Concept explainers
SummerFun. Inc., produces a variety of recreation and leisure products. The
Use the following information to develop aggregate plans.
Develop an aggregate plan using each of the following guidelines and compute the total cost for each plan. Hint: You will need extra output in April and August to accommodate demand in the following months.
a. Use regular production. Supplement using inventory, overtime, and subcontracting as needed. No backlogs allowed.
b. Use a level strategy. Use a combination of backlogs, subcontracting, and inventory to handle variations in demand. There should not be a backlog in the final period.
a)
To determine: The total cost using an aggregate plan.
Introduction:The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
Answer to Problem 7P
Explanation of Solution
Given information:
Regular production cost is $80, overtime production cost is $120, subcontracting cost is $140, backorder cost is $20, holding cost is $10, regular capacity is 40 units, overtime cost is 8 units, and subcontracting capacity is 12 units. Beginning inventory is given as 0 units. In addition to this forecast for 7 months is given as follows:
Month | March | April | May | June | July | August | September | Total |
Forecast | 50 | 44 | 55 | 60 | 50 | 40 | 51 | 350 |
Determine the total cost of the plan:
It is given that regular productions should be used. No backlogs are allowed. Supplements can be satisfied using overtime, subcontracting, and inventory.
Supporting explanation:
Forecast and regular time capacity are given. Regular time capacity is given as 40 units, remaining units should be produced using the overtime capacity. Maximum overtime capacity is given as 8 units. Thus, if the forecast is not satisfied, it can be produced using the subcontract:
Calculate the difference for the month of March:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 0 units.
Calculate the difference for the month of April:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 4 units.
Calculate the difference for the month of May:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is -4 units.
Note: The calculation repeats for all the months.
Beginning inventory:
The initial inventory is given as 0. For the remaining months, ending inventory of previous month would be the beginning inventory of present month.
Ending inventory for the month of March:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 0 units.
Ending inventory for the month of April:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 4 units.
Ending inventory for the month of May:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 0 units.
Note: The calculation repeats for all the months.
Average inventory for the month of March:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 0 units.
Average inventory for the month of April:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 2 units.
Average inventory for the month of May:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 2 units.
Note: The calculation repeats for all the months.
Calculate the regular time cost for the month of March:
Regular time cost per unit is given as $80 and regular time unit is given as 40. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $3,200.
Calculate the regular time cost for the month of April:
Regular time cost per unit is given as $80 and regular time unit is given as 40. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $3,200.
Calculate the regular time cost for the month of May:
Regular time cost per unit is given as $80 and regular time unit is given as 40. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $3,200.
Note: The calculation repeats for all the months.
Calculate the total regular time cost:
It is calculated by adding the regular time cost of all the months.
Hence, the total regular time cost is $22,400.
Calculate the overtime cost for the month of March:
Overtime cost per unit is given as $120 and overtime unit is given as 8. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $960.
Calculate the overtime cost for the month of April:
Overtime cost per unit is given as $120 and overtime unit is given as 8. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $960.
Calculate the overtime cost for the month of May:
Overtime cost per unit is given as $120 and overtime unit is given as 8. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $960.
Note: The calculation repeats for all the months.
Calculate the total overtime cost:
It is calculated by adding the overtime cost of all the months.
Hence, the total overtime cost is 6,120.
Calculate the subcontract cost for the month of March:
Subcontract cost per unit is given as $140 and subcontract unit is given as 2. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $280.
Calculate the subcontract cost for the month of April:
Subcontract cost per unit is given as $140 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Calculate the subcontract cost for the month of May:
Subcontract cost per unit is given as $140 and subcontract unit is given as 3. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $420.
Note: The calculation repeats for all the months.
Calculate the total subcontract cost:
It is calculated by adding the subcontract cost of all the months.
Hence, the total subcontract cost is $2,660.
Calculate the inventory cost for the month of March:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $0.
Calculate the inventory cost for the month of April:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $20.
Calculate the inventory cost for the month of May:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $20.
Note: The calculation repeats for all the months.
Calculate the total inventory cost:
It is calculated by adding the inventory cost of all the months.
Hence, the total inventory cost is $70.
Calculate the backorder cost for the month of March:
It is calculated by multiplying the backorder cost and the backlog. Hence, the backorder cost is $0.
Calculate the backorder cost for the month of April:
It is calculated by multiplying the backorder cost and the backlog. Hence, the backorder cost is $0.
Calculate the backorder cost for the month of May:
It is calculated by multiplying the backorder cost and the backlog. Hence, the backorder cost is $0.
Note: The calculation repeats for all the months.
Calculate the total cost of the plan:
It is calculated by adding the total regular time cost, overtime cost, subcontract cost, and inventory cost.
Hence, the total cost of the plan is $31,250.
b)
To determine: The total cost using a level strategy of aggregate planning.
Introduction:Level production strategy is a production strategy used to produce at a constant rate. This strategy keeps constant level of workforce and backlog of demand.
Answer to Problem 7P
Explanation of Solution
Given information:
Regular production cost is $80, overtime production cost is $120, subcontracting cost is $140, backorder cost is $20, holding cost is $10, regular capacity is 40 units, overtime cost is 8 units, and subcontracting capacity is 12 units. Beginning inventory is given as 0 units. In addition to this forecast for 7 months is given as follows:
Month | March | April | May | June | July | August | September | Total |
Forecast | 50 | 44 | 55 | 60 | 50 | 40 | 51 | 350 |
Determine the total cost of the plan:
Subcontracting, inventory, and backlogs can be used to handle the fluctuations in the demand. Initial solution using regular time and overtime without using subcontracting is as follows:
Supporting explanation:
Determine the regular time productivity:
It is calculated by taking an average of the given forecast.
Calculate the difference for the month of March:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is -2 units.
Calculate the difference for the month of April:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 4 units.
Calculate the difference for the month of May:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is --7 units.
Note: The calculation repeats for all the months.
Beginning inventory:
The initial inventory is given as 0. For the remaining months, ending inventory of previous month would be the beginning inventory of present month.
Ending inventory for the month of March:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 0 units.
Ending inventory for the month of April:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Difference between output and forecast is 2 (4-2). Hence, the ending inventory is 2 units.
Ending inventory for the month of May:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 0 units.
Note: The calculation repeats for all the months.
Average inventory for the month of March:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 0 units.
Average inventory for the month of April:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 1unit.
Average inventory for the month of May:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 1unit.
Note: The calculation repeats for all the months.
Backlogs for the month of 1:
It is number of units required in the month. As there is no previous month for 1st month, the difference would be the backlog. Hence, the backlog for 1st is 2 units.
Backlogs for the month of 2:
As the difference is positive, there would not be backlog.
Backlogs for the month of 3:
It is number of units required in the month. It is calculated by adding the backlog of previous month and the difference between output and forecast of current month (without considering the negative sign). Hence, the backlog is 5 units.
Note: The calculation repeats for all the months.
Calculate the regular time cost for the month of March:
Regular time cost per unit is given as $80 and regular time unit is given as 40. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $3,200.
Calculate the regular time cost for the month of April:
Regular time cost per unit is given as $80 and regular time unit is given as 40. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $3,200.
Calculate the regular time cost for the month of May:
Regular time cost per unit is given as $80 and regular time unit is given as 40. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $3,200.
Note: The calculation repeats for all the months.
Calculate the total regular time cost:
It is calculated by adding the regular time cost of all the months.
Hence, the total regular time cost is $22,400.
Calculate the overtime cost for the month of March:
Overtime cost per unit is given as $120 and overtime unit is given as 8. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $960.
Calculate the overtime cost for the month of April:
Overtime cost per unit is given as $120 and overtime unit is given as 8. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $960.
Calculate the overtime cost for the month of May:
Overtime cost per unit is given as $120 and overtime unit is given as 8. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $960.
Note: The calculation repeats for all the months.
Calculate the total overtime cost:
It is calculated by adding the overtime cost of all the months.
Hence, the total overtime cost is 6,120.
Calculate the subcontract cost for the month of March:
Subcontract cost per unit is given as $140 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $140.
Calculate the subcontract cost for the month of April:
Subcontract cost per unit is given as $140 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Calculate the subcontract cost for the month of May:
Subcontract cost per unit is given as $140 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Note: The calculation repeats for all the months.
Calculate the total subcontract cost:
It is calculated by adding the subcontract cost of all the months.
Hence, the total subcontract cost is $0.
Calculate the inventory cost for the month of March:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $0.
Calculate the inventory cost for the month of April:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $10.
Calculate the inventory cost for the month of May:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $10.
Note: The calculation repeats for all the months.
Calculate the total inventory cost:
It is calculated by adding the inventory cost of all the months.
Hence, the total inventory cost is $70.
Calculate the backorder cost for the month of March:
It is calculated by multiplying the backorder cost and the backlog. Hence, the backorder cost is $40.
Calculate the backorder cost for the month of April:
It is calculated by multiplying the backorder cost and the backlog. Hence, the backorder cost is $0.
Calculate the backorder cost for the month of May:
It is calculated by multiplying the backorder cost and the backlog. Hence, the backorder cost is $100.
Note: The calculation repeats for all the months.
Calculate the total backorder cost:
It is calculated by adding the backorder cost of all the months.
Hence, the total backorder cost is $1,360.
Calculate the total cost of the plan:
It is calculated by adding the total regular time cost, overtime cost, subcontract cost, and inventory cost.
Hence, the total cost of the plan is $30,500.
Determine the total cost of the plan:
Subcontracting, inventory, and backlogs can be used to handle the fluctuations in the demand. Final solution using regular time, overtime, and subcontracting is as follows:
Supporting explanation:
Determine the regular time productivity:
It is calculated by taking an average of the given forecast.
Calculate the difference for the month of March:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 0 units.
Calculate the difference for the month of April:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 4 units.
Calculate the difference for the month of May:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is -4 units.
Note: The calculation repeats for all the months.
Beginning inventory:
The initial inventory is given as 0. For the remaining months, ending inventory of previous month would be the beginning inventory of present month.
Ending inventory for the month of March:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 0 units.
Ending inventory for the month of April:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 4 units.
Ending inventory for the month of May:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 0 units.
Note: The calculation repeats for all the months.
Average inventory for the month of March:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 0 units.
Average inventory for the month of April:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 2 units.
Average inventory for the month of May:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 2 units.
Note: The calculation repeats for all the months.
Backlogs for the month of June:
It is number of units required in the month. It is calculated by adding the backlog of previous month and the difference between output and forecast of current month (without considering the negative sign). Hence, the backlog is 3 units.
Backlogs for the month of July:
It is number of units required in the month. It is calculated by adding the backlog of previous month and the difference between output and forecast of current month (without considering the negative sign). Hence, the backlog is 5 units.
Note: The calculation repeats for all the months.
Calculate the regular time cost for the month of March:
Regular time cost per unit is given as $80 and regular time unit is given as 40. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $3,200.
Calculate the regular time cost for the month of April:
Regular time cost per unit is given as $80 and regular time unit is given as 40. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $3,200.
Calculate the regular time cost for the month of May:
Regular time cost per unit is given as $80 and regular time unit is given as 40. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $3,200.
Note: The calculation repeats for all the months.
Calculate the total regular time cost:
It is calculated by adding the regular time cost of all the months.
Hence, the total regular time cost is $22,400.
Calculate the overtime cost for the month of March:
Overtime cost per unit is given as $120 and overtime unit is given as 8. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $960.
Calculate the overtime cost for the month of April:
Overtime cost per unit is given as $120 and overtime unit is given as 8. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $960.
Calculate the overtime cost for the month of May:
Overtime cost per unit is given as $120 and overtime unit is given as 8. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $960.
Note: The calculation repeats for all the months.
Calculate the total overtime cost:
It is calculated by adding the overtime cost of all the months.
Hence, the total overtime cost is 6,120.
Calculate the subcontract cost for the month of March:
Subcontract cost per unit is given as $140 and subcontract unit is given as 2. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $280.
Calculate the subcontract cost for the month of April:
Subcontract cost per unit is given as $140 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Calculate the subcontract cost for the month of May:
Subcontract cost per unit is given as $140 and subcontract unit is given as 3. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $420.
Note: The calculation repeats for all the months.
Calculate the total subcontract cost:
It is calculated by adding the subcontract cost of all the months.
Hence, the total subcontract cost is $1,960.
Calculate the inventory cost for the month of March:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $0.
Calculate the inventory cost for the month of April:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $20.
Calculate the inventory cost for the month of May:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $20.
Note: The calculation repeats for all the months.
Calculate the total inventory cost:
It is calculated by adding the inventory cost of all the months.
Hence, the total inventory cost is $70.
Calculate the backorder cost for the month of March:
It is calculated by multiplying the backorder cost and the backlog. Hence, the backorder cost is $0.
Calculate the backorder cost for the month of April:
It is calculated by multiplying the backorder cost and the backlog. Hence, the backorder cost is $0.
Calculate the backorder cost for the month of May:
It is calculated by multiplying the backorder cost and the backlog. Hence, the backorder cost is $0.
Note: The calculation repeats for all the months.
Calculate the total backorder cost:
It is calculated by adding the backorder cost of all the months.
Hence, the total backorder cost is $160.
Calculate the total cost of the plan:
It is calculated by adding the total regular time cost, overtime cost, subcontract cost, and inventory cost.
Hence, the total cost of the plan is $31,310.
Want to see more full solutions like this?
Chapter 11 Solutions
Operations Management
- working as a program operations managerarrow_forward12 X1, X230 1 x =0x2 write the Following linear Programming model by 1- general Form Canonical Forms Canonical formY 2- Standard Form Max Z=35X+ 4 X 2 +6 X3 ST. X+2X2-5x3 = 40 3X, + 6X2 + 7x 3 = 30 7x, +lox2 x3 = 50 X3 X 2 X 3 <0arrow_forwarda/ a Minimum cost assign each worker for one job at Jobs J1 12 33 WI 2 4 6 W2 5 W3 5 33 6 7arrow_forward
- وبة واضافة هذه القيمة الى القيم Ex: Assign each job for each worker at minimum total Cost عمل لكل عامل وبأقل كلفة ممكنة obs الأعمال Workors العمال J1 J2 J3 J4 W₁ 15 13 14 12 W2 11 12 15 13 W3 13 12 10 11 W4 15 17 14 16arrow_forwardThe average completion time (flow time) for the sequence developed using the FCFS rule = 11.75 days (round your response to two decimal places). The percentage utilization for the sequence developed using the FCFS rule = 42.55 % (enter your response as a percentage rounded to two decimal places). b) Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): An Alabama lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard's schedule. In what sequence would the jobs be ranked according to the decision rules on the left: Job Due Date A 212 B 209 C 208 D 210 Duration (days) 6 3 3 8 Sequence 1 Job B 2 3 4 A D The average tardiness (job lateness) for the sequence developed using the SPT rule = 5.00 days (round your response to two decimal places). The average completion time (flow time) for the sequence developed using the SPT rule = 10.25 days…arrow_forwardWith the aid of examples, fully discuss any five (5) political tactics used in organisations.arrow_forward
- a. With the aid of examples, define discrimination. b. Fully discuss any four (4) types of discrimination in the workplacearrow_forwardRead the Following Extract and Answer the Questions that Follows:The word politics has a somewhat negative connotation. It suggests that someone is attempting touse means or to gain ends that are not sanctioned by the organisation. Political behaviour, as we’vedefined it is quite neutral. Similarly, power is not inherently negative. Whether a person viewspower and politics as unsavoury topics depends on several considerations, most important perhapsbeing where the individual stands on a specific issue in each situation. Nonetheless, most managersare reluctant to admit to political character of their own work settings.Discuss any Five (5) Political tactics you know.arrow_forwardDescribe current features of Cigna Accredo pharmacy own appraisal forms and compare the system used against the textbook’s description of desirable features of appraisal forms. What improvements would you recommend and why?arrow_forward
- Provide a recommendation of a combination of different methods of performance data that could be used to arrive at an overall score for each person being rated in cigna Accredo pharmacy. Explain the comprehensive system you have recommended and why you have chosen this combination of tools. Support your answer with research.arrow_forwardAlready got wrong answer Plz Don't use chatgptarrow_forwardThe RTY calculation for the following process steps would be: A ➡ ○ A.YA+YB+YC+YD OB. (YA)(YB)(YCYD) OC. ((YA+YB+YC+YD)/4)*4 ○ D. (1/YA)+(1/YB)+(1/YC)+YD B C Darrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.