-added activities d. Delivery cycle time days % % daysarrow_forward
- A company produces two products, A and B, that go through a three-step sequence of fabrication, assembly, and packaging. Processing requirements for the departments (hours per unit) are: Product B Day A Department capacities are all 7 hours per day. The following production schedule is for the next three days: Mon Tues 5 4 3 Job Start Day Mon Fabrication 1.0 1.5 Tue Wed Wed 3 a. Develop, for each department and day, the capacity requirements for each product and the total load for each day. Ignore changeover time between A and B. Evaluate the projected loads for each day. (Round the final answers to 1 decimal place.) O No O Yes 1 Product B Assembly 1.0 1.0 A b. is the schedule feasible? Packaging 1.0 2.0 Fabrication Labor Assembly Labor Packaging Laborarrow_forwardMello Manufacturing Company is a diversified manufacturer that manufactures three products (Alpha, Beta, and Omega) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities Activity-Based Product Costing of the organization as follows: Activity Cost Pool Activity $259,200 Production Setup 55,000 Materials handling 9,750 Inspection 60,000 Product engineering 123,200 Total $507,150 The activity bases identified for each activity are as follows: Activity Activity Base Production Machine hours Setup Number of setups Materials handling Number of parts Inspection Product engineering Number of inspection hours Number of engineering hours he activity-base usage quantities and units produced for the three products were determined from corporate records and are as follows: Number of Number of Previous Nextarrow_forwardQuetion: Calculate the required total labor hours, if there are 5,000 units produced and 2.5 units are produced per labor.arrow_forward
- Use the following information for Exercises 5-44 through 5-46: The following six situations at Diviney Manufacturing Inc. are independent. a. A manual insertion process takes 30 minutes and 8 pounds of material to produce a product. Automating the insertion process requires 15 minutes of machine time and 7.5 pounds of material. The cost per labor hour is 12, the cost per machine hour is 8, and the cost per pound of materials is 10. b. With its original design, a gear requires 8 hours of setup time. By redesigning the gear so that the number of different grooves needed is reduced by 50%, the setup time is reduced by 75%. The cost per setup hour is 50. c. A product currently requires 6 moves. By redesigning the manufacturing layout, the number of moves can be reduced from 6 to 0. The cost per move is 20. d. Inspection time for a plant is 16,000 hours per year. The cost of inspection consists of salaries of 8 inspectors, totaling 320,000. Inspection also uses supplies costing 5 per inspection hour. The company eliminated most defective components by eliminating low-quality suppliers. The number of production errors was reduced dramatically by installing a system of statistical process control. Further quality improvements were realized by redesigning the products, making them easier to manufacture. The net effect was to achieve a close to zero-defect state and eliminate the need for any inspection activity. e. Each unit of a product requires 6 components. The average number of components is 6.5 due to component failure, requiring rework and extra components. Developing relations with the right suppliers and increasing the quality of the purchased component can reduce the average number of components to 6 components per unit. The cost per component is 500. f. A plant produces 100 different electronic products. Each product requires an average of 8 components that are purchased externally. The components are different for each part. By redesigning the products, it is possible to produce the 100 products so that they all have 4 components in common. This will reduce the demand for purchasing, receiving, and paying bills. Estimated savings from the reduced demand are 900,000 per year. 5-44 Nonvalue-Added Costs Refer to the information for Diviney Manufacturing on the previous page. Required: Estimate the nonvalue-added cost for each situation.arrow_forwardHart Manufacturing makes three products. Each product requires manufacturing operations in three departments: A, B, and C. The labor-hour requirements, by department, are as follows: During the next production period the labor-hours available are 450 in department A, 350 in department B, and 50 in department C. The profit contributions per unit are 25 for product 1, 28 for product 2, and 30 for product 3. a. Formulate a linear programming model for maximizing total profit contribution. b. Solve the linear program formulated in part (a). How much of each product should be produced, and what is the projected total profit contribution? c. After evaluating the solution obtained in part (b), one of the production supervisors noted that production setup costs had not been taken into account. She noted that setup costs are 400 for product 1, 550 for product 2, and 600 for product 3. If the solution developed in part (b) is to be used, what is the total profit contribution after taking into account the setup costs? d. Management realized that the optimal product mix, taking setup costs into account, might be different from the one recommended in part (b). Formulate a mixed-integer linear program that takes setup costs provided in part (c) into account. Management also stated that we should not consider making more than 175 units of product 1, 150 units of product 2, or 140 units of product 3. e. Solve the mixed-integer linear program formulated in part (d). How much of each product should be produced and what is the projected total profit contribution? Compare this profit contribution to that obtained in part (c).arrow_forwardUse the following information for Exercises 5-44 through 5-46: The following six situations at Diviney Manufacturing Inc. are independent. a. A manual insertion process takes 30 minutes and 8 pounds of material to produce a product. Automating the insertion process requires 15 minutes of machine time and 7.5 pounds of material. The cost per labor hour is 12, the cost per machine hour is 8, and the cost per pound of materials is 10. b. With its original design, a gear requires 8 hours of setup time. By redesigning the gear so that the number of different grooves needed is reduced by 50%, the setup time is reduced by 75%. The cost per setup hour is 50. c. A product currently requires 6 moves. By redesigning the manufacturing layout, the number of moves can be reduced from 6 to 0. The cost per move is 20. d. Inspection time for a plant is 16,000 hours per year. The cost of inspection consists of salaries of 8 inspectors, totaling 320,000. Inspection also uses supplies costing 5 per inspection hour. The company eliminated most defective components by eliminating low-quality suppliers. The number of production errors was reduced dramatically by installing a system of statistical process control. Further quality improvements were realized by redesigning the products, making them easier to manufacture. The net effect was to achieve a close to zero-defect state and eliminate the need for any inspection activity. e. Each unit of a product requires 6 components. The average number of components is 6.5 due to component failure, requiring rework and extra components. Developing relations with the right suppliers and increasing the quality of the purchased component can reduce the average number of components to 6 components per unit. The cost per component is 500. f. A plant produces 100 different electronic products. Each product requires an average of 8 components that are purchased externally. The components are different for each part. By redesigning the products, it is possible to produce the 100 products so that they all have 4 components in common. This will reduce the demand for purchasing, receiving, and paying bills. Estimated savings from the reduced demand are 900,000 per year. 5-45 Driver Analysis Refer to the information for Diviney Manufacturing on the previous page. Required: CONCEPTUAL CONNECTION For each situation, identify the possible root cause(s) of the activity cost (such as plant layout, process design, and product design).arrow_forward
- A manufacturing cell produces 40 units in five hours. What is the cycle time for the manufacturing cell? a. 8 units per hour b. 8 hours per unit c. 1/8 unit per hour d. 7.5 minutes per unitarrow_forwardBienestar Inc., has the following departmental structure for producing a well-known multivitamin: A consultant designed the following cellular manufacturing structure for the same product: The times above the processes represent the time required to process one unit of product. Required: 1. Calculate the time required to produce a batch of 15 bottles using a batch-processing departmental structure. 2. Calculate the time to process 15 units using cellular manufacturing. 3. How much manufacturing time will the cellular manufacturing structure save for a batch of 15 units?arrow_forwardK-Briggs Company uses the FIFO method to account for the costs of production. For Crushing, the first processing department, the following equivalent units schedule has been prepared: The cost per equivalent unit for the period was as follows: The cost of beginning work in process was direct materials, 40,000; conversion costs, 30,000. Required: 1. Determine the cost of ending work in process and the cost of goods transferred out. 2. Prepare a physical flow schedule.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningManagerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage LearningPrinciples of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax College
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,Essentials of Business Analytics (MindTap Course ...StatisticsISBN:9781305627734Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. AndersonPublisher:Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
Essentials of Business Analytics (MindTap Course ...
Statistics
ISBN:9781305627734
Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:Cengage Learning
Cost Accounting - Definition, Purpose, Types, How it Works?; Author: WallStreetMojo;https://www.youtube.com/watch?v=AwrwUf8vYEY;License: Standard YouTube License, CC-BY