Find the maximum number of days it can be late.
Answer to Problem 79SR
The total number of days it can be late are
Explanation of Solution
Given: It is given in the question that a construction company will be fined for each day it is late completing a bridge. The daily fine will be
Concept Used:
In this, use the concept of using the linear equation and solving the question.
Calculation: Let the number of day late be x.
The fixed amount that have to fine =
The amount that have to pay per day will be
Now, according to question,
Since there is also a one day in hand so total days are
Conclusion:
The total number of days are
Chapter 12 Solutions
Glencoe Algebra 2 Student Edition C2014
Additional Math Textbook Solutions
Algebra and Trigonometry (6th Edition)
University Calculus: Early Transcendentals (4th Edition)
Elementary Statistics: Picturing the World (7th Edition)
Calculus: Early Transcendentals (2nd Edition)
Pre-Algebra Student Edition
- Algebra and Trigonometry (6th Edition)AlgebraISBN:9780134463216Author:Robert F. BlitzerPublisher:PEARSONContemporary Abstract AlgebraAlgebraISBN:9781305657960Author:Joseph GallianPublisher:Cengage LearningLinear Algebra: A Modern IntroductionAlgebraISBN:9781285463247Author:David PoolePublisher:Cengage Learning
- Algebra And Trigonometry (11th Edition)AlgebraISBN:9780135163078Author:Michael SullivanPublisher:PEARSONIntroduction to Linear Algebra, Fifth EditionAlgebraISBN:9780980232776Author:Gilbert StrangPublisher:Wellesley-Cambridge PressCollege Algebra (Collegiate Math)AlgebraISBN:9780077836344Author:Julie Miller, Donna GerkenPublisher:McGraw-Hill Education