Concept explainers
Using the data for the coffee table in Problem 14.31, build a labor

To determine: The number of labor hours and employees needed each day.
Explanation of Solution
Given information:
- Table requires 1 top, 4 legs, 1/8 gallon of strain, 1/16 gallon of blue, 2 short braces, 2 long braces, and brass cap on the bottom of each leg.
- 100 gallons of glue as inventory.
- All items except brass caps, stain and glue are planned on a Lot for lot basis.
- Caps are purchased in 1000’s, stain and glue by gallon.
- Lead time = 1 (for each item).
- 640 coffee tables needed on day 5 and 6.
- 128 coffee tables needed on days 7 and 8.
- Labor standard for each top is 2 labor hours.
- Each leg with brass cap installation and each pair of braces need ¼ hour.
- Base assembly needs 1 labor hour.
- Final assembly of table requires 2 labor hours.
- Number of hours per day is 8.
Product structure:
Net requirements plan:
Table:
Period (Day) | ||||||||
Table | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 640 | 640 | 128 | 128 | ||||
Scheduled receipt | ||||||||
On hand (0) | 0 | 0 | 0 | 0 | ||||
Net requirement | 640 | 640 | 128 | 128 | ||||
Planned order receipt | 640 | 640 | 128 | 128 | ||||
Planned order release | 640 | 640 | 128 | 128 |
Day 5:
The gross requirement is 640 (1 assembly) of Coffee table derived from the given information. The On hand is 0. Therefore, the net requirement is 640. The lead time is 1 week. The planned order release will be 640 in day 4 which will be the planned order receipt in day 5.
Day 6:
The gross requirement is 640 (1 assembly) of Coffee table derived from the given information. The On hand is 0. Therefore, the net requirement is 640. The lead time is 1 week. The planned order release will be 640 in day 5 which will be the planned order receipt in day 6.
Day 7:
The gross requirement is 128 (1 assembly) of Coffee table derived from the given information. The On hand is 0. Therefore, the net requirement is 128. The lead time is 1 week. The planned order release will be 128 in day 6 which will be the planned order receipt in day 7.
Day 8:
The gross requirement is 128 (1 assembly) of Coffee table derived from the given information. The On hand is 0. Therefore, the net requirement is 128. The lead time is 1 week. The planned order release will be 128 in day 7 which will be the planned order receipt in day 8.
Top:
Period (Day) | ||||||||
Top | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 640 | 640 | 128 | 128 | ||||
Scheduled receipt | ||||||||
On hand (0) | 0 | 0 | 0 | 0 | ||||
Net requirement | 640 | 640 | 128 | 128 | ||||
Planned order receipt | 640 | 640 | 128 | 128 | ||||
Planned order release | 640 | 640 | 128 | 128 |
Day 4:
The gross requirement is 640 (1 assembly) of Top derived from the planned order release of Table. The On hand is 0. Therefore, the net requirement is 640. The lead time is 1 week. The planned order release will be 640 in day 3 which will be the planned order receipt in day 4.
Day 5:
The gross requirement is 640 (1 assembly) of Top derived from the planned order release of Table. The On hand is 0. Therefore, the net requirement is 640. The lead time is 1 week. The planned order release will be 640 in day 4 which will be the planned order receipt in day 5.
Day 6:
The gross requirement is 128 (1 assembly) of Top derived from the planned order release of Table. The On hand is 0. Therefore, the net requirement is 128. The lead time is 1 week. The planned order release will be 128 in day 5 which will be the planned order receipt in day 6.
Day 7:
The gross requirement is 128 (1 assembly) of Top derived from the planned order release of Table. The On hand is 0. Therefore, the net requirement is 128. The lead time is 1 week. The planned order release will be 128 in day 6 which will be the planned order receipt in day 7.
Stain:
Period (Day) | ||||||||
Stain | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 80 | 80 | 16 | 16 | ||||
Scheduled receipt | ||||||||
On hand (0) | 0 | 0 | 0 | 0 | ||||
Net requirement | 80 | 80 | 16 | 16 | ||||
Planned order receipt | 80 | 80 | 16 | 16 | ||||
Planned order release | 80 | 80 | 16 | 16 |
Day 4:
The gross requirement is 80 (1 assembly) of Stain derived from the planned order release of Table. The On hand is 0. Therefore, the net requirement is 80. The lead time is 1 week. The planned order release will be 80 in day 3 which will be the planned order receipt in day 4.
Day 5:
The gross requirement is 80 (1 assembly) of Stain derived from the planned order release of Table. The On hand is 0. Therefore, the net requirement is 80. The lead time is 1 week. The planned order release will be 80 in day 4 which will be the planned order receipt in day 5.
Day 6:
The gross requirement is 16 (1 assembly) of Stain derived from the planned order release of Table. The On hand is 0. Therefore, the net requirement is 16. The lead time is 1 week. The planned order release will be 16 in day 5 which will be the planned order receipt in day 6.
Day 7:
The gross requirement is 16 (1 assembly) of Stain derived from the planned order release of Table. The On hand is 0. Therefore, the net requirement is 16. The lead time is 1 week. The planned order release will be 16 in day 6 which will be the planned order receipt in day 7.
Glue:
Period (Day) | ||||||||
Glue | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 40 | 40 | 8 | 8 | ||||
Scheduled receipt | ||||||||
On hand (100) | 100 | 60 | 20 | 12 | 4 | |||
Net requirement | 0 | 0 | 0 | 0 | ||||
Planned order receipt | ||||||||
Planned order release |
Day 4:
The gross requirement is 40 (1 assembly) of Glue derived from the planned order release of Table. The On hand is 100. Therefore, the net requirement is 0. Therefore there will be no planned order release. The excess inventory 60 will be available at week 5.
Day 5:
The gross requirement is 40 (1 assembly) of Glue derived from the planned order release of Table. The On hand is 60. Therefore, the net requirement is 0. Therefore there will be no planned order release. The excess inventory 20 will be available at week 6.
Day 6:
The gross requirement is 8 (1 assembly) of Glue derived from the planned order release of Table. The On hand is 20. Therefore, the net requirement is 0. Therefore there will be no planned order release. The excess inventory 12 will be available at week 7.
Day 7:
The gross requirement is 8 (1 assembly) of Glue derived from the planned order release of Table. The On hand is 12. Therefore, the net requirement is 0. Therefore there will be no planned order release. The excess inventory 8 will be available at week 8.
Base assembly:
Period (Day) | ||||||||
Base | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 640 | 640 | 128 | 128 | ||||
Scheduled receipt | ||||||||
On hand (0) | 0 | 0 | 0 | 0 | ||||
Net requirement | 640 | 640 | 128 | 128 | ||||
Planned order receipt | 640 | 640 | 128 | 128 | ||||
Planned order release | 640 | 640 | 128 | 128 |
Day 4:
The gross requirement is 640 (1 assembly) of base assembly derived from the planned order release of Table. The On hand is 0. Therefore, the net requirement is 640. The lead time is 1 week. The planned order release will be 640 in day 3 which will be the planned order receipt in day 4.
Day 5:
The gross requirement is 640 (1 assembly) of base assembly derived from the planned order release of Table. The On hand is 0. Therefore, the net requirement is 640. The lead time is 1 week. The planned order release will be 640 in day 4 which will be the planned order receipt in day 5.
Day 6:
The gross requirement is 128 (1 assembly) of base assembly derived from the planned order release of Table. The On hand is 0. Therefore, the net requirement is 128. The lead time is 1 week. The planned order release will be 128 in day 5 which will be the planned order receipt in day 6.
Day 7:
The gross requirement is 128 (1 assembly) of base assembly derived from the planned order release of Table. The On hand is 0. Therefore, the net requirement is 128. The lead time is 1 week. The planned order release will be 128 in day 6 which will be the planned order receipt in day 7.
Short brace:
Period (Day) | ||||||||
Short Brace | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 1,280 | 1,280 | 256 | 256 | ||||
Scheduled receipt | ||||||||
On hand (0) | 0 | 0 | 0 | 0 | ||||
Net requirement | 1,280 | 1,280 | 256 | 256 | ||||
Planned order receipt | 1,280 | 1,280 | 256 | 256 | ||||
Planned order release | 1,280 | 1,280 | 256 | 256 |
Day 3:
The gross requirement is 1,280 (2 assembly) of short brace derived from the planned order release of base assembly. The On hand is 0. Therefore, the net requirement is 1,280. The lead time is 1 week. The planned order release will be 1,280 in day 2 which will be the planned order receipt in day 3.
Day 4:
The gross requirement is 1,280 (2 assembly) of short brace derived from the planned order release of base assembly. The On hand is 0. Therefore, the net requirement is 1,280. The lead time is 1 week. The planned order release will be 1,280 in day 3 which will be the planned order receipt in day 4.
Day 5:
The gross requirement is 256 (2 assembly) of short brace derived from the planned order release of base assembly. The On hand is 0. Therefore, the net requirement is 256. The lead time is 1 week. The planned order release will be 256 in day 4 which will be the planned order receipt in day 5.
Day 6:
The gross requirement is 256 (2 assembly) of short brace derived from the planned order release of base assembly. The On hand is 0. Therefore, the net requirement is 256. The lead time is 1 week. The planned order release will be 256 in day 5 which will be the planned order receipt in day 6.
Long brace:
Period (Day) | ||||||||
Long Brace | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 1,280 | 1,280 | 256 | 256 | ||||
Scheduled receipt | ||||||||
On hand (0) | 0 | 0 | 0 | 0 | ||||
Net requirement | 1,280 | 1,280 | 256 | 256 | ||||
Planned order receipt | 1,280 | 1,280 | 256 | 256 | ||||
Planned order release | 1,280 | 1,280 | 256 | 256 |
Day 3:
The gross requirement is 1,280 (2 assembly) of long brace derived from the planned order release of base assembly. The On hand is 0. Therefore, the net requirement is 1,280. The lead time is 1 week. The planned order release will be 1,280 in day 2 which will be the planned order receipt in day 3.
Day 4:
The gross requirement is 1,280 (2 assembly) of long brace derived from the planned order release of base assembly. The On hand is 0. Therefore, the net requirement is 1,280. The lead time is 1 week. The planned order release will be 1,280 in day 3 which will be the planned order receipt in day 4.
Day 5:
The gross requirement is 256 (2 assembly) of long brace derived from the planned order release of base assembly. The On hand is 0. Therefore, the net requirement is 256. The lead time is 1 week. The planned order release will be 256 in day 4 which will be the planned order receipt in day 5.
Day 6:
The gross requirement is 256 (2 assembly) of long brace derived from the planned order release of base assembly. The On hand is 0. Therefore, the net requirement is 256. The lead time is 1 week. The planned order release will be 256 in day 5 which will be the planned order receipt in day 6.
Leg:
Period (Day) | ||||||||
Leg | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 2,560 | 2,560 | 512 | 512 | ||||
Scheduled receipt | ||||||||
On hand (0) | ||||||||
Net requirement | 2,560 | 2,560 | 512 | 512 | ||||
Planned order receipt | 2,560 | 2,560 | 512 | 512 | ||||
Planned order release | 2,560 | 2,560 | 512 | 512 |
Day 3:
The gross requirement is 2,560 (4 assembly) of leg derived from the planned order release of base assembly. The On hand is 0. Therefore, the net requirement is 2,560. The lead time is 1 week. The planned order release will be 2,560 in day 2 which will be the planned order receipt in day 3.
Day 4:
The gross requirement is 2,560 (4 assembly) of leg derived from the planned order release of base assembly. The On hand is 0. Therefore, the net requirement is 2,560. The lead time is 1 week. The planned order release will be 2,560 in day 3 which will be the planned order receipt in day 4.
Day 5:
The gross requirement is 512 (4 assembly) of leg derived from the planned order release of base assembly. The On hand is 0. Therefore, the net requirement is 512. The lead time is 1 week. The planned order release will be 512 in day 4 which will be the planned order receipt in day 5.
Day 6:
The gross requirement is 512 (4 assembly) of leg derived from the planned order release of base assembly. The On hand is 0. Therefore, the net requirement is 256. The lead time is 1 week. The planned order release will be 512 in day 5 which will be the planned order receipt in day 6.
Brass caps:
Period (Day) | ||||||||
Brass caps | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 2,560 | 2,560 | 512 | 512 | ||||
Scheduled receipt | ||||||||
On hand (0) | 0 | 440 | 880 | 368 | 856 | 856 | 856 | |
Net requirement | 2,560 | 2,120 | 0 | 144 | ||||
Planned order receipt | 3,000 | 3,000 | 1,000 | |||||
Planned order release | 3,000 | 3,000 | 1,000 |
Day 2:
The gross requirement is 2,560 (1 assembly) of brass caps derived from the planned order release of legs. The On hand is 0. Therefore, the net requirement is 2,560. The lead time is 1 week. The planned order release will be 3,000 (1 Lot = 1,000) in day 1 which will be the planned order receipt in day 2. The excess inventory of 440 is available at day 3.
Day 3:
The gross requirement is 2,560 (1 assembly) of brass caps derived from the planned order release of legs. The On hand is 440. Therefore, the net requirement is 2,120. The lead time is 1 week. The planned order release will be 3,000 (1 Lot = 1,000) in day 2 which will be the planned order receipt in day 3. The excess inventory of 880 is available at day 4.
Day 4:
The gross requirement is 512 (1 assembly) of brass caps derived from the planned order release of legs. The On hand is 880. Therefore, the net requirement is 0. Therefore, there will be no planned release. The excess inventory of 368 is available at day 5.
Day 5:
The gross requirement is 512 (1 assembly) of brass caps derived from the planned order release of legs. The On hand is 368. Therefore, the net requirement is 144. The lead time is 1 week. The planned order release will be 1,000 (1 Lot = 1,000) in day 4 which will be the planned order receipt in day 5. The excess inventory of 856 is available at the next day.
Calculation of labor hours / day:
Master Schedule | Hours Required | Day 1 | Day 2 | Day 3 | Day 4 | Day 5 | Day 6 | Day 7 | Day 8 |
Table assembly | 2 | 1280 | 1280 | 256 | 256 | ||||
Top preparation | 2 | 1280 | 1280 | 256 | 256 | ||||
Assemble base | 1 | 640 | 640 | 128 | 128 | ||||
Long brace (2) | 0.25 | 320 | 320 | 64 | 64 | ||||
Short brace (2) | 0.25 | 320 | 320 | 64 | 64 | ||||
Leg (4) | 0.25 | 640 | 640 | 128 | 128 | ||||
Total Hours | 0 | 1280 | 3200 | 3456 | 1920 | 640 | 256 | ||
Employees need @ 8 hours / day | 0 | 160 | 400 | 432 | 240 | 80 | 32 |
The master production schedule is derived from net requirements plan.
Formula to calculate number of hours / each day:
Formula to calculate the number of employees per 8 hour day:
Day 2:
Calculation of total hours for each day for each component:
Long brace:
Short brace:
Leg:
Calculation of total hours / day:
The total hours is calculated by summing all the hours needed for each component in a day.
Calculation of number of employees per 8 hour day:
The number of employees is calculated by dividing the total hours per day with the number of hours per day.
Day 3:
Calculation of total hours for each day for each component:
Top preparation:
Assemble base:
Long brace:
Short brace:
Leg:
Calculation of total hours / day:
The total hours is calculated by summing all the hours needed for each component in a day.
Calculation of number of employees per 8 hour day:
The number of employees is calculated by dividing the total hours per day with the number of hours per day.
Day 4:
Calculation of total hours for each day for each component:
Table assembly:
Top preparation:
Assemble base:
Long brace:
Short brace:
Leg:
Calculation of total hours / day:
The total hours is calculated by summing all the hours needed for each component in a day.
Calculation of number of employees per 8 hour day:
The number of employees is calculated by dividing the total hours per day with the number of hours per day.
Day 5:
Calculation of total hours for each day for each component:
Table assembly:
Top preparation:
Assemble base:
Long brace:
Short brace:
Leg:
Calculation of total hours / day:
The total hours is calculated by summing all the hours needed for each component in a day.
Calculation of number of employees per 8 hour day:
The number of employees is calculated by dividing the total hours per day with the number of hours per day.
Day 6:
Calculation of total hours for each day for each component:
Table assembly:
Top preparation:
Assemble base:
Calculation of total hours / day:
The total hours is calculated by summing all the hours needed for each component in a day.
Calculation of number of employees per 8 hour day:
The number of employees is calculated by dividing the total hours per day with the number of hours per day.
Day 7:
Calculation of total hours for each day for each component:
Table assembly:
Calculation of total hours / day:
The total hours is calculated by summing all the hours needed for each component in a day.
Calculation of number of employees per 8 hour day:
The number of employees is calculated by dividing the total hours per day with the number of hours per day.
Want to see more full solutions like this?
Chapter 14 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
- Can you guys help me with this? Thank you! Here's the question: Compared to the CONSTRAINT model, how has the network changed? How do you plan to add contingency to your network? Please answer this thoroughly Here's the what-if scenario: Assume that the LA warehouse becomes temporarily or even indefinitely disabled since facing a large-scale labor disruption. Re-optimize the network considering this new constraint. Here's the scenario comparison analysis: Scenario Constraint Scenario vs What-if Scenario Summary The Constraint Scenario exhibits a higher total cost of $7,424,575.45 compared to the What-if Scenario's total cost of $6,611,905.60, signifying a difference of approximately $812,669.85, which indicates a more expensive operation in the Constraint Scenario. The average service time is slightly higher in the Constraint Scenario (0.72 days vs. 0.70 days), suggesting that the What-if Scenario provides a marginally quicker service. Moreover, the average end-to-end service time…arrow_forwardCan you guys help me with this? Thank you! Here's the question: Compared to the CONSTRAINT model, how has the network changed? How do you plan to add contingency to your network? Please answer this throughly Here's the what-if scenario: Assume that Dallas plant has lost power. It cannot serve the DCs anymore and has to remain locked indefinitely. Re-optimize the network considering this new constraint. Here's the scenario comparison analysis: Scenario Constraint Scenario vs What-if Scenario Summary In comparing the Constraint Scenario to the What-if Scenario, a few key differences highlight the efficiencies evident in the supply chain. Firstly, the total cost in the Constraint Scenario is lower at $7,424,575.45, while the What-if Scenario incurs a total cost of $7,486,369.12, resulting in a cost delta of $61,793.67. Additionally, although both scenarios exhibit the same average service time of 0.72 days, the What-if Scenario has a more favorable average end-to-end service time of 2.41…arrow_forwardEmployee In-Service Training ASSIGNMENT: In-Service Training. The intern is required to plan and implement two in-service training sessions for employees. Each in-service should last at least 10 but not more than 30 minutes and should be given to all employees affected. The preceptor or supervisor/unit manager must approve all in-service topics. 1) One presentation should be related to a policy or procedure of any kind (e.g. proper use of equipment); 2) The second presentation must be related to sanitation or safety. For each in-service presentation, the intern must develop a written class plan and a visual aid (may be a handout, poster, PowerPoint slide presentation, etc.) appropriate to the life experiences, cultural diversity and educational background of the target audience. The intern must also measure behavior change. Note, this cannot be measured by a written pre- and post- test. That would be measuring knowledge. The intern mustactually observe and document that the learners…arrow_forward
- A small furniture manufacturer produces tables and chairs. Each product must go through three stages of the manufacturing process – assembly, finishing, and inspection. Each table requires 3 hours of assembly, 2 hours of finishing, and 1 hour of inspection. The profit per table is $120 while the profit per chair is $80. Currently, each week there are 200 hours of assembly time available, 180 hours of finishing time, and 40 hours of inspection time. Linear programming is to be used to develop a production schedule. Define the variables as follows: T = number of tables produced each week C= number of chairs produced each week According to the above information, what would the objective function be? (a) Maximize T+C (b) Maximize 120T + 80C (c) Maximize 200T+200C (d) Minimize 6T+5C (e) none of the above According to the information provided in Question 17, which of the following would be a necessary constraint in the problem? (a) T+C ≤ 40 (b) T+C ≤ 200 (c) T+C ≤ 180 (d) 120T+80C ≥ 1000…arrow_forwardAs much detail as possible. Dietary Management- Nursing Home Don't add any fill-in-the-blanksarrow_forwardMenu Planning Instructions Use the following questions and points as a guide to completing this assignment. The report should be typed. Give a copy to the facility preceptor. Submit a copy in your Foodservice System Management weekly submission. 1. Are there any federal regulations and state statutes or rules with which they must comply? Ask preceptor about regulations that could prescribe a certain amount of food that must be kept on hand for emergencies, etc. Is the facility accredited by any agency such as Joint Commission? 2. Describe the kind of menu the facility uses (may include standard select menu, menu specific to station, non-select, select, room service, etc.) 3. What type of foodservice does the facility have? This could be various stations to choose from, self-serve, 4. conventional, cook-chill, assembly-serve, etc. Are there things about the facility or system that place a constraint on the menu to be served? Consider how patients/guests are served (e.g. do they serve…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing
- Contemporary MarketingMarketingISBN:9780357033777Author:Louis E. Boone, David L. KurtzPublisher:Cengage LearningPurchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning