Chapter 14, Problem 11P
a)
Summary Introduction
To develop: A gross requirements plan for item C.
Introduction:
Gross requirements plan:
The gross requirements plan is the plan where the independent and dependent demand for a product or a component before the on-hand inventory and the
b)
Summary Introduction
To develop: A net requirements plan for item C.
Introduction:
Net requirements plan:
The net requirements plan is the plan which is established on the gross requirements plan formed by deducting the stock on and the scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Given the following product structure, master production schedule, and inventory status below and assuming the requirements for each BOM item is 1: (a) develop a
gross requirements plan for Item C; (b) develop a net requirements plan for Item C.
Click the icon to view the product structure, master production schedule and inventory status.
a) Develop a gross requirements plan for Items C. To do so, first find the gross requirements plans for its parents: items A and H. (Enter your responses as whole
numbers).
Item
A Gross req
1
2
More Info
3
Period
Gross requirements: A
Gross requirements: H
Item
A
B
C
D
E
4
A
On
Hand
15
110
60
40
85
5
Week
6 7
8
100
Lead
Time
1
2
2
1
2
Q
9
90
8
Item
F
G
H
E
J
K
10
60
9
On
Hand
80
65
20
110
110
10
11
50
E
H
K
11 12
12
160
Lead
Time
2
1
1
2
2
G
C
■
G
X
2
Given the product structure, master productionschedule, and inventory status in Figure 14.13, and assuming therequirements for each BOM item is I:a) develop a gross requirements plan for Item C;b) develop a net requirements plan for Item C.
Chapter 14 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
Ch. 14 - Ethical Dilemma For many months your prospective...Ch. 14 - What is the difference between a gross...Ch. 14 - Prob. 2DQCh. 14 - What are the similarities between MRP and DRP?Ch. 14 - How does MRP II differ from MRP?Ch. 14 - Which is the best lot-sizing policy for...Ch. 14 - What impact does ignoring carrying cost in the...Ch. 14 - MRP is more than an inventory system; what...Ch. 14 - What are the options for the production planner...Ch. 14 - Master schedules are expressed in three different...
Ch. 14 - What functions of the firm affect an MRP system?...Ch. 14 - Prob. 11DQCh. 14 - Prob. 12DQCh. 14 - Prob. 13DQCh. 14 - Prob. 14DQCh. 14 - As an approach to inventory management, how does...Ch. 14 - Prob. 16DQCh. 14 - Use the Web or other sources to: a) Find stories...Ch. 14 - Prob. 18DQCh. 14 - Prob. 19DQCh. 14 - You have developed the following simple product...Ch. 14 - You are expected to have the gift bags in Problem...Ch. 14 - Prob. 3PCh. 14 - Your boss at Xiangling Hu Products, Inc., has just...Ch. 14 - The demand for subassembly S is 100 units in week...Ch. 14 - Prob. 6PCh. 14 - Prob. 7PCh. 14 - Prob. 8PCh. 14 - Prob. 9PCh. 14 - Prob. 10PCh. 14 - Prob. 11PCh. 14 - Prob. 12PCh. 14 - Prob. 13PCh. 14 - Prob. 14PCh. 14 - You are product planner for product A (in Problem...Ch. 14 - Prob. 16PCh. 14 - Prob. 17PCh. 14 - Heather Adams, production manager for a Colorado...Ch. 14 - Prob. 19PCh. 14 - Prob. 20PCh. 14 - Prob. 21PCh. 14 - Prob. 22PCh. 14 - Data Table for Problems 14.22 through 14.25 ...Ch. 14 - Develop a POQ solution and calculate total...Ch. 14 - Using your answers for the lot sizes computed in...Ch. 14 - M. de Koster, of Rene Enterprises, has the master...Ch. 14 - Grace Greenberg, production planner for Science...Ch. 14 - Prob. 28PCh. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Courtney Kamauf schedules production of a popular...Ch. 14 - Using the data for the coffee table in Problem...Ch. 14 - Prob. 1CSCh. 14 - Prob. 2CSCh. 14 - Prob. 1.1VCCh. 14 - Prob. 1.2VCCh. 14 - Prob. 1.3VCCh. 14 - Prob. 2.1VCCh. 14 - Prob. 2.2VCCh. 14 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 1 spring, and 3 clamps. The base is assembled from 2 clamp and 1 housing. Each clamp has 1 handle and 1 casting. Each housing has 2 bearing and 2 shaft. There is no inventory on hand. Part 2 a) Design a product structure noting the quantities for each item and show the low-level coding. Match each number in the structure below with the corresponding item. Number Item I Bracket II Spring Subscript left parenthesis 1 right parenthesis III Clamp Subscript left parenthesis 3 right parenthesis IV Bearing Subscript left parenthesis 2 rightarrow_forwardAs the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs, and 4 clamps. The base is assembled from 1 clamp and 1 housing. Each clamp has 1 handle and 2 castings. Each housing has 1 bearing and 2 shafts. There is no inventory on hand. Part 2 a) Design a product structure noting the quantities for each item and show the low-level coding. Match each number in the structure below with the corresponding item. Number Item I Spring Subscript left parenthesis 2 right parenthesisSpring(2) II Housing Subscript left parenthesis 1 right parenthesisHousing(1) III Casting Subscript left parenthesis 2 right parenthesisCasting(2) IV Shaft Subscript left parenthesis 2 right parenthesisShaft(2) Bracket Base(1) Clamp(1) Handle(1) Clamp(4) Bearing(1) Handle(1) Casting(2) IIIIIIIV Part 3 b) Determine the…arrow_forwardAs the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs, and 4 clamps. The base is assembled from 1 clamp and 2 housings. Each clamp has 1 handle and 1 casting. Each housing has 2 bearings and 1 shaft. There is no inventory on hand. A. Design a product structure noting the quantities for each item and show the low-level coding. B. Determine the gross quantities needed of each item if you are to assemble 50 brackets. C. Compute the net quantities if there are 25 of the base and 100 of the clamp in stock.arrow_forward
- help please I need it to be done in excelarrow_forwardPlease do not give solution in image formate thanku.arrow_forwardFigure 1 shows the BOM for product A. Table 1 shows the MPS quantity start dates for product A, and Table 2 contains data from inventory records for items B, C, and D. The production planner wants to determine the material requirements plan for items B, C, and D for the next 8 weeks. What is the planned receipts quantity for item D for week 6? C (3) D (2) 8 (1) D (2) C2) Figure 1. BOM for product A Table 1. MPS quantity start dates for product A Week Product 1 3 70 4. 6. 7. 8. 80 100 70 100 Table 2. Inventory record data Item Data category Lot-sizing rule Lead time Scheduled receipts Beginning inventory Safety stock LAL 2 weeks 100 (week 3) FOQ= 500 1 week 150 (week 1) POQ (P-4) 1 week 500 (week 1) 600 100 200 None 130arrow_forward
- Please help with this Thanksarrow_forwardExplain the concept of a Requirements Management Plan (RMP) and its importance in guiding the management of requirements throughout a project.arrow_forwarda) Given the product structure and master production scheduleshown in Figure 14.12, develop a gross requirements plan forall items.b) G iven the product structure, master production schedule, andinven tory status shown in Figure 14.12, develop a net requirementsplan (planned order release) for all items.arrow_forward
- Help me to solve thisarrow_forwardYou have just been notified that the lead time forcomponent G of product A ( You are product pla nner for product A (in Problem(A part structure, lead time (weeks), and on-handquantities for product A are shown in Figure 14. 14. From theinformation shown, generate:a) An indented bill of material fo r product A b) Net requirements for each part to produce I0 As in week 8using lot-for-lot. IP).) The field service manager, Mark Moon,has just called and told you that the requirements for B and Fshould each be increased by I 0 units for his repair requi rements inthe field.a) Prepare a list showing the quantity of each part required to produce the requirements for the service manager and the production request of I 0 Bs and Fs. b) Prepare a net requirement plan by date for the new requirements (for both production and field service), assuming that the field service manager wants his 10 units ofB and F in week 6 and the 10 production…arrow_forwardhello I need help with number 13 please and I need it only in excelarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY