EBK PRINCIPLES OF OPERATIONS MANAGEMENT
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
11th Edition
ISBN: 9780135175644
Author: Munson
Publisher: VST
bartleby

Concept explainers

Question
Book Icon
Chapter 14, Problem 13P

a)

Summary Introduction

To construct: A product structure.

Introduction:

Product structure:

The product structure is a visual representation of the components needed for a product assembly and the sequence at which they must be developed. It will clearly depict the parents and children components at each level.

a)

Expert Solution
Check Mark

Answer to Problem 13P

Product structure:

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 14, Problem 13P , additional homework tip  1

Explanation of Solution

Given information:

  • 1000 20” fans due in week 7.
  • Each fan is made of a housing assembly, two grills, fan assembly and an electrical unit.
  • Housing assembly is made of frame, two supports, and a handle.
  • Fan assembly is made up of a hub and five blades.
  • Electrical unit consists of a motor, switch and a knob.
Component Lead time On-hand inventory Lot size Scheduled receipt
20" Fan 1 100
Housing 1 100
Frame 2
Supports (2) 1 50 100
Handle 1 400 500
Grills (2) 2 200 500
Fan assembly 3 150
Hub 1
Blades (5) 2 100
Electrical unit 1
Motor 1
Switch 1 20 12
Knob 1 25 200 in week 2

Product structure:

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 14, Problem 13P , additional homework tip  2

The product is a 20” fan. It is made of four components. Each fan is made of a housing assembly, two grills, fan assembly and an electrical unit. Housing assembly is made of frame, two supports, and a handle. Fan assembly is made up of a hub and five blades. Electrical unit consists of a motor, switch and a knob.

b)

Summary Introduction

To construct: A time-phased product structure.

Introduction:

Time-phased product structure:

The time-phased product structure will represent the product visually with the details of when each component must begin production. It should be done to ensure that all the components are on time.

b)

Expert Solution
Check Mark

Answer to Problem 13P

Time-phased product structure:

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 14, Problem 13P , additional homework tip  3

Explanation of Solution

Given information:

  • 1000 20” fans due in week 7.
  • Each fan is made of a housing assembly, two grills, fan assembly and an electrical unit.
  • Housing assembly is made of frame, two supports, and a handle.
  • Fan assembly is made up of a hub and five blades.
  • Electrical unit consists of a motor, switch and a knob.
Component Lead time On-hand inventory Lot size Scheduled receipt
20" Fan 1 100
Housing 1 100
Frame 2
Supports (2) 1 50 100
Handle 1 400 500
Grills (2) 2 200 500
Fan assembly 3 150
Hub 1
Blades (5) 2 100
Electrical unit 1
Motor 1
Switch 1 20 12
Knob 1 25 200 in week 2

Time-phased product structure:

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 14, Problem 13P , additional homework tip  4

The end product is the fan which must be ready at week 7. All the other components must be completed on week 6. The components at the lower level must be completed first before proceeding to the higher levels. Each component at each level is begun depending on the lead time of the product.

The products are started in advance so that they are developed and ready on time so that the dependent parent will be ready to develop its product. The process is repeated until all the subassemblies are ready to make the final product.

c)

Summary Introduction

To develop: A net requirements plan.

Introduction:

Net requirements plan:

The net requirements plan is the plan which is established on the gross requirements plan formed by deducting the stock on and the scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.

c)

Expert Solution
Check Mark

Explanation of Solution

Given information:

  • 1000 20” fans due in week 7.
  • Each fan is made of a housing assembly, two grills, fan assembly and an electrical unit.
  • Housing assembly is made of frame, two supports, and a handle.
  • Fan assembly is made up of a hub and five blades.
  • Electrical unit consists of a motor, switch and a knob.
Component Lead time On-hand inventory Lot size Scheduled receipt
20" Fan 1 100
Housing 1 100
Frame 2
Supports (2) 1 50 100
Handle 1 400 500
Grills (2) 2 200 500
Fan assembly 3 150
Hub 1
Blades (5) 2 100
Electrical unit 1
Motor 1
Switch 1 20 12
Knob 1 25 200 in week 2

Net requirements plan:

20’’ Fan:

Week
20" Fan 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 1,000
Scheduled  receipt
On hand (100) 100
Net requirement 900
Planned order receipt 900
Planned order release 900

Week 7:

The gross requirement is 1,000 (1 assembly). The on hand inventory is 100. Hence, the net requirement is 900. The lead time is 1 week. Therefore, the planned order release will be 900 in week 6 which will be the planned order receipt in week 7.

Housing:

Week
Housing 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 900
Scheduled  receipt
On hand (100) 100
Net requirement 800
Planned order receipt 800
Planned order release 800

Week 6:

The gross requirement is 900 (1 assembly) derived from the planned order release of 20” fan. The on hand inventory is 100. Hence, the net requirement is 800. The lead time is 1 week. Therefore, the planned order release will be 800 in week 5 which will be the planned order receipt in week 6.

Grills:

Week
Grills 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 1,800
Scheduled  receipt
On hand (200) 200 400
Net requirement 1,600
Planned order receipt 2,000
Planned order release 2,000

Week 6:

The gross requirement is 1,800 (2 assembly) derived from the planned order release of 20” fan. The on hand inventory is 200. Hence, the net requirement is 1,600. The lead time is 2 weeks. Therefore, the planned order release will be 2,000 (Lot Size = 500) in week 4 which will be the planned order receipt in week 6. The excess inventory will be available at week 7.

Fan assembly:

Week
Fan assembly 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 900
Scheduled  receipt
On hand (150) 150
Net requirement 750
Planned order receipt 750
Planned order release 750

Week 6:

The gross requirement is 900 (1 assembly) derived from the planned order release of 20” fan. The on hand inventory is 150. Hence, the net requirement is 750. The lead time is 2 weeks. Therefore, the planned order release will be 750 in week 4 which will be the planned order receipt in week 6.

Electrical unit:

Electrical Unit 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 900
Scheduled  receipt
On hand (0) 0
Net requirement 900
Planned order receipt 900
Planned order release 900

Week 6:

The gross requirement is 900 (1 assembly) derived from the planned order release of 20” fan. The on hand inventory is 0. Hence, the net requirement is 900. The lead time is 1 week. Therefore, the planned order release will be 900 in week 5 which will be the planned order receipt in week 6.

Frame:

Frame 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 800
Scheduled  receipt
On hand (0) 0
Net requirement 800
Planned order receipt 800
Planned order release 800

Week 5:

The gross requirement is 800 (1 assembly) derived from the planned order release of Housing. The on hand inventory is 0. Hence, the net requirement is 800. The lead time is 2 weeks. Therefore, the planned order release will be 800 in week 3 which will be the planned order receipt in week 5.

Supports:

Week
Supports 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 1,600
Scheduled  receipt
On hand (50) 50
Net requirement 1,550
Planned order receipt 1,600
Planned order release 1,600

Week 5:

The gross requirement is 1,600 (2 assembly) derived from the planned order release of Housing. The on hand inventory is 50. Hence, the net requirement is 1,550. The lead time is 1 week. Therefore, the planned order release will be 1,600 (Lot size = 100) in week 4 which will be the planned order receipt in week 5. The excess inventory is available at week 6.

Handle:

Week
Handle 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 800
Scheduled  receipt
On hand (400) 400 100
Net requirement 400
Planned order receipt 500
Planned order release 500

Week 5:

The gross requirement is 800 (1 assembly) derived from the planned order release of Housing. The on hand inventory is 400. Hence, the net requirement is 400. The lead time is 1 week. Therefore, the planned order release will be 500 (Lot size = 500) in week 4 which will be the planned order receipt in week 5. The excess inventory is available at week 6.

Hub:

Week
Hub 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 750
Scheduled  receipt
On hand (0) 0
Net requirement 750
Planned order receipt 750
Planned order release 750

Week 3:

The gross requirement is 750 (1 assembly) derived from the planned order release of fan assembly. The on hand inventory is 0. Hence, the net requirement is 750. The lead time is 1 week. Therefore, the planned order release will be 750 in week 2 which will be the planned order receipt in week 3.

Blades:

Week
Blades 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 3,750
Scheduled  receipt
On hand (0) 0 50
Net requirement 3,750
Planned order receipt 3,800
Planned order release 3,800

Week 3:

The gross requirement is 3,750 (5 assembly) derived from the planned order release of fan assembly. The on hand inventory is 0. Hence, the net requirement is 3,750. The lead time is 2 weeks. Therefore, the planned order release will be 3,800 (Lot size = 100) in week 1 which will be the planned order receipt in week 3. The excess inventory will be available at week 4.

Motor:

Week
Motor 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 900
Scheduled  receipt
On hand (0) 0
Net requirement 900
Planned order receipt 900
Planned order release 900

Week 5:

The gross requirement is 900 (1 assembly) derived from the planned order release of Electrical unit. The on hand inventory is 0. Hence, the net requirement is 900. The lead time is 1 week. Therefore, the planned order release will be 900 in week 4 which will be the planned order receipt in week 5.

Switch:

Week
Switch 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 900
Scheduled  receipt
On hand (20) 20 8
Net requirement 880
Planned order receipt 888
Planned order release 888

Week 5:

The gross requirement is 900 (1 assembly) derived from the planned order release of Electrical unit. The on hand inventory is 20. Hence, the net requirement is 880. The lead time is 1 week. Therefore, the planned order release will be 888 (Lot Size = 12) in week 4 which will be the planned order receipt in week 5. The excess inventory will be available at week 6.

Knob:

Week
Knob 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 900
Scheduled  receipt 200
On hand (0) 200 200 200
Net requirement 700
Planned order receipt 700
Planned order release 700

Week 2:

There is a scheduled receipt of 200 which can be used as inventory.

Week 5:

The gross requirement is 900 (1 assembly) derived from the planned order release of Electrical unit. The on hand inventory is 0. But, there is a scheduled receipt of 200. Hence, the net requirement is 7000. The lead time is 1 week. Therefore, the planned order release will be 700 in week 4 which will be the planned order receipt in week 5.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
What are some good examples of bullet points on a resume for a Christian Elementary School?
What is an example of a cover letter for a Christian School Long-Term Substitute Teaching position?
The supply chain is a conventional notion, but organizations are only really interested in making products that they can sell to customers. Provided they have reliable supplies of materials and reasonable transport for finished products, logistics is irrelevant. Do you think this is true? If yes, explain, and if no, clearly explain as well.

Chapter 14 Solutions

EBK PRINCIPLES OF OPERATIONS MANAGEMENT

Ch. 14 - What functions of the firm affect an MRP system?...Ch. 14 - Prob. 11DQCh. 14 - Prob. 12DQCh. 14 - Prob. 13DQCh. 14 - Prob. 14DQCh. 14 - As an approach to inventory management, how does...Ch. 14 - Prob. 16DQCh. 14 - Use the Web or other sources to: a) Find stories...Ch. 14 - Prob. 18DQCh. 14 - Prob. 19DQCh. 14 - You have developed the following simple product...Ch. 14 - You are expected to have the gift bags in Problem...Ch. 14 - Prob. 3PCh. 14 - Your boss at Xiangling Hu Products, Inc., has just...Ch. 14 - The demand for subassembly S is 100 units in week...Ch. 14 - Prob. 6PCh. 14 - Prob. 7PCh. 14 - Prob. 8PCh. 14 - Prob. 9PCh. 14 - Prob. 10PCh. 14 - Prob. 11PCh. 14 - Prob. 12PCh. 14 - Prob. 13PCh. 14 - Prob. 14PCh. 14 - You are product planner for product A (in Problem...Ch. 14 - Prob. 16PCh. 14 - Prob. 17PCh. 14 - Heather Adams, production manager for a Colorado...Ch. 14 - Prob. 19PCh. 14 - Prob. 20PCh. 14 - Prob. 21PCh. 14 - Prob. 22PCh. 14 - Data Table for Problems 14.22 through 14.25 ...Ch. 14 - Develop a POQ solution and calculate total...Ch. 14 - Using your answers for the lot sizes computed in...Ch. 14 - M. de Koster, of Rene Enterprises, has the master...Ch. 14 - Grace Greenberg, production planner for Science...Ch. 14 - Prob. 28PCh. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Courtney Kamauf schedules production of a popular...Ch. 14 - Using the data for the coffee table in Problem...Ch. 14 - Prob. 1CSCh. 14 - Prob. 2CSCh. 14 - Prob. 1.1VCCh. 14 - Prob. 1.2VCCh. 14 - Prob. 1.3VCCh. 14 - Prob. 2.1VCCh. 14 - Prob. 2.2VCCh. 14 - Prob. 2.3VC
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.