SummerFun. Inc., produces a variety of recreation and leisure products. The
Use the following information to develop aggregate plans.
Develop an aggregate plan using each of the following guidelines and compute the total cost for each plan. Hint: You will need extra output in April and August to accommodate demand in the following months.
a. Use regular production. Supplement using inventory, overtime, and subcontracting as needed. No backlogs allowed.
b. Use a level strategy. Use a combination of backlogs, subcontracting, and inventory to handle variations in demand. There should not be a backlog in the final period.
a)
To determine: The total cost using an aggregate plan.
Introduction:The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
Answer to Problem 7P
Explanation of Solution
Given information:
Regular production cost is $80, overtime production cost is $120, subcontracting cost is $140, backorder cost is $20, holding cost is $10, regular capacity is 40 units, overtime cost is 8 units, and subcontracting capacity is 12 units. Beginning inventory is given as 0 units. In addition to this forecast for 7 months is given as follows:
Month | March | April | May | June | July | August | September | Total |
Forecast | 50 | 44 | 55 | 60 | 50 | 40 | 51 | 350 |
Determine the total cost of the plan:
It is given that regular productions should be used. No backlogs are allowed. Supplements can be satisfied using overtime, subcontracting, and inventory.
Supporting explanation:
Forecast and regular time capacity are given. Regular time capacity is given as 40 units, remaining units should be produced using the overtime capacity. Maximum overtime capacity is given as 8 units. Thus, if the forecast is not satisfied, it can be produced using the subcontract:
Calculate the difference for the month of March:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 0 units.
Calculate the difference for the month of April:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 4 units.
Calculate the difference for the month of May:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is -4 units.
Note: The calculation repeats for all the months.
Beginning inventory:
The initial inventory is given as 0. For the remaining months, ending inventory of previous month would be the beginning inventory of present month.
Ending inventory for the month of March:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 0 units.
Ending inventory for the month of April:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 4 units.
Ending inventory for the month of May:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 0 units.
Note: The calculation repeats for all the months.
Average inventory for the month of March:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 0 units.
Average inventory for the month of April:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 2 units.
Average inventory for the month of May:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 2 units.
Note: The calculation repeats for all the months.
Calculate the regular time cost for the month of March:
Regular time cost per unit is given as $80 and regular time unit is given as 40. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $3,200.
Calculate the regular time cost for the month of April:
Regular time cost per unit is given as $80 and regular time unit is given as 40. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $3,200.
Calculate the regular time cost for the month of May:
Regular time cost per unit is given as $80 and regular time unit is given as 40. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $3,200.
Note: The calculation repeats for all the months.
Calculate the total regular time cost:
It is calculated by adding the regular time cost of all the months.
Hence, the total regular time cost is $22,400.
Calculate the overtime cost for the month of March:
Overtime cost per unit is given as $120 and overtime unit is given as 8. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $960.
Calculate the overtime cost for the month of April:
Overtime cost per unit is given as $120 and overtime unit is given as 8. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $960.
Calculate the overtime cost for the month of May:
Overtime cost per unit is given as $120 and overtime unit is given as 8. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $960.
Note: The calculation repeats for all the months.
Calculate the total overtime cost:
It is calculated by adding the overtime cost of all the months.
Hence, the total overtime cost is 6,120.
Calculate the subcontract cost for the month of March:
Subcontract cost per unit is given as $140 and subcontract unit is given as 2. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $280.
Calculate the subcontract cost for the month of April:
Subcontract cost per unit is given as $140 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Calculate the subcontract cost for the month of May:
Subcontract cost per unit is given as $140 and subcontract unit is given as 3. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $420.
Note: The calculation repeats for all the months.
Calculate the total subcontract cost:
It is calculated by adding the subcontract cost of all the months.
Hence, the total subcontract cost is $2,660.
Calculate the inventory cost for the month of March:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $0.
Calculate the inventory cost for the month of April:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $20.
Calculate the inventory cost for the month of May:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $20.
Note: The calculation repeats for all the months.
Calculate the total inventory cost:
It is calculated by adding the inventory cost of all the months.
Hence, the total inventory cost is $70.
Calculate the backorder cost for the month of March:
It is calculated by multiplying the backorder cost and the backlog. Hence, the backorder cost is $0.
Calculate the backorder cost for the month of April:
It is calculated by multiplying the backorder cost and the backlog. Hence, the backorder cost is $0.
Calculate the backorder cost for the month of May:
It is calculated by multiplying the backorder cost and the backlog. Hence, the backorder cost is $0.
Note: The calculation repeats for all the months.
Calculate the total cost of the plan:
It is calculated by adding the total regular time cost, overtime cost, subcontract cost, and inventory cost.
Hence, the total cost of the plan is $31,250.
b)
To determine: The total cost using a level strategy of aggregate planning.
Introduction:Level production strategy is a production strategy used to produce at a constant rate. This strategy keeps constant level of workforce and backlog of demand.
Answer to Problem 7P
Explanation of Solution
Given information:
Regular production cost is $80, overtime production cost is $120, subcontracting cost is $140, backorder cost is $20, holding cost is $10, regular capacity is 40 units, overtime cost is 8 units, and subcontracting capacity is 12 units. Beginning inventory is given as 0 units. In addition to this forecast for 7 months is given as follows:
Month | March | April | May | June | July | August | September | Total |
Forecast | 50 | 44 | 55 | 60 | 50 | 40 | 51 | 350 |
Determine the total cost of the plan:
Subcontracting, inventory, and backlogs can be used to handle the fluctuations in the demand. Initial solution using regular time and overtime without using subcontracting is as follows:
Supporting explanation:
Determine the regular time productivity:
It is calculated by taking an average of the given forecast.
Calculate the difference for the month of March:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is -2 units.
Calculate the difference for the month of April:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 4 units.
Calculate the difference for the month of May:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is --7 units.
Note: The calculation repeats for all the months.
Beginning inventory:
The initial inventory is given as 0. For the remaining months, ending inventory of previous month would be the beginning inventory of present month.
Ending inventory for the month of March:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 0 units.
Ending inventory for the month of April:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Difference between output and forecast is 2 (4-2). Hence, the ending inventory is 2 units.
Ending inventory for the month of May:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 0 units.
Note: The calculation repeats for all the months.
Average inventory for the month of March:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 0 units.
Average inventory for the month of April:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 1unit.
Average inventory for the month of May:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 1unit.
Note: The calculation repeats for all the months.
Backlogs for the month of 1:
It is number of units required in the month. As there is no previous month for 1st month, the difference would be the backlog. Hence, the backlog for 1st is 2 units.
Backlogs for the month of 2:
As the difference is positive, there would not be backlog.
Backlogs for the month of 3:
It is number of units required in the month. It is calculated by adding the backlog of previous month and the difference between output and forecast of current month (without considering the negative sign). Hence, the backlog is 5 units.
Note: The calculation repeats for all the months.
Calculate the regular time cost for the month of March:
Regular time cost per unit is given as $80 and regular time unit is given as 40. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $3,200.
Calculate the regular time cost for the month of April:
Regular time cost per unit is given as $80 and regular time unit is given as 40. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $3,200.
Calculate the regular time cost for the month of May:
Regular time cost per unit is given as $80 and regular time unit is given as 40. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $3,200.
Note: The calculation repeats for all the months.
Calculate the total regular time cost:
It is calculated by adding the regular time cost of all the months.
Hence, the total regular time cost is $22,400.
Calculate the overtime cost for the month of March:
Overtime cost per unit is given as $120 and overtime unit is given as 8. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $960.
Calculate the overtime cost for the month of April:
Overtime cost per unit is given as $120 and overtime unit is given as 8. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $960.
Calculate the overtime cost for the month of May:
Overtime cost per unit is given as $120 and overtime unit is given as 8. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $960.
Note: The calculation repeats for all the months.
Calculate the total overtime cost:
It is calculated by adding the overtime cost of all the months.
Hence, the total overtime cost is 6,120.
Calculate the subcontract cost for the month of March:
Subcontract cost per unit is given as $140 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $140.
Calculate the subcontract cost for the month of April:
Subcontract cost per unit is given as $140 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Calculate the subcontract cost for the month of May:
Subcontract cost per unit is given as $140 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Note: The calculation repeats for all the months.
Calculate the total subcontract cost:
It is calculated by adding the subcontract cost of all the months.
Hence, the total subcontract cost is $0.
Calculate the inventory cost for the month of March:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $0.
Calculate the inventory cost for the month of April:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $10.
Calculate the inventory cost for the month of May:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $10.
Note: The calculation repeats for all the months.
Calculate the total inventory cost:
It is calculated by adding the inventory cost of all the months.
Hence, the total inventory cost is $70.
Calculate the backorder cost for the month of March:
It is calculated by multiplying the backorder cost and the backlog. Hence, the backorder cost is $40.
Calculate the backorder cost for the month of April:
It is calculated by multiplying the backorder cost and the backlog. Hence, the backorder cost is $0.
Calculate the backorder cost for the month of May:
It is calculated by multiplying the backorder cost and the backlog. Hence, the backorder cost is $100.
Note: The calculation repeats for all the months.
Calculate the total backorder cost:
It is calculated by adding the backorder cost of all the months.
Hence, the total backorder cost is $1,360.
Calculate the total cost of the plan:
It is calculated by adding the total regular time cost, overtime cost, subcontract cost, and inventory cost.
Hence, the total cost of the plan is $30,500.
Determine the total cost of the plan:
Subcontracting, inventory, and backlogs can be used to handle the fluctuations in the demand. Final solution using regular time, overtime, and subcontracting is as follows:
Supporting explanation:
Determine the regular time productivity:
It is calculated by taking an average of the given forecast.
Calculate the difference for the month of March:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 0 units.
Calculate the difference for the month of April:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 4 units.
Calculate the difference for the month of May:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is -4 units.
Note: The calculation repeats for all the months.
Beginning inventory:
The initial inventory is given as 0. For the remaining months, ending inventory of previous month would be the beginning inventory of present month.
Ending inventory for the month of March:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 0 units.
Ending inventory for the month of April:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 4 units.
Ending inventory for the month of May:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 0 units.
Note: The calculation repeats for all the months.
Average inventory for the month of March:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 0 units.
Average inventory for the month of April:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 2 units.
Average inventory for the month of May:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 2 units.
Note: The calculation repeats for all the months.
Backlogs for the month of June:
It is number of units required in the month. It is calculated by adding the backlog of previous month and the difference between output and forecast of current month (without considering the negative sign). Hence, the backlog is 3 units.
Backlogs for the month of July:
It is number of units required in the month. It is calculated by adding the backlog of previous month and the difference between output and forecast of current month (without considering the negative sign). Hence, the backlog is 5 units.
Note: The calculation repeats for all the months.
Calculate the regular time cost for the month of March:
Regular time cost per unit is given as $80 and regular time unit is given as 40. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $3,200.
Calculate the regular time cost for the month of April:
Regular time cost per unit is given as $80 and regular time unit is given as 40. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $3,200.
Calculate the regular time cost for the month of May:
Regular time cost per unit is given as $80 and regular time unit is given as 40. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $3,200.
Note: The calculation repeats for all the months.
Calculate the total regular time cost:
It is calculated by adding the regular time cost of all the months.
Hence, the total regular time cost is $22,400.
Calculate the overtime cost for the month of March:
Overtime cost per unit is given as $120 and overtime unit is given as 8. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $960.
Calculate the overtime cost for the month of April:
Overtime cost per unit is given as $120 and overtime unit is given as 8. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $960.
Calculate the overtime cost for the month of May:
Overtime cost per unit is given as $120 and overtime unit is given as 8. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $960.
Note: The calculation repeats for all the months.
Calculate the total overtime cost:
It is calculated by adding the overtime cost of all the months.
Hence, the total overtime cost is 6,120.
Calculate the subcontract cost for the month of March:
Subcontract cost per unit is given as $140 and subcontract unit is given as 2. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $280.
Calculate the subcontract cost for the month of April:
Subcontract cost per unit is given as $140 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Calculate the subcontract cost for the month of May:
Subcontract cost per unit is given as $140 and subcontract unit is given as 3. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $420.
Note: The calculation repeats for all the months.
Calculate the total subcontract cost:
It is calculated by adding the subcontract cost of all the months.
Hence, the total subcontract cost is $1,960.
Calculate the inventory cost for the month of March:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $0.
Calculate the inventory cost for the month of April:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $20.
Calculate the inventory cost for the month of May:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $20.
Note: The calculation repeats for all the months.
Calculate the total inventory cost:
It is calculated by adding the inventory cost of all the months.
Hence, the total inventory cost is $70.
Calculate the backorder cost for the month of March:
It is calculated by multiplying the backorder cost and the backlog. Hence, the backorder cost is $0.
Calculate the backorder cost for the month of April:
It is calculated by multiplying the backorder cost and the backlog. Hence, the backorder cost is $0.
Calculate the backorder cost for the month of May:
It is calculated by multiplying the backorder cost and the backlog. Hence, the backorder cost is $0.
Note: The calculation repeats for all the months.
Calculate the total backorder cost:
It is calculated by adding the backorder cost of all the months.
Hence, the total backorder cost is $160.
Calculate the total cost of the plan:
It is calculated by adding the total regular time cost, overtime cost, subcontract cost, and inventory cost.
Hence, the total cost of the plan is $31,310.
Want to see more full solutions like this?
Chapter 11 Solutions
Operations Management
- Forecast Data is given within problem. Cost Data is attached Southeast Soda Pop, Inc., has a new fruit drink for which it has high hopes. John Mittenthal, the production planner, has assembled the following cost data and demand forecast: LOADING... Click the icon to view the demand forecast. LOADING... Click the icon to view the cost data. John's job is to develop an aggregate plan. The three initial options he wants to evaluate are: • Plan A: a strategy that hires and fires personnel as necessary to meet the forecast. • Plan B: a level strategy. • Plan C: a level strategy that produces 1,000 cases per quarter and meets the forecast demand with inventory and subcontracting. Part 2 a) Which strategy is the lowest-cost plan? Try hiring and layoffs (to meet the forecast) as necessary (enter your responses as whole numbers). Hiring and Layoff Plan Quarter Forecast Production Hire (Units) Layoff (Units)…arrow_forwardPlease help me obtain the answer of this question. Please provide me the solution/computation.arrow_forwardThe forecast demand for fudge for the next four months is 120, 160, 20, and 60 pounds. a. What is the recommended production rate if a level strategy is adopted with no backorders or stock outs? b. What is the ending inventory for Month 4 under this plan? c. What is the level production rate with no ending inventory in month 4.arrow_forward
- 1. Develop an aggregate plan for the following forecast Period 3 4 5 6 7 Total 1 2 8 Forecast 190 230 260 280 210 170 160 260 180 1,940 There are 20 workers who can produce 10 units per period at a cost of P6.00 per unit. There is no beginning invetory and the cost of carrying inventory is P5.00 per unit per period. Backlog cost is P10.00 per unit per period. Will the present workforce able to produce the forecast? b. What is the total cost of the plan? a.arrow_forwardDeb Bishop Health and Beauty Products has developed a new shampoo and you need to develop its aggregate schedule. The cost accounting department has supplied you the cost relevant to the aggregate plan and the marketing department has provided a four-quarter forecast. Click the icon to view the four-quarter forecast. Click the icon to view the costs relevant to the aggregate plan. Your job is to develop an aggregate plan for the next four quarters. a) Try hiring and layoffs (to meet the forecast) as necessary (enter your responses as whole numbers). More Info Hiring and Layoff Plan Hire Layoff Quarter Forecast Production (Units) (Units) 1,600 1 1,400 1400 0 200 2 1,000 1,000 0 400 3 1,600 1,600 600 0 4 1,200 ☑ More Info Previous quarter's output Beginning inventory Stockout cost for backorders Inventory holding cost Hiring workers Layoff workers Unit cost Overtime Subcontracting Costs 1,600 units $45 per unit O units $11 per unit for every unit held at the end of the quarter $50 per…arrow_forwardDeb Bishop Health and Beauty Products has developed a new shampoo and you need to develop its aggregate schedule. The cost accounting department has supplied you the cost relevant to the aggregate plan and the marketing department has provided a four-quarter forecast. the four-quarter forecast. Quarter Forecast 1 1,400 2 1,100 3 1,700 4 1,300 aggregate plan. Costs Previous quarter's output 1,600 units Beginning inventory 0 units Stockout cost for backorders $55 per unit Inventory holding cost $11 per unit for every unit held at the end of the quarter Hiring workers $50 per unit Layoff workers $75 per unit Unit cost $35 per unit Overtime $20 extra per unit Subcontracting Not available Your job is to develop an aggregate plan for the next four quarters. Part 2 a) Try hiring and layoffs (to meet the forecast) as necessary (enter your responses as whole…arrow_forward
- help:) thank you!! two partsarrow_forwardNeed only handwritten solution only (not typed one).arrow_forwardA manager has prepared a forecast of expected aggregate demand for the next six months. Develop an aggregate plan to meet this demand given this additional information: A level production rate of 500 units per month can be used. Backorders are allowed, and they are charged at the rate of $20 per unit per month. Inventory holding costs are $1 per unit per month in ending inventory. Determine the cost of this plan if regular time cost is $10 per unit and beginning inventory is zero. Overtime costs $16 per unit and subcontracting costs $20 per unit. In the 4th month, overtime is not possible. While outsourcing is not possible in the 3rd month. Overtime capacity is 50 units and subcontracting capacity is 50 units. Month Forecast 1 400 2 480 3 560 4 720 5…arrow_forward
- Manager T. C. Downs of Plum Engines, a producer of lawn mowers and leaf blowers, must develop an aggregate plan given the forecast for engine demand shown in the table. The department has a regular output capacity of 135 engines per month. Regular output has a cost of $60 per engine. The beginning inventory is zero engines. Overtime has a cost of $100 per engine. a. Develop a chase plan that matches the forecast and compute the total cost of your plan. Regular production can be less than regular capacity. (Negative amounts should be indicated by a minus sign. Leave no cells blank - be certain to enter "0" wherever required.) b. Compare the costs to a level plan that uses inventory to absorb fluctuations. Inventory carrying cost is $2 per engine per month. Backlog cost is $120 per engine per month. There should not be a backlog in the last month. Set regular production equal to the monthly average of total forecasted demand. Assume that using overtime is not an option. (Negative amounts…arrow_forwardDeb Bishop Health and Beauty Products has developeda new shampoo, and you need to develop its aggregate schedule.The cost accounting department bas supplied you the costsrelevant to the aggregate plan, and the marketing department hasprovided a four-quarter forecast. All are shown as follows: Your job is to develop an aggregate plan for the next four quarters.a) First, try hiring and layoffs (to meet the forecast) as necessary.b) Then try a plan that holds employment steady.c) Which is the more economical plan for Deb Bishop Healthand Beauty Products?arrow_forwardA manager has prepared a forecast of expected aggregate demand for the next six months. Develop an aggregate plan to meet this demand given this additional information: A level production rate of 1000 units per month can be used. Backorders are allowed, and they are charged at the rate of $20 per unit per month. Inventory holding costs are $1 per unit per month in ending inventory. Determine the cost of this plan if regular time cost is $10 per unit and beginning inventory is zero. Overtime costs $16 per unit and subcontracting costs $20 per unit. In the 4th month, overtime is not possible. While outsourcing is not allowed in the 3rd month. Overtime capacity is 100 units and subcontracting capacity is 100 units per month. Month Forecast 1 800 2 960 3 1120 4 1440 5…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.