Concept explainers
a)
To determine: The change in the items due to the change in the lead time of item G.
Introduction:
Net requirements plan:
The Net requirements plan is the plan which is established on the Gross requirements plan formed by deducting the stock on and the
a)
Answer to Problem 16P
The change will take place only with item G because it has no children. The Lead time of 4 weeks will preempt the Planned order release by 1 one week.
Explanation of Solution
Given information:
- 10 units for service and production department for B and F.
- 10 units of A at week 8.
- Lead time of G has been changed to 4 weeks.
Part | A | B | C | D | E | F | G | H |
On hand | 0 | 2 | 10 | 5 | 4 | 5 | 1 | 10 |
Product structure:
Net requirements plan:
Item A:
Week | ||||||||
Item A | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 10 | |||||||
Scheduled receipt | ||||||||
On-hand (0) | 0 | |||||||
Net requirement | 10 | |||||||
Planned order receipt | 10 | |||||||
Planned order release | 10 |
Week 8:
The gross requirement is 10 (1 assembly). The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 7 which will be the Planned order receipt in week 8.
Item B:
Week | ||||||||
Item B | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 10 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (2) | 2 | 0 | ||||||
Net requirement | 8 | 10 | ||||||
Planned order receipt | 8 | 10 | ||||||
Planned order release | 8 | 10 |
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 2. Hence, the Net requirement is 8. The lead time is 1 week. Therefore, the planned order release will be 8 in week 5 which will be the planned order receipt in week 6.
Week 7:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the planned order release will be 10 in week 6 which will be the planned order receipt in week 7.
Item F:
Week | ||||||||
Item F | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 10 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (5) | 5 | 0 | ||||||
Net requirement | 5 | 10 | ||||||
Planned order receipt | 5 | 10 | ||||||
Planned order release | 5 | 10 |
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 5. Hence, the Net requirement is 5. The lead time is 1 week. Therefore, the Planned order release will be 5 in week 5 which will be the Planned order receipt in week 6.
Week 7:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 6 which will be the Planned order receipt in week 7.
Item D:
Week | ||||||||
Item D | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 8 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (5) | 5 | 0 | ||||||
Net requirement | 3 | 10 | ||||||
Planned order receipt | 3 | 10 | ||||||
Planned order release | 3 | 10 |
Week 5:
The gross requirement is 8 (1 assembly) derived from the Planned order release of B. The on-hand inventory is 5. Hence, the Net requirement is 3. The lead time is 1 week. Therefore, the Planned order release will be 3 in week 4 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of B. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 5 which will be the Planned order receipt in week 6.
Item G (Lead Time = 3):
Week | ||||||||
Item G | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 5 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (1) | 1 | 0 | ||||||
Net requirement | 4 | 10 | ||||||
Planned order receipt | 4 | 10 | ||||||
Planned order release | 4 | 10 |
Week 5:
The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 1. Hence, the Net requirement is 4. The lead time is 3 weeks. Therefore, the Planned order release will be 4 in week 2 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 3 weeks. Therefore, the Planned order release will be 10 in week 3 which will be the Planned order receipt in week 6.
Item G (Lead Time = 4):
Week | ||||||||
Item G | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 5 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (1) | 1 | 0 | ||||||
Net requirement | 4 | 10 | ||||||
Planned order receipt | 4 | 10 | ||||||
Planned order release | 4 | 10 |
Week 5:
The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 1. Hence, the Net requirement is 4. The lead time is 4 weeks. Therefore, the Planned order release will be 4 in week 1 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 4 weeks. Therefore, the Planned order release will be 10 in week 2 which will be the Planned order receipt in week 6.
Item H:
Week | ||||||||
Item H | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 5 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (10) | 10 | 5 | ||||||
Net requirement | 5 | |||||||
Planned order receipt | 5 | |||||||
Planned order release | 5 |
Week 5:
The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 10. Hence, the Net requirement is 0. Therefore, there will be no Planned order release. The excess inventory will be available in week 6.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 5. Hence, the Net requirement is 5. The lead time is 1 week. Therefore, the Planned order release will be 5 in week 5 which will be the Planned order receipt in week 6.
Item C:
Week | ||||||||
Item C | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 13 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (10) | 10 | 0 | ||||||
Net requirement | 3 | 10 | ||||||
Planned order receipt | 3 | 10 | ||||||
Planned order release | 3 | 10 |
Week 5:
The gross requirement is 13 (1 assembly) derived from the Planned order release of B and H. The on-hand inventory is 10. Hence, the Net requirement is 3. The lead time is 2 weeks. Therefore, the Planned order release will be 3 in week 3 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of B and H. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 2 weeks. Therefore, the Planned order release will be 10 in week 4 which will be the Planned order receipt in week 6.
Item E:
Week | ||||||||
Item E | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 3 | 15 | ||||||
Scheduled receipt | ||||||||
On-hand (4) | 4 | 1 | ||||||
Net requirement | 14 | |||||||
Planned order receipt | 14 | |||||||
Planned order release | 14 |
Week 4:
The gross requirement is 3 (1 assembly) derived from the Planned order release of D. The on-hand inventory is 4. Hence, the Net requirement is 0. Therefore, there will be no Planned order release. The excess inventory will be available in week 5.
Week 5:
The gross requirement is 15 (1 assembly) derived from the Planned order release of H. The on-hand inventory is 1. Hence, the Net requirement is 14. The lead time is 1 week. Therefore, the Planned order release will be 14 in week 4 which will be the Planned order receipt in week 5.
Hence, the change will take place only with item G because it has no children. The Lead time of 4 weeks will preempt the Planned order release by 1 one week.
b)
To determine: The implications of the production plan because of change in the lead time of item G.
Introduction:
Net requirements plan:
The Net requirements plan is the plan which is established on the Gross requirements plan formed by deducting the stock on and the Scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.
b)
Answer to Problem 16P
The production plan will be altered such that item F and four units of A will be delayed by 1 week.
Explanation of Solution
Given information:
- 10 units for service and production department for B and F.
- 10 units of A at week 8.
- Lead time of G has been changed to 4 weeks.
Part | A | B | C | D | E | F | G | H |
On Hand | 0 | 2 | 10 | 5 | 4 | 5 | 1 | 10 |
Product structure:
Net requirements plan:
Item A:
Week | ||||||||
Item A | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 10 | |||||||
Scheduled receipt | ||||||||
On-hand (0) | 0 | |||||||
Net requirement | 10 | |||||||
Planned order receipt | 10 | |||||||
Planned order release | 10 |
Week 8:
The gross requirement is 10 (1 assembly). The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 7 which will be the Planned order receipt in week 8.
Item B:
Week | ||||||||
Item B | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 10 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (2) | 2 | 0 | ||||||
Net requirement | 8 | 10 | ||||||
Planned order receipt | 8 | 10 | ||||||
Planned order release | 8 | 10 |
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 2. Hence, the Net requirement is 8. The lead time is 1 week. Therefore, the Planned order release will be 8 in week 5 which will be the Planned order receipt in week 6.
Week 7:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 6 which will be the Planned order receipt in week 7.
Item F:
Week | ||||||||
Item F | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 10 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (5) | 5 | 0 | ||||||
Net requirement | 5 | 10 | ||||||
Planned order receipt | 5 | 10 | ||||||
Planned order release | 5 | 10 |
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 5. Hence, the Net requirement is 5. The lead time is 1 week. Therefore, the Planned order release will be 5 in week 5 which will be the Planned order receipt in week 6.
Week 7:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 6 which will be the Planned order receipt in week 7.
Item D:
Week | ||||||||
Item D | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 8 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (5) | 5 | 0 | ||||||
Net requirement | 3 | 10 | ||||||
Planned order receipt | 3 | 10 | ||||||
Planned order release | 3 | 10 |
Week 5:
The gross requirement is 8 (1 assembly) derived from the Planned order release of B. The on-hand inventory is 5. Hence, the Net requirement is 3. The lead time is 1 week. Therefore, the Planned order release will be 3 in week 4 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of B. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 5 which will be the Planned order receipt in week 6.
Item G (Lead Time = 3):
Week | ||||||||
Item G | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 5 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (1) | 1 | 0 | ||||||
Net requirement | 4 | 10 | ||||||
Planned order receipt | 4 | 10 | ||||||
Planned order release | 4 | 10 |
Week 5:
The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 1. Hence, the Net requirement is 4. The lead time is 3 weeks. Therefore, the Planned order release will be 4 in week 2 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 3 weeks. Therefore, the Planned order release will be 10 in week 3 which will be the Planned order receipt in week 6.
Item G (Lead Time = 4):
Week | ||||||||
Item G | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 5 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (1) | 1 | 0 | ||||||
Net requirement | 4 | 10 | ||||||
Planned order receipt | 4 | 10 | ||||||
Planned order release | 4 | 10 |
Week 5:
The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 1. Hence, the Net requirement is 4. The lead time is 4 weeks. Therefore, the Planned order release will be 4 in week 1 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 4 weeks. Therefore, the Planned order release will be 10 in week 2 which will be the Planned order receipt in week 6.
Item H:
Week | ||||||||
Item H | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 5 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (10) | 10 | 5 | ||||||
Net requirement | 5 | |||||||
Planned order receipt | 5 | |||||||
Planned order release | 5 |
Week 5:
The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 10. Hence, the Net requirement is 0. Therefore, there will be no Planned order release. The excess inventory will be available in week 6.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 5. Hence, the Net requirement is 5. The lead time is 1 week. Therefore, the Planned order release will be 5 in week 5 which will be the Planned order receipt in week 6.
Item C:
Week | ||||||||
Item C | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 13 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (10) | 10 | 0 | ||||||
Net requirement | 3 | 10 | ||||||
Planned order receipt | 3 | 10 | ||||||
Planned order release | 3 | 10 |
Week 5:
The gross requirement is 13 (1 assembly) derived from the Planned order release of B and H. The on-hand inventory is 10. Hence, the Net requirement is 3. The lead time is 2 weeks. Therefore, the Planned order release will be 3 in week 3 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of B and H. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 2 weeks. Therefore, the Planned order release will be 10 in week 4 which will be the Planned order receipt in week 6.
Item E:
Week | ||||||||
Item E | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 3 | 15 | ||||||
Scheduled receipt | ||||||||
On-hand (4) | 4 | 1 | ||||||
Net requirement | 14 | |||||||
Planned order receipt | 14 | |||||||
Planned order release | 14 |
Week 4:
The gross requirement is 3 (1 assembly) derived from the Planned order release of D. The on-hand inventory is 4. Hence, the Net requirement is 0. Therefore, there will be no Planned order release. The excess inventory will be available in week 5.
Week 5:
The gross requirement is 15 (1 assembly) derived from the Planned order release of H. The on-hand inventory is 1. Hence, the Net requirement is 14. The lead time is 1 week. Therefore, the Planned order release will be 14 in week 4 which will be the Planned order receipt in week 5.
If this week is week 1 of the production plan, the increase in the lead time will make that only 1 assembly of G will be available for F in week 5. Hence, item F and consequently 4 units of item A will be delayed by a time of 1 week.
c)
To determine: The options the
c)
Explanation of Solution
Options the production manager has to manage these changes:
The production manager can do the following. They are:
- The production manager can inform the customer in advance that the 4 units will be delayed by a time of 1 week.
- The production manager can ask the supplier of item G to expedite the production or the delivery.
- The production manager can reduce the time take for production of item F or A.
Want to see more full solutions like this?
Chapter 14 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
- How would you design and implement a modern networking solution for JAMS Manufacturing to connect all their facilities and ensure seamless communication? The company currently has standalone systems in three manufacturing plants and an office building, each using its own modem or router for internet access. The goal is to create private networks for each location, connect them to one another, and provide Internet access to all. You’ll need to consider factors like new computer systems, servers, and telecommunications wiring, and explain how your solution will benefit the company and how it will be implemented effectively.arrow_forwardIdentify specific performance management processes covered in this course and how each aligns with an elements of LaFevor’s HCMS Model.arrow_forwardIdentify specific performance management processes covered in this course and how each aligns with LaFevor’s HCMS Model. LaFevor, K. (2017). What’s in Your Human Capital Management Strategy? The Game Plan, the Path, and Achievingarrow_forward
- assess how Human Capital Management Strategy is aimed at building an effective integrated performance management system: Discuss how human capital management strategy relates to performance management.arrow_forwardCASE STUDY 9-1 Was Robert Eaton a Good Performance Management Leader? R obert Eaton was CEO and chairman of Chrys- ler from 1993 to 1998, replacing Lee Iacocca, who retired after serving in this capacity since 1978. Eaton then served as cochairman of the newly merged DaimlerChrysler organization from 1998 to 2000. In fact, Eaton was responsible for the sale of Chrysler Corporation to Daimler-Benz, thereby creating DaimlerChrysler. With 362,100 employees, DaimlerChrysler had achieved revenues of €136.4 billion in 2003. DaimlerChrysler's passenger car brands included Maybach, Mercedes-Benz, Chrysler, Jeep, Dodge, and Smart. Commercial vehicle brands included Mercedes-Benz, Freightliner, Sterling, Western Star, and Setra. From the beginning of his tenure as CEO, Eaton communicated with the people under him. He immediately shared his plans for the future with his top four executives, and upon the advice of his colleague, Bob Lutz, decided to look around the company before making any hasty…arrow_forwardCritically assess Martin’s coaching style.arrow_forward
- Compare Robert Eaton’s performance management leadership presented in the case against the performance management leadership principles, functions, and behaviors. What recommendations can be made about what he might do more effectively? Explain and defend your answer.arrow_forwardIn the context of the material in Chapter 9, provide a critical analysis of the decisions that Henry has made in assigning Martin to this role.arrow_forwardpanies (pp. 80-118). New York, NY: Times Books, specifically Chap. 4, "Robert Eaton and Robert Lutz; The Copilots." CASE STUDY 9-2 Performance Management Leadership at Henry's Commercial Sales and Leasing H enry is the owner of a small real estate agency that handles the sale and leasing of commercial property. He has two real estate agents working in the office, along with himself. He also has two customer service representatives (CSRs), each of whom has a real estate license, and one receptionist who has worked for the company for about three months. Henry has recently decided that he needs another customer service representative. He hasarrow_forward
- Discuss possible solutions to help Tara become an effective CSR. What should martin be doing to help her?arrow_forwardWhat are the ethical challenges regarding employees (i.e., diversity, discrimination, sexual harassment, privacy, employee theft, bad leadership, etc.) that Apple Inc. has faced over the past five to ten years and that they should prepare to face in the next five to ten years. Once a developed list of challenges is created, consider how having faced those challenges will impact and be impacted by the social cause you've selected. Propose the findings on the ethical challenges faced by Apple Inc. in recent history and the near future. Analyze ways in which each challenge was (and/or could be) appropriately handled and areas for improvement. Evaluate the ethical/moral aspects of Apple Inc. that protected it from ethical challenges in the past and could protect it in the future. Assess how ethical challenges and handling of ethical challenges could positively or negatively impact the charitable cause are selected and how the selection of your social cause could positively or negatively…arrow_forwardBy selecting Cigna Accredo pharmacy that i identify in my resand compare the current feedback system against the “Characteristics of a Good Multiple Source Feedback Systems” described in section 8-3-3. What can be improved? As a consultant, what recommendations would you make?arrow_forward
- MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational PublishingPurchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningContemporary MarketingMarketingISBN:9780357033777Author:Louis E. Boone, David L. KurtzPublisher:Cengage Learning
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,