Interpretation: A real estate firm wishes to open four new offices in Boston area and they are having six potential sites available. Based on the number of employees in each office and the location of the properties that each employee will manage, the firm estimated the total travel time in hours per day for each office and each location. The optimal assignment of offices to sites to minimize employee travel time needs to be determined.
Offices | |||||
A | B | C | D | ||
1 | 10 | 3 | 3 | 8 | |
2 | 13 | 5 | 2 | 6 | |
Sites | 3 | 12 | 9 | 9 | 4 |
4 | 14 | 2 | 7 | 7 | |
5 | 17 | 7 | 4 | 3 | |
6 | 12 | 8 | 5 | 5 |
Concept Introduction: A discrete facility location problem is considered, when a balance has to be achieved between the minimum and maximum number of customers, wherein there is a difference that arises between the allocation of these customers made to every plant.

Answer to Problem 46AP
The optimal travel time has been derived as 17.
Explanation of Solution
Given information:
Offices | |||||
A | B | C | D | ||
1 | 10 | 3 | 3 | 8 | |
2 | 13 | 5 | 2 | 6 | |
Sites | 3 | 12 | 9 | 9 | 4 |
4 | 14 | 2 | 7 | 7 | |
5 | 17 | 7 | 4 | 3 | |
6 | 12 | 8 | 5 | 5 |
When there are no inter-departmental interactions and a discrete set of alternative locations could be considered, then assignment problems can be considered to be appropriate. Following are the procedure for solution for assignment problems:
- The smallest number in row 1 needs to be identified and it should be subtracted from all the entries in that row. This procedure needs to be repeated for all the rows in cost matrix.
- Similarly, the smallest number in column 1 needs to be identified and it should be subtracted from all the entries in column 1. This procedure needs to be repeated for all the columns in cost matrix.
- At a certain point, each column and each row will have at least a zero. If there is possibility for making a zero assignment, then the same can be done, which in turn will be the optimal solution, and if not, then proceed to the next step.
- The maximum number of zero cost assignments needs to be determined, which will be equal to smallest number of lines adequate to cover all zeros. These lines are not necessarily unique and are found by inspection. The number of lines drawn should be less than the maximum number of zero cost assignments.
- The smallest uncovered number should be identified and proceed with the following steps:
- Subtract smallest uncovered number from all the other uncovered numbers.
- Add this to the step at the point where the line crosses.
- Return back to step 3
Step 1: The below shown matrix, not being a square matrix, dummy rows to balance the sites and offices are added.
Offices | ||||
Sites | A | B | C | D |
1 | 10 | 3 | 3 | 8 |
2 | 13 | 5 | 2 | 6 |
3 | 12 | 9 | 9 | 4 |
4 | 14 | 2 | 7 | 7 |
5 | 17 | 7 | 4 | 3 |
6 | 12 | 8 | 5 | 5 |
By adding the dummy rows the matrix has been modified as shown below:
Offices | ||||||
Sites | A | B | C | D | E | F |
1 | 10 | 3 | 3 | 8 | 0 | 0 |
2 | 13 | 5 | 2 | 6 | 0 | 0 |
3 | 12 | 9 | 9 | 4 | 0 | 0 |
4 | 14 | 2 | 7 | 7 | 0 | 0 |
5 | 17 | 7 | 4 | 3 | 0 | 0 |
6 | 12 | 8 | 5 | 5 | 0 | 0 |
Step 2: The row reducing matrix needs to be performed by subtracting the smallest number from each row. Since in this case, the resultant zero assignment has been achieved for each office, further column reduction matrix is not performed.
Offices | ||||||
Sites | A | B | C | D | E | F |
1 | 0 | 1 | 1 | 5 | 0 | 0 |
2 | 3 | 3 | 0 | 3 | 0 | 0 |
3 | 2 | 7 | 7 | 1 | 0 | 0 |
4 | 4 | 0 | 5 | 4 | 0 | 0 |
5 | 7 | 5 | 2 | 0 | 0 | 0 |
6 | 2 | 6 | 3 | 2 | 0 | 0 |
Step 3: From each site identifying of the zero assignment gives the following matrix
Offices | ||||||
Sites | A | B | C | D | E | F |
1 | 1 | 1 | 5 | 0 | 0 | |
2 | 3 | 3 | 3 | 0 | 0 | |
3 | 2 | 7 | 7 | 1 | ![]() | 0 |
4 | 4 | ![]() | 5 | 4 | 0 | 0 |
5 | 7 | 5 | 2 | ![]() | 0 | 0 |
6 | 2 | 6 | 3 | 2 | 0 | ![]() |
Thus the optimal solution for travel time will be
Want to see more full solutions like this?
Chapter 11 Solutions
Production and Operations Analysis, Seventh Edition
- Note: A waiting line model solver computer package is needed to answer these questions. The Kolkmeyer Manufacturing Company uses a group of six identical machines, each of which operates an average of 23 hours between breakdowns. With randomly occurring breakdowns, the Poisson probability distribution is used to describe the machine breakdown arrival process. One person from the maintenance department provides the single-server repair service for the six machines. Management is now considering adding two machines to its manufacturing operation. This addition will bring the number of machines to eight. The president of Kolkmeyer asked for a study of the need to add a second employee to the repair operation. The service rate for each individual assigned to the repair operation is 0.40 machines per hour. (a) Compute the operating characteristics if the company retains the single-employee repair operation. (Round your answers to four decimal places. Report time in hours.) La = L = Wa W = h…arrow_forwardBurger Dome sells hamburgers, cheeseburgers, french fries, soft drinks, and milk shakes, as well as a limited number of specialty items and dessert selections. Although Burger Dome would like to serve each customer immediately, at times more customers arrive than can be handled by the Burger Dome food service staff. Thus, customers wait in line to place and receive their orders. Burger Dome analyzed data on customer arrivals and concluded that the arrival rate is 40 customers per hour. Burger Dome also studied the order-filling process and found that a single employee can process an average of 56 customer orders per hour. Burger Dome is concerned that the methods currently used to serve customers are resulting in excessive waiting times and a possible loss of sales. Management wants to conduct a waiting line study to help determine the best approach to reduce waiting times and improve service. Suppose Burger Dome establishes two servers but arranges the restaurant layout so that an…arrow_forwardAgan Interior Design provides home and office decorating assistance to its customers. In normal operation, an average of 2.6 customers arrive each hour. One design consultant is available to answer customer questions and make product recommendations. The consultant averages 10 minutes with each customer. (a) Compute the operating characteristics of the customer waiting line, assuming Poisson arrivals and exponential service times. (Round your answers to four decimal places. Report time in hours.) λ= μ = = L = Wa W = P. W h (b) Service goals dictate that an arriving customer should not wait for service more than an average of 5 minutes. Is this goal being met? (Round your answer to one decimal place.) W₁ (in minutes) = min, which is ---Select--- than the desired wait time, so the goal ---Select--- met. What action do you recommend? (Select all that apply.) Hire another consultant. Increase the hours of operation. Decrease the mean service rate. Increase the mean service rate. There is…arrow_forward
- Communication Tips (2015) Tactful bragging Respond to the question "So, what do you do?" Whether you are student or have a job/internship, how can you tactfully brag in your answer to this question? Use the three elements from the video (listed below) when crafting your brag statement: Focus on results vs title Process vs job description Loop back to listener Example of an instructor's brag statement: "I help hundreds of students each semester to connect with one another, develop communication skills and prepare for upcoming interviews. Through improv games we explore presence, flexibility, and storytelling. How have your networking experiences on campus been so far?"arrow_forwardAccounting problemarrow_forwardGovernment's new plan to shift cargo from roads back to rail 26TH JANUARY 2024 Government is seeking to finalise a plan aimed at improving its rail network and move cargo away from a billion rand per day to its logistics crises, government has said an urgentturnaround is needed to improve its 31 000km locomotive network as more and more cargo moves from rail to trucks. The Department of Transport (DoT) hosted a discussion with industry stakeholders regarding the Freight Road to Rail Migration Plan on Thursday - the latest development in the wake of President Cyril Ramphosa forming the National Logistics Crisis Committee last year. Transnet, the South African National Roads Agency (Sanral) and private sector companies were all in attendance. The Freight Road to Rail Migration Plan is part of government's strategies to improve the country's ongoing logistics crises. In October last year, the government unveiled its Freight Logistics Roadmap to improve the ports and rail networks and…arrow_forward
- Assess what led to such logistical inefficiencies / collapse of a previously world class freight networkarrow_forwardWhich of the following statements concerning the evaluation of training programs is true? Most companies thoroughly evaluate the return on investment of their training programs It is relatively easy to establish a control group and a treatment group for evaluation Results level of evaluation measures how well participants liked the program Behavior level criteria measure whether skills learned in training result in behavior changes back on the jobarrow_forwardEligibility testing is an disparate impact validation method none of the above a method to validate promotions and progressive discipline activity a test an employee administers to ensure that the potential employee is capable and qualified to perform the requirements of the positionarrow_forward
- A no-strike pledge by a union in a collective bargaining agreement is given in return for management’s agreement to: a grievance procedure a union shop a wage increase a fringe benefit increase binding arbitration of grievancesarrow_forwardWhich is the major OD technique that is used for increasing the communication, cooperation, and cohesiveness of work units? Leadership analysis Developing objectives Groupthink Strategic Planning team Buildingarrow_forwardAn American multinational firm usually is less than fully successful in adapting itself to local practices in each country because: American managers are often ignorant of local conditions None of the above management direction may be centralized in the home office All of the above Foreign subsidiaries often have American managersarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningManagement, Loose-Leaf VersionManagementISBN:9781305969308Author:Richard L. DaftPublisher:South-Western College Pub