Concept explainers
a)
To develop: A net requirements plan for items.
Introduction:
Net requirements plan:
The net requirements plan is the plan which is established on the gross requirements plan formed by deducting the stock on and the
a)

Explanation of Solution
Given information:
Product structure:
Period | 8 | 9 | 10 | 11 | 12 |
Gross requirements: A | 100 | 50 | 150 | ||
Gross requirements: H | 100 | 50 |
Inventory and lead time:
Item | A | B | C | D | E | F | G | H | J | K |
Lead time | 1 | 2 | 2 | 1 | 2 | 2 | 1 | 1 | 2 | 2 |
On hand | 0 | 100 | 50 | 50 | 75 | 75 | 75 | 0 | 100 | 100 |
- 1 assembly for each item
Item A:
Week | ||||||||||||
Item A | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 100 | 50 | 150 | |||||||||
Scheduled receipt | ||||||||||||
On hand (0) | 0 | 0 | 0 | |||||||||
Net requirement | 100 | 50 | 150 | |||||||||
Planned order receipt | 100 | 50 | 150 | |||||||||
Planned order release | 100 | 50 | 150 |
Week 8:
The gross requirement is 100 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 1 week. Therefore, the planned order release will be 100 in week 7 which will be the planned order receipt in week 8.
Week 10:
The gross requirement is 50 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 1 week. Therefore, the planned order release will be 50 in week 9 which will be the planned order receipt in week 10.
Week 12:
The gross requirement is 150 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 150. The lead time is 1 week. Therefore, the planned order release will be 150 in week 11 which will be the planned order receipt in week 12.
Item H:
Week | ||||||||||||
Item H | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 100 | 50 | ||||||||||
Scheduled receipt | ||||||||||||
On hand (0) | 0 | 0 | ||||||||||
Net requirement | 100 | 50 | ||||||||||
Planned order receipt | 100 | 50 | ||||||||||
Planned order release | 100 | 50 |
Week 9:
The gross requirement is 100 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 1000. The lead time is 1 week. Therefore, the planned order release will be 100 in week 8 which will be the planned order receipt in week 10.
Week 11:
The gross requirement is 50 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 1 week. Therefore, the planned order release will be 50 in week 9 which will be the planned order receipt in week 11.
Item B:
Week | ||||||||||||
Item B | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 100 | 50 | 150 | |||||||||
Scheduled receipt | ||||||||||||
On hand (100) | 100 | 0 | 0 | |||||||||
Net requirement | 0 | 50 | 150 | |||||||||
Planned order receipt | 50 | 150 | ||||||||||
Planned order release | 50 | 150 |
Week 7:
The gross requirement is 100 (1 assembly) derived from planned order release of A. The on hand inventory is 100. Hence, the net requirement is 0. Therefore, there will be no planned order release.
Week 9:
The gross requirement is 50 (1 assembly) derived from the planned order release of A. The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 2 weeks. Therefore, the planned order release will be 50 in week 7 which will be the planned order receipt in week 9.
Week 11:
The gross requirement is 150 (1 assembly) derived from planned order release of A. The on hand inventory is 0. Hence, the net requirement is 150. The lead time is 2 weeks. Therefore, the planned order release will be 150 in week 9 which will be the planned order receipt in week 11.
Item C:
Week | ||||||||||||
Item C | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 100 | 100 | 50 | 50 | 150 | |||||||
Scheduled receipt | ||||||||||||
On hand (50) | 50 | 0 | 0 | 0 | 0 | |||||||
Net requirement | 50 | 100 | 50 | 50 | 150 | |||||||
Planned order receipt | 50 | 100 | 50 | 50 | 150 | |||||||
Planned order release | 50 | 100 | 50 | 50 | 150 |
Week 7:
The gross requirement is 100 (1 assembly) derived from planned order release of A. The on hand inventory is 50. Hence, the net requirement is 50. The lead time is 2 weeks. Therefore, the planned order release will be 50 in week 5 which will be the planned order receipt in week 7.
Week 8:
The gross requirement is 100 (1 assembly) derived from planned order release of H. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 2 weeks. Therefore, the planned order release will be 100 in week 6 which will be the planned order receipt in week 8.
Week 9:
The gross requirement is 50 (1 assembly) derived from the planned order release of A. The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 2 weeks. Therefore, the planned order release will be 50 in week 7 which will be the planned order receipt in week 9.
Week 10:
The gross requirement is 50 (1 assembly) derived from planned order release of H. The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 2 weeks. Therefore, the planned order release will be 50 in week 8 which will be the planned order receipt in week 10.
Week 11:
The gross requirement is 150 (1 assembly) derived from planned order release of A. The on hand inventory is 0. Hence, the net requirement is 150. The lead time is 2 weeks. Therefore, the planned order release will be 150 in week 9 which will be the planned order receipt in week 11.
Item J:
Week | ||||||||||||
Item J | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 100 | 50 | ||||||||||
Scheduled receipt | ||||||||||||
On hand (100) | 100 | 0 | ||||||||||
Net requirement | 0 | 50 | ||||||||||
Planned order receipt | 0 | 50 | ||||||||||
Planned order release | 50 |
Week 8:
The gross requirement is 100 (1 assembly) derived from planned order release of H. The on hand inventory is 100. Hence, the net requirement is 0. Therefore, there will be no planned order release.
Week 10:
The gross requirement is 50 (1 assembly) derived from the planned order release of H. The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 2 weeks. Therefore, the planned order release will be 50 in week 8 which will be the planned order receipt in week 10.
Item K:
Week | ||||||||||||
Item K | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 100 | 50 | ||||||||||
Scheduled receipt | ||||||||||||
On hand (100) | 100 | 0 | ||||||||||
Net requirement | 0 | 50 | ||||||||||
Planned order receipt | 50 | |||||||||||
Planned order release | 50 |
Week 8:
The gross requirement is 100 (1 assembly) derived from planned order release of H. The on hand inventory is 100. Hence, the net requirement is 0. Therefore, there will be no planned order release.
Week 10:
The gross requirement is 50 (1 assembly) derived from the planned order release of H. The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 2 weeks. Therefore, the planned order release will be 50 in week 8 which will be the planned order receipt in week 10.
Item D:
Week | ||||||||||||
Item D | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 50 | 150 | ||||||||||
Scheduled receipt | ||||||||||||
On hand (50) | 50 | 0 | ||||||||||
Net requirement | 150 | |||||||||||
Planned order receipt | 150 | |||||||||||
Planned order release | 150 |
Week 7:
The gross requirement is 50 (1 assembly) derived from planned order release of B. The on hand inventory is 500. Hence, the net requirement is 0. Therefore, there will be no planned order release.
Week 9:
The gross requirement is 150 (1 assembly) derived from the planned order release of B. The on hand inventory is 0. Hence, the net requirement is 150. The lead time is 1 week. Therefore, the planned order release will be 150 in week 8 which will be the planned order receipt in week 9.
Item E:
Week | ||||||||||||
Item E | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 50 | 100 | 150 | |||||||||
Scheduled receipt | ||||||||||||
On hand (75) | 75 | 25 | 0 | |||||||||
Net requirement | 0 | 75 | 150 | |||||||||
Planned order receipt | 75 | 150 | ||||||||||
Planned order release | 75 | 150 |
Week 7:
The gross requirement is 50 (1 assembly) derived from planned order release of B. The on hand inventory is 75. Hence, the net requirement is 0. Therefore, there will be no planned order release.
Week 8:
The gross requirement is 100 (1 assembly) derived from the planned order release of J and K. The on hand inventory is 25. Hence, the net requirement is 75. The lead time is 2 weeks. Therefore, the planned order release will be 75 in week 6 which will be the planned order receipt in week 8.
Week 9:
The gross requirement is 150 (1 assembly) derived from planned order release of B. The on hand inventory is 0. Hence, the net requirement is 150. The lead time is 2 weeks. Therefore, the planned order release will be 150 in week 7 which will be the planned order receipt in week 9.
Item F:
Week | ||||||||||||
Item F | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 50 | 100 | 50 | 100 | 150 | |||||||
Scheduled receipt | ||||||||||||
On hand (75) | 75 | 25 | 0 | 0 | 0 | |||||||
Net requirement | 0 | 75 | 50 | 100 | 150 | |||||||
Planned order receipt | 75 | 50 | 100 | 150 | ||||||||
Planned order release | 75 | 50 | 100 | 150 |
Week 5:
The gross requirement is 50 (1 assembly) derived from planned order release of C. The on hand inventory is 75. Hence, the net requirement is 0. Therefore, there will be no planned order release.
Week 6:
The gross requirement is 100 (1 assembly) derived from planned order release of C. The on hand inventory is 25. Hence, the net requirement is 75. The lead time is 2 weeks. Therefore, the planned order release will be 75 in week 4 which will be the planned order receipt in week 6.
Week 7:
The gross requirement is 50 (1 assembly) derived from the planned order release of C. The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 2 weeks. Therefore, the planned order release will be 50 in week 5 which will be the planned order receipt in week 7.
Week 8:
The gross requirement is 100 (1 assembly) derived from planned order release of C and J. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 2 weeks. Therefore, the planned order release will be 100 in week 6 which will be the planned order receipt in week 8.
Week 9:
The gross requirement is 150 (1 assembly) derived from planned order release of C. The on hand inventory is 0. Hence, the net requirement is 150. The lead time is 2 weeks. Therefore, the planned order release will be 150 in week 7 which will be the planned order receipt in week 9.
Item G:
Week | ||||||||||||
Item G | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 50 | 100 | 50 | 100 | 150 | |||||||
Scheduled receipt | ||||||||||||
On hand (75) | 75 | 25 | 0 | 0 | 0 | |||||||
Net requirement | 0 | 75 | 50 | 100 | 150 | |||||||
Planned order receipt | 75 | 50 | 100 | 150 | ||||||||
Planned order release | 75 | 50 | 100 | 150 |
Week 5:
The gross requirement is 50 (1 assembly) derived from planned order release of C. The on hand inventory is 75. Hence, the net requirement is 0. Therefore, there will be no planned order release.
Week 6:
The gross requirement is 100 (1 assembly) derived from planned order release of C. The on hand inventory is 25. Hence, the net requirement is 75. The lead time is 1 week. Therefore, the planned order release will be 75 in week 5 which will be the planned order receipt in week 6.
Week 7:
The gross requirement is 50 (1 assembly) derived from the planned order release of C. The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 1 week. Therefore, the planned order release will be 50 in week 6 which will be the planned order receipt in week 7.
Week 8:
The gross requirement is 100 (1 assembly) derived from planned order release of C and K. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 1 week. Therefore, the planned order release will be 100 in week 7 which will be the planned order receipt in week 8.
Week 9:
The gross requirement is 150 (1 assembly) derived from planned order release of C. The on hand inventory is 0. Hence, the net requirement is 150. The lead time is 1 week. Therefore, the planned order release will be 150 in week 8 which will be the planned order receipt in week 9.
b)
To develop: A net requirements plan for all items.
Introduction:
Net requirements plan:
The net requirements plan is the plan which is established on the gross requirements plan formed by deducting the stock on and the scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.
b)

Explanation of Solution
Given information:
Product structure:
Period | 8 | 9 | 10 | 11 | 12 |
Gross requirements: A | 100 | 50 | 150 | ||
Gross requirements: H | 100 | 50 |
Inventory and lead time:
Item | A | B | C | D | E | F | G | H | J | K |
Lead time | 1 | 2 | 2 | 1 | 2 | 2 | 1 | 1 | 2 | 2 |
On hand | 0 | 100 | 50 | 50 | 75 | 75 | 75 | 0 | 100 | 100 |
- 1 assembly for each item
- 2 assemblies for item B, C and F.
Item A:
Week | ||||||||||||
Item A | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 100 | 50 | 150 | |||||||||
Scheduled receipt | ||||||||||||
On hand (0) | 0 | 0 | 0 | |||||||||
Net requirement | 100 | 50 | 150 | |||||||||
Planned order receipt | 100 | 50 | 150 | |||||||||
Planned order release | 100 | 50 | 150 |
Week 8:
The gross requirement is 100 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 1 week. Therefore, the planned order release will be 100 in week 7 which will be the planned order receipt in week 8.
Week 10:
The gross requirement is 50 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 1 week. Therefore, the planned order release will be 50 in week 9 which will be the planned order receipt in week 10.
Week 12:
The gross requirement is 150 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 150. The lead time is 1 week. Therefore, the planned order release will be 150 in week 11 which will be the planned order receipt in week 12.
Item H:
Week | ||||||||||||
Item H | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 100 | 50 | ||||||||||
Scheduled receipt | ||||||||||||
On hand (0) | 0 | 0 | ||||||||||
Net requirement | 100 | 50 | ||||||||||
Planned order receipt | 100 | 50 | ||||||||||
Planned order release | 100 | 50 |
Week 9:
The gross requirement is 100 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 1000. The lead time is 1 week. Therefore, the planned order release will be 100 in week 8 which will be the planned order receipt in week 10.
Week 11:
The gross requirement is 50 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 1 week. Therefore, the planned order release will be 50 in week 9 which will be the planned order receipt in week 11.
Item B:
Week | ||||||||||||
Item B | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 200 | 100 | 300 | |||||||||
Scheduled receipt | ||||||||||||
On hand (100) | 100 | 0 | 0 | |||||||||
Net requirement | 100 | 100 | 300 | |||||||||
Planned order receipt | 100 | 100 | 300 | |||||||||
Planned order release | 100 | 100 | 300 |
Week 7:
The gross requirement is 200 (2 assembly) derived from planned order release of A. The on hand inventory is 100. Hence, the net requirement is 100. Therefore, the planned order release will be 100 in week 5 which will be the planned order receipt in week 7.
Week 9:
The gross requirement is 100 (2 assembly) derived from the planned order release of A. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 2 weeks. Therefore, the planned order release will be 100 in week 7 which will be the planned order receipt in week 9.
Week 11:
The gross requirement is 300 (2 assembly) derived from planned order release of A. The on hand inventory is 0. Hence, the net requirement is 300. The lead time is 2 weeks. Therefore, the planned order release will be 300 in week 9 which will be the planned order receipt in week 11.
Item C:
Week | ||||||||||||
Item C | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 200 | 200 | 100 | 100 | 300 | |||||||
Scheduled receipt | ||||||||||||
On hand (50) | 50 | 0 | 0 | 0 | 0 | |||||||
Net requirement | 150 | 200 | 100 | 100 | 300 | |||||||
Planned order receipt | 150 | 200 | 100 | 100 | 300 | |||||||
Planned order release | 150 | 200 | 100 | 100 | 300 |
Week 7:
The gross requirement is 200 (2 assembly) derived from planned order release of A. The on hand inventory is 50. Hence, the net requirement is 150. The lead time is 2 weeks. Therefore, the planned order release will be 150 in week 5 which will be the planned order receipt in week 7.
Week 8:
The gross requirement is 200 (2 assembly) derived from planned order release of H. The on hand inventory is 0. Hence, the net requirement is 200. The lead time is 2 weeks. Therefore, the planned order release will be 200 in week 6 which will be the planned order receipt in week 8.
Week 9:
The gross requirement is 100 (2 assembly) derived from the planned order release of A. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 2 weeks. Therefore, the planned order release will be 100 in week 7 which will be the planned order receipt in week 9.
Week 10:
The gross requirement is 100 (2 assembly) derived from planned order release of H. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 2 weeks. Therefore, the planned order release will be 100 in week 8 which will be the planned order receipt in week 10.
Week 11:
The gross requirement is 300 (2 assembly) derived from planned order release of A. The on hand inventory is 0. Hence, the net requirement is 300. The lead time is 2 weeks. Therefore, the planned order release will be 300 in week 9 which will be the planned order receipt in week 11.
Item J:
Week | ||||||||||||
Item J | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 100 | 50 | ||||||||||
Scheduled receipt | ||||||||||||
On hand (100) | 100 | 0 | ||||||||||
Net requirement | 0 | 50 | ||||||||||
Planned order receipt | 0 | 50 | ||||||||||
Planned order release | 50 |
Week 8:
The gross requirement is 100 (1 assembly) derived from planned order release of H. The on hand inventory is 100. Hence, the net requirement is 0. Therefore, there will be no planned order release.
Week 10:
The gross requirement is 50 (1 assembly) derived from the planned order release of H. The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 2 weeks. Therefore, the planned order release will be 50 in week 8 which will be the planned order receipt in week 10.
Item K:
Week | ||||||||||||
Item K | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 100 | 50 | ||||||||||
Scheduled receipt | ||||||||||||
On hand (100) | 100 | 0 | ||||||||||
Net requirement | 0 | 50 | ||||||||||
Planned order receipt | 50 | |||||||||||
Planned order release | 50 |
Week 8:
The gross requirement is 100 (1 assembly) derived from planned order release of H. The on hand inventory is 100. Hence, the net requirement is 0. Therefore, there will be no planned order release.
Week 10:
The gross requirement is 50 (1 assembly) derived from the planned order release of H. The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 2 weeks. Therefore, the planned order release will be 50 in week 8 which will be the planned order receipt in week 10.
Item D:
Week | ||||||||||||
Item D | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 100 | 100 | 300 | |||||||||
Scheduled receipt | ||||||||||||
On hand (50) | 50 | 0 | 0 | |||||||||
Net requirement | 50 | 100 | 300 | |||||||||
Planned order receipt | 50 | 100 | 300 | |||||||||
Planned order release | 50 | 100 | 300 |
Week 6:
The gross requirement is 100 (1 assembly) derived from the planned order release of B. The on hand inventory is 50. Hence, the net requirement is 50. The lead time is 1 week. Therefore, the planned order release will be 50 in week 5 which will be the planned order receipt in week 6.
Week 8:
The gross requirement is 100 (1 assembly) derived from the planned order release of B. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 1 week. Therefore, the planned order release will be 100 in week 7 which will be the planned order receipt in week 8.
Week 8:
The gross requirement is 300 (1 assembly) derived from the planned order release of B. The on hand inventory is 0. Hence, the net requirement is 300. The lead time is 1 week. Therefore, the planned order release will be 300 in week 9 which will be the planned order receipt in week 10.
Item E:
Week | ||||||||||||
Item E | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 100 | 100 | 100 | 300 | ||||||||
Scheduled receipt | ||||||||||||
On hand (75) | 75 | 0 | 0 | 0 | ||||||||
Net requirement | 25 | 100 | 100 | 300 | ||||||||
Planned order receipt | 25 | 100 | 100 | 300 | ||||||||
Planned order release | 25 | 100 | 100 | 300 |
Week 5:
The gross requirement is 100 (1 assembly) derived from planned order release of B. The on hand inventory is 75. Hence, the net requirement is 25. The lead time is 2 weeks. Therefore, the planned order release will be 25 in week 3 which will be the planned order receipt in week 5.
Week 7:
The gross requirement is 100 (1 assembly) derived from planned order release of B. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 2 weeks. Therefore, the planned order release will be 100 in week 5 which will be the planned order receipt in week 7.
Week 8:
The gross requirement is 100 (1 assembly) derived from the planned order release of J and K. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 2 weeks. Therefore, the planned order release will be 100 in week 6 which will be the planned order receipt in week 8.
Week 9:
The gross requirement is 300 (1 assembly) derived from planned order release of B. The on hand inventory is 0. Hence, the net requirement is 300. The lead time is 2 weeks. Therefore, the planned order release will be 300 in week 7 which will be the planned order receipt in week 9.
Item F:
Week | ||||||||||||
Item F | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 300 | 400 | 200 | 300 | 600 | |||||||
Scheduled receipt | ||||||||||||
On hand (75) | 75 | 0 | 0 | 0 | 0 | |||||||
Net requirement | 225 | 400 | 200 | 300 | 600 | |||||||
Planned order receipt | 225 | 400 | 200 | 300 | 600 | |||||||
Planned order release | 225 | 400 | 200 | 300 | 600 |
Week 5:
The gross requirement is 300 (2 assembly) derived from planned order release of C. The on hand inventory is 75. Hence, the net requirement is 225. The lead time is 2 weeks. Therefore, the planned order release will be 225 in week 3 which will be the planned order receipt in week 5.
Week 6:
The gross requirement is 400 (2 assembly) derived from planned order release of C. The on hand inventory is 0. Hence, the net requirement is 400. The lead time is 2 weeks. Therefore, the planned order release will be 400 in week 4 which will be the planned order receipt in week 6.
Week 7:
The gross requirement is 200 (2 assembly) derived from the planned order release of C. The on hand inventory is 0. Hence, the net requirement is 200. The lead time is 2 weeks. Therefore, the planned order release will be 200 in week 5 which will be the planned order receipt in week 7.
Week 8:
The gross requirement is 300 (2 assembly) derived from planned order release of C and J. The on hand inventory is 0. Hence, the net requirement is 300. The lead time is 2 weeks. Therefore, the planned order release will be 300 in week 6 which will be the planned order receipt in week 8.
Week 9:
The gross requirement is 600 (2 assembly) derived from planned order release of C. The on hand inventory is 0. Hence, the net requirement is 600. The lead time is 2 weeks. Therefore, the planned order release will be 600 in week 7 which will be the planned order receipt in week 9.
Item G:
Week | ||||||||||||
Item G | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 150 | 200 | 100 | 150 | 300 | |||||||
Scheduled receipt | ||||||||||||
On hand (75) | 75 | 0 | 0 | 0 | 0 | |||||||
Net requirement | 75 | 200 | 100 | 150 | 300 | |||||||
Planned order receipt | 75 | 200 | 100 | 150 | 300 | |||||||
Planned order release | 75 | 200 | 100 | 150 | 300 |
Week 5:
The gross requirement is 150 (1 assembly) derived from planned order release of C. The on hand inventory is 75. Hence, the net requirement is 75. The lead time is 1 week. Therefore, the planned order release will be 75 in week 4 which will be the planned order receipt in week 5.
Week 6:
The gross requirement is 200 (1 assembly) derived from planned order release of C. The on hand inventory is 0. Hence, the net requirement is 200. The lead time is 1 week. Therefore, the planned order release will be 200 in week 5 which will be the planned order receipt in week 6.
Week 7:
The gross requirement is 100 (1 assembly) derived from the planned order release of C. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 1 week. Therefore, the planned order release will be 100 in week 6 which will be the planned order receipt in week 7.
Week 8:
The gross requirement is 150 (1 assembly) derived from planned order release of C and K. The on hand inventory is 0. Hence, the net requirement is 150. The lead time is 1 week. Therefore, the planned order release will be 150 in week 7 which will be the planned order receipt in week 8.
Week 9:
The gross requirement is 300 (1 assembly) derived from planned order release of C. The on hand inventory is 0. Hence, the net requirement is 300. The lead time is 1 week. Therefore, the planned order release will be 300 in week 8 which will be the planned order receipt in week 9.
Want to see more full solutions like this?
Chapter 14 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
- Follow guidelines and summarize in a paragrapharrow_forwardCan you guys help me with this? Thank you! Business Environment: Provide insights into the guidelines for conducting business in the chosen country and working there as an expatriate. This information is vital for understanding the practicalities of engagement in that particular environment. The country in here is India Put the answer as bullet points, provide sources that have relevant information for the answer on business environment of India that enhance its value and uniqueness within the global supply chain landscape.arrow_forwardConsider this sign seen in a local restaurant: “To-go orders do NOT include complimentary chips and salsa. If you have any questions, see our management, NOT our employees.” How does the sign in the restaurant affect the service process and customer satisfaction? How would a five-star restaurant handle to-go orders differently? What competitive priorities are involved?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational PublishingPurchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning