Concept explainers
a)
To determine: Thesequence of jobs that are based on decision rule First Come First Served (FCFS).
Introduction: First Come First Served is the
b)
To determine: The sequence of jobs based on decision rule Shortest Processing Time (SPT).
Introduction: Shortest Processing Tine is the scheduling rule, which helps to arrange the sequence in the order. Here, job with the shortest duration would be served first. Then, the process would go on from the shortest to largest duration.
c)
To determine: The sequence of jobs based on decision rule Longest Processing Time (LPT).
Introduction: Largest Processing Tine is the scheduling rule, which helps to arrange the sequence in the order. Here, job with the largest duration would be served first. Then, the process would go on from the largest to shortest duration.
d)
To determine: The sequence of jobs based on decision rule Earliest Due Date (EDD).
Introduction: Earliest Due Date is the scheduling rule, which helps to arrange the sequence in the order. Here, job with the earliest due date would be served first. Then, the process would go on from the earliest due date to latest due date.
e)
To determine: The sequence of jobs based on critical ratio.
Introduction: Critical ratio is kind of scheduling rule that helps to identify that, the task or job is on the correct track. It would help to identify if the task is behind or ahead of the schedule.
Want to see the full answer?
Check out a sample textbook solutionChapter 15 Solutions
EP PRIN.OF OPERATIONS MGMT.-MYOMLAB
- QUESTION 6 The framing department has six jobs waiting to be processed as shown in Table 3 below. It is now time zero and all jobs are ready to begin. Each has only one operation remaining. Table 3 Jobs (In order of arrival) Processing Time Due Date A 5 12 B 7 18 C 8. 14 D 3 10 E 9 22 F 12 17 Using minimum flow time as the evaluation criterion, recommend the best rule to sequence the jobs from the list below: i. FCFS ii. SOT iii. EDD iv. STRarrow_forwardQuestion 4: Six jobs waiting at a workstation will be processed in order, starting with the one with the shortest break time. In the table below, the time elapsed since the arrival of the works, the time remaining to the delivery and the processing time are given. According to this, create the work order and fill in the data in the relevant table.(fill in the second table in the photos)a) What is the average delay time with the generated order?b) How many hours is the average flow time?c) How many jobs will be delayed?d) How many jobs will not be delayed?arrow_forwardQuestion 1) Scheduling If the following jobs are sequenced according to the FCFS rule Job Processing Time (days) Due Date A 8 12 B 6 15 C 11 17 D 5 10 E 3 8 What is the mean tardiness (in days) for all jobs? What is the mean completion time in days for all jobs? What is the maximum job tardiness (in days)arrow_forward
- Question 1: the following table contains information concerning four jobs that are awaiting processing at a work center. Job Time Due Date Job A (Days) 15 (Days) 21 7 15 16 10 17 a. Sequence the jobs using (1) First come, first served, (2) Shortest processing time, (3) Earliest due date, and (4) Critical ratio. ASsume the list is by order of arrival. b. For each of the methods in part a, determine (1) the average job flow time, (2) the average tardiness, and (3) the average number of jobs at the work center. c. Is one method superior to the others?arrow_forwardQuestion 3 of 19 The following table contains information concerning four jobs that are awaiting processing at a work center. Job Time Due date (days) (days) 14 10 7 6 Job A B C D Determine the average flow time using the EDD rule. Select the correct response: 20 20.5 19.75 21 20 16 15 17 ProviQUSarrow_forwardQuestion 34 Consider the processing times and priorities for four jobs: Job Processing time (minutes) Weight/Priority (cost per minute) A 10 6 B 2 1 C 50 2 D 16 10 Assume the weighted shortest processing time (WSPT) rule is used. Which job should be processed third? Group of answer choices A B C Darrow_forward
- QUESTION 5 (SCHEDULING: CYCLICAL SCHEDULING) 15.26 Daniel's Barber Shop at Newark Airport is open 7 days a week but has fluctuating demand. Daniel Ball is inter- ested in treating his barbers as well as he can with steady work and preferably 5 days of work with two consecutive days off. His analysis of his staffing needs resulted in the following plan. Schedule Daniel's staff with the minimum number of barbers. DAY MON. TUE. WED. THU. FRI. SAT. SUN. 6 5 5 5 6 4 3 Barbers neededarrow_forwardQuestion 32 The processing times of four jobs are given as follows: Job Processing time (minutes) A 10 B 30 C 16 D 24 Assume the jobs arrived in alphabetical order of the job name and no other job arrives in the next 70 minutes. What is the average flow time in minutes if the jobs are processed in shortest processing time (SOP) order? Group of answer choices 166 41.5 38 20.5arrow_forwardAllocate the tasks to workstations taking into consideration the precedence requirements and using the LOT rule to break ties between feasible tasks.arrow_forward
- Question 35 Consider the processing times and due dates of the following jobs: Job Processing time (days) Due date (days) 1 3 29 2 19 25 3 24 40 4 8 20 What is the average lateness if the earliest due date (EDD) is used to sequence the jobs? Group of answer choices 0.75 1.25 4.25 5.67arrow_forwardQuestion attachedarrow_forwardQuestion E only.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.