Concept explainers
Compute the total cost for each aggregate plan using these unit costs:
Regular output = $40
Overtime = $50
Subcontract = $60
Average Balance Inventory = $10
a.
b.
c. (Refer to part b) After complaints from some workers about working overtime every month during the first half of the year, the manager is now considering adding some temporary workers for the second half of the year, which would increase regular output to a steady 350 units a month, not using any overtime, and using subcontracting to make up needed output. Determine the total cost of that plan.
a)
To compute: The total cost for each aggregate plan
Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
Answer to Problem 1P
Explanation of Solution
Given information:
Regular output is $40, overtime is $50, subcontract is $60, and average balance inventory is $10.
In addition to this, the following information is given:
Month | January | February | March | April | May | June |
Forecast | 300 | 320 | 320 | 340 | 320 | 320 |
Regular | 300 | 300 | 300 | 300 | 300 | 300 |
Overtime | 20 | 20 | 20 | 20 | 20 | 20 |
Subcontract | 0 | 0 | 0 | 0 | 0 | 0 |
Determine the aggregate plan to compute total cost:
Month | January | February | March | April | May | June | Total | |
Forecast | 300 | 320 | 320 | 340 | 320 | 320 | 1,920 | |
Output | ||||||||
Regular | 300 | 300 | 300 | 300 | 300 | 300 | 1,800 | |
Part-time | ||||||||
Overtime | 20 | 20 | 20 | 20 | 20 | 20 | 120 | |
Subcontract | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Difference | 20 | 0 | 0 | -20 | 0 | 0 | 0 | |
Inventory | ||||||||
Beginning | 0 | 20 | 20 | 20 | 0 | 0 | 60 | |
Ending | 20 | 20 | 20 | 0 | 0 | 0 | 60 | |
Average | 10 | 20 | 20 | 10 | 0 | 0 | 60 | |
Backlog | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Costs | ||||||||
Regular | 40 | $12,000 | $12,000 | $12,000 | $12,000 | $12,000 | $12,000 | $72,000 |
Part-time | ||||||||
Overtime | 50 | $1,000 | $1,000 | $1,000 | $1,000 | $1,000 | $1,000 | $6,000 |
Subcontract | 60 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
Hire/Layoff | ||||||||
Inventory | 10 | $100 | $200 | $200 | $100 | $0 | $0 | $600 |
Backorders | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
$13,100 | $13,200 | $13,200 | $13,100 | $13,000 | $13,000 | $78,600 |
Supporting calculation:
Forecast, regular time units, overtime, and subcontract units were given.
Calculate the difference of month January:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 20 units.
Calculate the difference of month February:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 0 units.
Calculate the difference of month March:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 0 units.
Note: The calculation repeats for all the months.
Beginning inventory:
The initial inventory is given as 0. For the remaining months, ending inventory of previous month would be the beginning inventory of present month.
Ending inventory for the month of January:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 20 units.
Ending inventory for the month of February:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 20 units.
Ending inventory for the month of March:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 20 units.
Note: The calculation repeats for all the months.
Average inventory for the month of January:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 10 units.
Average inventory for the month of February:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 20 units.
Average inventory for the month of March:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 20 units.
Note: The calculation repeats for all the months.
Calculate the regular time cost for the month of January:
Regular time cost per unit is given as $40 and regular time unit is given as 300. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $12,000.
Calculate the regular time cost for the month of February:
Regular time cost per unit is given as $40 and regular time unit is given as 300. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $12,000.
Calculate the regular time cost for the month of March:
Regular time cost per unit is given as $40 and regular time unit is given as 300. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $12,000.
Note: The calculation repeats for all the months.
Calculate the total regular time cost:
It is calculated by adding the regular time cost of all the months.
Hence, the total regular time cost is $72,000.
Calculate the overtime cost for the month of January:
Overtime cost per unit is given as $50 and overtime unit is given as 20. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $1,000.
Calculate the overtime cost for the month of February:
Overtime cost per unit is given as $50 and overtime unit is given as 20. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $1,000.
Calculate the overtime cost for the month of March:
Overtime cost per unit is given as $50 and overtime unit is given as 20. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $1,000.
Note: The calculation repeats for all the months.
Calculate the total overtime cost:
It is calculated by adding the overtime cost of all the months.
Hence, the total overtime cost is $6,000.
Calculate the subcontract cost for the month of January:
Subcontract cost per unit is given as $60 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Calculate the subcontract cost for the month of February:
Subcontract cost per unit is given as $60 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Calculate the subcontract cost for the month of March:
Subcontract cost per unit is given as $60 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Note: The calculation repeats for all the months.
Calculate the total subcontract cost:
It is calculated by adding the subcontract cost of all the months.
Hence, the total subcontract cost is $0.
Calculate the inventory cost for the month of January:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $100.
Calculate the inventory cost for the month of February:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $200.
Calculate the inventory cost for the month of March:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $200.
Note: The calculation repeats for all the months.
Calculate the total inventory cost:
It is calculated by adding the inventory cost of all the months.
Hence, the total inventory cost is $600.
Calculate the total cost of the plan:
It is calculated by adding the total regular time cost, overtime cost, subcontract cost, and inventory cost.
Hence, the total cost of the plan is $78,600.
b)
To compute: The total cost for each aggregate plan.
Introduction:The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
Answer to Problem 1P
Explanation of Solution
Given information:
Regular output is $40, overtime is $50, subcontract is $60, and average balance inventory is $10.
In addition to this, the following information is given:
Month | July | August | September | October | November | December |
Forecast | 320 | 340 | 360 | 380 | 400 | 400 |
Regular | 300 | 300 | 300 | 300 | 300 | 300 |
Overtime | 20 | 20 | 20 | 20 | 30 | 30 |
Subcontract | 20 | 30 | 40 | 40 | 60 | 70 |
Determine the aggregate plan to compute total cost:
Month | July | August | September | October | November | December | Total | |
Forecast | 320 | 340 | 360 | 380 | 400 | 400 | 2,200 | |
Output | ||||||||
Regular | 300 | 300 | 300 | 300 | 300 | 300 | 1,800 | |
Part-time | ||||||||
Overtime | 20 | 20 | 20 | 20 | 30 | 30 | 140 | |
Subcontract | 20 | 30 | 40 | 40 | 60 | 70 | 260 | |
Difference | 20 | 10 | 0 | -20 | -10 | 0 | 0 | |
Inventory | ||||||||
Beginning | 0 | 20 | 30 | 30 | 10 | 0 | 90 | |
Ending | 20 | 30 | 30 | 10 | 0 | 0 | 90 | |
Average | 10 | 25 | 30 | 20 | 5 | 0 | 90 | |
Backlog | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Costs | ||||||||
Regular | 40 | $12,000 | $12,000 | $12,000 | $12,000 | $12,000 | $12,000 | $72,000 |
Part-time | ||||||||
Overtime | 50 | $1,000 | $1,000 | $1,000 | $1,000 | $1,500 | $1,500 | $7,000 |
Subcontract | 60 | $1,200 | $1,800 | $2,400 | $2,400 | $3,600 | $4,200 | $15,600 |
Hire/Layoff | ||||||||
Inventory | 10 | $100 | $250 | $300 | $200 | $50 | $0 | $900 |
Backorders | ||||||||
$14,300 | $15,050 | $15,700 | $15,600 | $17,150 | $17,700 | $95,500 |
Supporting calculation:
Forecast, regular time units, overtime, and subcontract units were given.
Calculate the difference of month July:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 20 units.
Calculate the difference of month August:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 10 units.
Calculate the difference of month September:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 0 units.
Note: The calculation repeats for all the months.
Beginning inventory:
The initial inventory is given as 0. For the remaining months, ending inventory of previous month would be the beginning inventory of present month.
Ending inventory for the month of July:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 20 units.
Ending inventory for the month of August:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 20 units.
Ending inventory for the month of September:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 20 units.
Note: The calculation repeats for all the months.
Average inventory for the month of July:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 10 units.
Average inventory for the month of August:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 25 units.
Average inventory for the month of September:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 30 units.
Note: The calculation repeats for all the months.
Calculate the regular time cost for the month of July:
Regular time cost per unit is given as $40 and regular time unit is given as 300. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $12,000.
Calculate the regular time cost for the month of August:
Regular time cost per unit is given as $40 and regular time unit is given as 300. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $12,000.
Calculate the regular time cost for the month of September:
Regular time cost per unit is given as $40 and regular time unit is given as 300. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $12,000.
Note: The calculation repeats for all the months.
Calculate the total regular time cost:
It is calculated by adding the regular time cost of all the months.
Hence, the total regular time cost is $72,000.
Calculate the overtime cost for the month of July:
Overtime cost per unit is given as $50 and overtime unit is given as 20. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $1,000.
Calculate the overtime cost for the month of August:
Overtime cost per unit is given as $50 and overtime unit is given as 20. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $1,000.
Calculate the overtime cost for the month of September:
Overtime cost per unit is given as $50 and overtime unit is given as 20. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $1,000.
Note: The calculation repeats for all the months.
Calculate the total overtime cost:
It is calculated by adding the overtime cost of all the months.
Hence, the total overtime cost is $6,000.
Calculate the subcontract cost for the month of July:
Subcontract cost per unit is given as $60 and subcontract unit is given as 20. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $1,200.
Calculate the subcontract cost for the month of August:
Subcontract cost per unit is given as $60 and subcontract unit is given as 30. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $1,800.
Calculate the subcontract cost for the month of September:
Subcontract cost per unit is given as $60 and subcontract unit is given as 40. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $2,400.
Note: The calculation repeats for all the months.
Calculate the total subcontract cost:
It is calculated by adding the subcontract cost of all the months.
Hence, the total subcontract cost is $15,600.
Calculate the inventory cost for the month of July:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $100.
Calculate the inventory cost for the month of August:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $250.
Calculate the inventory cost for the month of September:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $300.
Note: The calculation repeats for all the months.
Calculate the total inventory cost:
It is calculated by adding the inventory cost of all the months.
Hence, the total inventory cost is $900.
Calculate the total cost of the plan:
It is calculated by adding the total regular time cost, overtime cost, subcontract cost, and inventory cost.
Hence, the total cost of the plan is $95,500.
c)
To compute: The total cost for each aggregate plan.
Introduction:The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
Answer to Problem 1P
Explanation of Solution
Given information:
Regular output is $40, overtime is $50, subcontract is $60, and average balance inventory is $10.
In addition to this, the following information is given:
Month | July | August | September | October | November | December |
Forecast | 320 | 340 | 360 | 380 | 400 | 400 |
Regular | 350 | 350 | 350 | 350 | 350 | 350 |
Overtime | 0 | 0 | 0 | 0 | 0 | 0 |
It is given that subcontract can be used whenever necessary.
Determine the aggregate plan to compute total cost:
Month | July | August | September | October | November | December | Total | |
Forecast | 320 | 340 | 360 | 380 | 400 | 400 | 2,200 | |
Output | ||||||||
Regular | 350 | 350 | 350 | 350 | 350 | 350 | 2,100 | |
Part-time | ||||||||
Overtime | ||||||||
Subcontract | 50 | 50 | ||||||
Difference | 30 | 10 | -10 | -30 | 0 | 0 | 0 | |
Inventory | ||||||||
Beginning | 0 | 30 | 40 | 30 | 0 | 0 | 100 | |
Ending | 30 | 40 | 30 | 0 | 0 | 0 | 100 | |
Average | 15 | 35 | 35 | 15 | 0 | 0 | 100 | |
Backlog | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Costs | ||||||||
Regular | 40 | $14,000 | $14,000 | $14,000 | $14,000 | $14,000 | $14,000 | $84,000 |
Part-time | ||||||||
Overtime | 50 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
Subcontract | 60 | $0 | $0 | $0 | $0 | $3,000 | $3,000 | $6,000 |
Hire/Layoff | ||||||||
Inventory | 10 | $150 | $350 | $350 | $150 | $0 | $0 | $1,000 |
Backorders | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
$14,150 | $14,350 | $14,350 | $14,150 | $17,000 | $17,000 | $91,000 |
Supporting calculation:
Forecast, regular time units, overtime, and subcontract units were given.
Calculate the difference of month July:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 30 units.
Calculate the difference of month August:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 10 units.
Calculate the difference of month September:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is -10 units.
Note: The calculation repeats for all the months.
Beginning inventory:
The initial inventory is given as 0. For the remaining months, ending inventory of previous month would be the beginning inventory of present month.
Ending inventory for the month of July:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 30 units.
Ending inventory for the month of August:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 40 units.
Ending inventory for the month of September:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 20 units.
Note: The calculation repeats for all the months.
Average inventory for the month of July:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 15 units.
Average inventory for the month of August:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 35 units.
Average inventory for the month of September:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 35 units.
Note: The calculation repeats for all the months.
Calculate the regular time cost for the month of July:
Regular time cost per unit is given as $40 and regular time unit is given as 350. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $14,000.
Calculate the regular time cost for the month of August:
Regular time cost per unit is given as $40 and regular time unit is given as 350. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $14,000.
Calculate the regular time cost for the month of September:
Regular time cost per unit is given as $40 and regular time unit is given as 350. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $14,000.
Note: The calculation repeats for all the months.
Calculate the total regular time cost:
It is calculated by adding the regular time cost of all the months.
Hence, the total regular time cost is $84,000.
Calculate the overtime cost for the month of July:
Overtime cost per unit is given as $50 and overtime unit is given as 0. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $0.
Calculate the overtime cost for the month of August:
Overtime cost per unit is given as $50 and overtime unit is given as 0. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $0.
Calculate the overtime cost for the month of September:
Overtime cost per unit is given as $50 and overtime unit is given as 0. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $0.
Note: The calculation repeats for all the months.
Calculate the total overtime cost:
It is calculated by adding the overtime cost of all the months.
Hence, the total overtime cost is $0.
Calculate the subcontract cost for the month of July:
Subcontract cost per unit is given as $60 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Calculate the subcontract cost for the month of August:
Subcontract cost per unit is given as $60 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Calculate the subcontract cost for the month of September:
Subcontract cost per unit is given as $60 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Note: The calculation repeats for all the months. As there are backlogs in the month of November and December, there would be 50 units of subcontracting in those months.
Calculate the total subcontract cost:
It is calculated by adding the subcontract cost of all the months.
Hence, the total subcontract cost is $15,600.
Calculate the inventory cost for the month of July:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $150.
Calculate the inventory cost for the month of August:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $350.
Calculate the inventory cost for the month of September:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $350.
Note: The calculation repeats for all the months.
Calculate the total inventory cost:
It is calculated by adding the inventory cost of all the months.
Hence, the total inventory cost is $1,000.
Calculate the total cost of the plan:
It is calculated by adding the total regular time cost, overtime cost, subcontract cost, and inventory cost.
Hence, the total cost of the plan is $91,000.
Want to see more full solutions like this?
Chapter 11 Solutions
Operations Management
- وبة واضافة هذه القيمة الى القيم Ex: Assign each job for each worker at minimum total Cost عمل لكل عامل وبأقل كلفة ممكنة obs الأعمال Workors العمال J1 J2 J3 J4 W₁ 15 13 14 12 W2 11 12 15 13 W3 13 12 10 11 W4 15 17 14 16arrow_forwardThe average completion time (flow time) for the sequence developed using the FCFS rule = 11.75 days (round your response to two decimal places). The percentage utilization for the sequence developed using the FCFS rule = 42.55 % (enter your response as a percentage rounded to two decimal places). b) Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): An Alabama lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard's schedule. In what sequence would the jobs be ranked according to the decision rules on the left: Job Due Date A 212 B 209 C 208 D 210 Duration (days) 6 3 3 8 Sequence 1 Job B 2 3 4 A D The average tardiness (job lateness) for the sequence developed using the SPT rule = 5.00 days (round your response to two decimal places). The average completion time (flow time) for the sequence developed using the SPT rule = 10.25 days…arrow_forwardWith the aid of examples, fully discuss any five (5) political tactics used in organisations.arrow_forward
- a. With the aid of examples, define discrimination. b. Fully discuss any four (4) types of discrimination in the workplacearrow_forwardRead the Following Extract and Answer the Questions that Follows:The word politics has a somewhat negative connotation. It suggests that someone is attempting touse means or to gain ends that are not sanctioned by the organisation. Political behaviour, as we’vedefined it is quite neutral. Similarly, power is not inherently negative. Whether a person viewspower and politics as unsavoury topics depends on several considerations, most important perhapsbeing where the individual stands on a specific issue in each situation. Nonetheless, most managersare reluctant to admit to political character of their own work settings.Discuss any Five (5) Political tactics you know.arrow_forwardDescribe current features of Cigna Accredo pharmacy own appraisal forms and compare the system used against the textbook’s description of desirable features of appraisal forms. What improvements would you recommend and why?arrow_forward
- Provide a recommendation of a combination of different methods of performance data that could be used to arrive at an overall score for each person being rated in cigna Accredo pharmacy. Explain the comprehensive system you have recommended and why you have chosen this combination of tools. Support your answer with research.arrow_forwardAlready got wrong answer Plz Don't use chatgptarrow_forwardThe RTY calculation for the following process steps would be: A ➡ ○ A.YA+YB+YC+YD OB. (YA)(YB)(YCYD) OC. ((YA+YB+YC+YD)/4)*4 ○ D. (1/YA)+(1/YB)+(1/YC)+YD B C Darrow_forward
- Can you guys help me with this? 1. What did you learn about the case, the concepts of transformational leadership; transactional leadership; Herzberg's Two Factors; Maslow's Hierarchy of needs theories that been applied through the case? Here is the case: Theranos (2003-2018):Overview: Theranos promised to revolutionize blood testing but was exposed formisleading claims about its technology, leading to its collapse 2. What did you learn about the case between Elon Musk and Twitter, the concepts of transformational leadership; transactional leadership; Herzberg's Two Factors Theory; Maslow's Hierarchy of needs theories that been applied through the case? 3. What did you learn about the case of Blockbuster's decline and their failure to adapt with digital streaming, the concepts of autocratic leadership; transactional leadership; Herzberg's Two Factors; Maslow's Hierarchy of needs theories that been applied through the case?arrow_forwardCan you guys help me with this? 1. What did you learn about the case, the concepts of transformational leadership; transactional leadership; Herzberg's Two Factors; and Maslow's Hierarchy of needs theories that have been applied through the case? Here is the case: The COVID-19 Pandemic Response (2020-Present): Overview: Global leaders had to navigate an unprecedented health crisis, balancingpublic health needs with economic pressures. 2. What did you learn about the case, the concepts of transformational leadership; transactional leadership; Herzberg's Two Factors Theory; and Maslow's Hierarchy of Needs theories that have been applied through the case? Here's the case: Google Glass (2013):Overview: Google launched its augmented reality glasses with high expectations, butprivacy concerns and limited functionality led to poor adoption 3. What did you learn about the case of Kodak's failure to keep up with digital photography, the concepts of autocratic leadership; transformational…arrow_forwardWith the above information do the following:1. Based on the From-To chart presented develop an ActivityRelationship Chart for this operation.2. Develop a Space-Relationship Diagram for this operation.3. Evaluate the actual layout using the “Distance Traveled byProduct” technique discussed in class (use rectilinear distance inall calculations).4. Develop two layout improvement alternatives.5. Evaluate alternatives using the “Distance Traveled by Product”technique discussed in class (use rectilinear distance in allcalculations).6. Make a layout recommendation based on alternatives evaluatedarrow_forward