Interpretation: A machine shop located on the outskirts of Los Angeles accepts custom orders from a number of high-tech firms in southern California. The machine shop consists of four departments: A (lathes), B (drills), C (grinders), and D (sanders). The from-to chart showing distances in feet between department centers is given.
To Department | |||||||
A | B | C | D | ||||
A | 45 | 63 | 32 | ||||
From Department | B | 29 | 27 | 46 | |||
C | 63 | 75 | 68 | ||||
D | 40 | 30 | 68 |
The shop has accepted orders for production of four products: P1, P2, P3 and P4. The routing for production of these products and the weekly production rates are
Product | Routing | Weekly Production |
P1 | A-B-C-D | 200 |
P2 | A-C-D | 600 |
P3 | B-D | 400 |
P4 | B-C-D | 500 |
Assuming that products are produced in batches of size 25; from the given data, a from-to chart giving numbers of materials handling trips per week between departments needs to be given.
Concept Introduction: A routing planning chart consisting of a matrix is called a from-to chart. Various operations are written across the top and along the left side of the form.
(b)
Interpretation: A machine shop located on the outskirts of Los Angeles accepts custom orders from a number of high-tech forms in southern California. The machine shop consists of four departments: A(lathes), B(drills), C(grinders), and D(sanders). The from-to chart showing distances in feet between department centers is given.
To Department | ||||||
A | B | C | D | |||
A | 45 | 63 | 32 | |||
From Department | B | 29 | 27 | 46 | ||
C | 63 | 75 | 68 | |||
D | 40 | 30 | 68 |
The shop has accepted orders for production of four products: P1, P2, P3 and P4. The routing for production of these products and the weekly production rates are
Product | Routing | Weekly Production |
P1 | A-B-C-D | 200 |
P2 | A-C-D | 600 |
P3 | B-D | 400 |
P4 | B-C-D | 500 |
Assuming that products are produced in batches of size 25, and assuming that the cost of transportation of one batch 1 foot is estimated to be $1.50; from the from-to chart derived from part (a), a from-to chart giving the materials handling cost per week between departments, needs to given.
Concept Introduction: A routing planning chart consisting of a matrix is called a from-to chart. Various operations are written across the top and along the left side of the form.
(c)
Interpretation: A machine shop located on the outskirts of Los Angeles accepts custom orders from a number of high-tech forms in southern California. The machine shop consists of four departments: A(lathes), B(drills), C(grinders), and D(sanders). The from-to chart showing distances in feet between department centers is given.
To Department | ||||||
A | B | C | D | |||
A | 45 | 63 | 32 | |||
From Department | B | 29 | 27 | 46 | ||
C | 63 | 75 | 68 | |||
D | 40 | 30 | 68 |
The shop has accepted orders for production of four products: P1, P2, P3 and P4. The routing for production of these products and the weekly production rates are
Product | Routing | Weekly Production |
P1 | A-B-C-D | 200 |
P2 | A-C-D | 600 |
P3 | B-D | 400 |
P4 | B-C-D | 500 |
Assuming that products are produced in batches of size 25, based on the results of part (b) and assuming that
Concept Introduction: A routing planning chart consisting of a matrix is called a from-to chart. Various operations are written across the top and along the left side of the form.
(d)
Interpretation: A machine shop located on the outskirts of Los Angeles accepts custom orders from a number of high-tech forms in southern California. The machine shop consists of four departments: A(lathes), B(drills), C(grinders), and D(sanders). The from-to chart showing distances in feet between department centers is given.
To Department | ||||||
A | B | C | D | |||
A | 45 | 63 | 32 | |||
From Department | B | 29 | 27 | 46 | ||
C | 63 | 75 | 68 | |||
D | 40 | 30 | 68 |
The shop has accepted orders for production of four products: P1, P2, P3 and P4. The routing for production of these products and the weekly production rates are
Product | Routing | Weekly Production |
P1 | A-B-C-D | 200 |
P2 | A-C-D | 600 |
P3 | B-D | 400 |
P4 | B-C-D | 500 |
Assuming that products are produced in batches of size 25, supposing that the machine shop is located in a building that is 60 feet by 80 feet and that departments are rectangularly shaped, with the shape of facility as in Figure 10-32, a layout consistent with the relationship chart obtained from part (c) needs to be sketched.
Concept Introduction: A routing planning chart consisting of a matrix is called a from-to chart. Various operations are written across the top and along the left side of the form.

Want to see the full answer?
Check out a sample textbook solution
Chapter 11 Solutions
EBK PRODUCTION AND OPERATIONS ANALYSIS
- Question 6. An electrical engineering company is designing two types of solar panel systems: Standard Panels (S) and High-Efficiency Panels (H). The company has certain constraints regarding the hours of labor and material available for production each week. Each Standard Panel requires 4 hours of labor and 2 units of material and each High-Efficiency Panel requires 3 hours of labor and 5 units of material. The company has a maximum of 60 hours of labor and 40 units of material available per week. The profit from each Standard Panel is GH¢80, and the profit from each High-Efficiency Panel is GH¢100. The company wants to determine how many of each type of panel to produce in order to maximize profit. i) Solve this LPP by using graphical analysis ii) What will be the slack at the optimal solution point? Show calculation.arrow_forwardqusestion 6. An electrical engineering company is designing two types of solar panel systems: Standard Panels (S) and High-Efficiency Panels (H). The company has certain constraints regarding the hours of labor and material available for production each week. Each Standard Panel requires 4 hours of labor and 2 units of material and each High-Efficiency Panel requires 3 hours of labor and 5 units of material. The company has a maximum of 60 hours of labor and 40 units of material available per week. The profit from each Standard Panel is GH¢80, and the profit from each High-Efficiency Panel is GH¢100. The company wants to determine how many of each type of panel to produce in order to maximize profit. i. Formulate a linear programming model of the problem for the company. ii Convert the linear programming model formulated in (a) to a standard form.arrow_forwardG ווח >>> Mind Tap Cengage Learning 1- CENGAGE MINDTAP Chapter 09 Excel Activity: Exponential Smoothing Question 1 3.33/10 e Submit 自 A ng.cengage.com C Excel Online Student Work G A retail store records customer demand during each sales period. 1. What is the f... Q Search this course ? ✓ Co Excel Online Tutorial Excel Online Activity: Exponential Smoothing A-Z A retail store records customer demand during each sales period. The data has been collected in the Microsoft Excel Online file below. Use the Microsoft Excel Online file below to develop the single exponential smoothing forecast and answer the following questions. Office Video X Open spreadsheet Questions 1. What is the forecast for the 13th period based on the single exponential smoothing? Round your answer to two decimal places. 25.10 2. What is the MSE for the single exponential smoothing forecast? Round your answer to two decimal places. 21.88 Activity Frame ? 3. Choose the correct graph for the single exponential…arrow_forward
- Not use ai pleasearrow_forwardItems removed from the work area (5S) were taken to a storage area called ___________. Choose from: SORT, STORD, KNUJ, STUFF, FUDG SORT STORD KNUJ STUFF FUDGarrow_forwardCould you please help explain How was the poor strategic decisions lead to economic downturns of Circuit City Company? What are the sequences of key events and problems that contribute to its collapse. Could you please explain each one them and give the examples If Circuit City would apply Lean Six Sigma. would it helped prevent businesses from collapsed?? How Qualitative and quantitative Research Methodology in Case Study Research would affect Circuit City?arrow_forward
- Apple is a global technology company renowned for its innovation and design. To create its products, Apple has established a world class global supply chain to bring their products to market. What strategies is Apple using to source and manufacture its products? How does Apple view its responsibility to its suppliers and those who build its products?arrow_forwardCritical Path Method (CPM) is an important Project Management Tool that has wide industry application in modern day Project Management. By using an example of the project of your choice, critically examine the practical application of CPM as a Project Management Tool.arrow_forwardwhat is an other difination for principle?arrow_forward
- Need help or ideas to design out two slides as my script and writing quite long to squeese into two slides. But can just point form in slides with correct title and a good script for me to present two slides in only 2.5 mins. Following is my draft, pls guide me step by step on powerpoint creation and good script to present findings. My draft: Slide 1: Foreign Labor Exploitation in Dyson's Supply Chain Introduction Dyson's former Malaysian supplier, ATA IMS Bhd, became embroiled in serious labor exploitation allegations in 2021. These concerns surfaced when whistleblowers exposed unethical labor practices affecting migrant workers, primarily from Nepal and Bangladesh. Key Forms of Exploitation Debt Bondage Due to Recruitment Fees Workers were forced to pay exorbitant recruitment fees before securing employment, often taking loans at high interest rates. This financial burden trapped them in debt bondage, leaving them with little choice but to accept exploitative working…arrow_forwardNot use ai pleasearrow_forwardThe Business Development Bank of Canada. (2023). Canadian economic outlook for 2024: Shifting into neutral. https://www.bdc.ca/en/articles-tools/blog/canadian-economic-outlook-for-2024-shifting-into-neutral “Despite persistently high inflation and rising interest rates, the news was generally better than expected for the Canadian economy in 2023” (BDC Blog 2024). Discussion Question: In your view, what are the most pressing problems for Canadian companies or consumers in 2024? Explain your answer using current examples of companies or consumer concerns.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningMarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing