Identifying and managing unused capacity (continuation of 12-29). Refer to Exercise 12-29.
- 1. Calculate the amount and cost of unused architectural support capacity at the beginning of 2017, based on the number of jobs actually done in 2017.
Required
- 2. Suppose Compton can add or reduce its architectural support capacity in increments of 10 units. What is the maximum amount of costs that Compton could save in 2017 by downsizing architectural support capacity?
- 3. Compton, in fact, does not eliminate any of its unused architectural support capacity. Why might Compton not downsize?
12-29 Strategy, balanced scorecard, service company. Compton Associates is an architectural firm that has been in practice only a few years. Because it is a relatively new firm, the market for the firm’s services is very competitive. To compete successfully, Compton must deliver quality services at a low cost. Compton presents the following data for 2016 and 2017.
2016 | 2017 | |
1. Number of jobs billed | 40 | 50 |
2. Selling price per job | $32,000 | $30,000 |
3. Architect labor-hours | 24,000 | 27,000 |
4. Cost per architect labor-hour | $35 | $36 |
5. Architect support capacity (number of jobs the firm can do) | 60 | 60 |
6. Total cost of software-implementation support | $168,000 | $180,000 |
7. Software-implementation support-capacity cost per job (row 6 ÷ row 5) | $2,800 | $3,000 |
Architect labor-hour costs are variable costs. Architect support costs for each year depend on the Architect support capacity that Compton chooses to maintain each year (that is, the number of jobs it can do each year). Architect support costs do not vary with the actual number of jobs done that year.
- 1. Is Compton Associate’s strategy one of product differentiation or cost leadership? Explain briefly.
Required
- 2. Describe key measures you would include in Compton’s balanced scorecard and your reasons for doing so.
Want to see the full answer?
Check out a sample textbook solutionChapter 12 Solutions
Horngren's Cost Accounting: A Managerial Emphasis (16th Edition)
- Hi teacher please help me this question solutionarrow_forwardCalculate the costarrow_forwardThe cost to manufacture an unfinished unit is $140 ($95 variable, $45 fixed). The selling price per unit is $155. The company has the unused productive capacity and has determined that units could be finished and sold for $198 with an increase in variable costs of 40%. What is the additional net income per unit to be gained by finishing the unit?arrow_forward
- Financial accounting questionarrow_forwardIf sales revenue is $110 million and accounts receivable increased by $18 million, the amount of cash received from customers: a. was $110 million. b. was $73 million. c. depends on the mix of cash sales and credit sales. d. was $92 million.arrow_forwardPlease solve this question general Accountingarrow_forward
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningEssentials of Business Analytics (MindTap Course ...StatisticsISBN:9781305627734Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. AndersonPublisher:Cengage Learning