Chapter 11, Problem 48AP

(a)

Summary Introduction

Interpretation: A machine shop located on the outskirts of Los Angeles accepts custom orders from a number of high-tech firms in southern California. The machine shop consists of four departments: A (lathes), B (drills), C (grinders), and D (sanders). The from-to chart showing distances in feet between department centers is given.

    To Department
     ABCD
    A456332
    From DepartmentB292746
    C637568
    D403068

The shop has accepted orders for production of four products: P1, P2, P3 and P4. The routing for production of these products and the weekly production rates are

    ProductRoutingWeekly Production
    P1A-B-C-D200
    P2A-C-D600
    P3B-D400
    P4B-C-D500

Assuming that products are produced in batches of size 25; from the given data, a from-to chart giving numbers of materials handling trips per week between departments needs to be given.

Concept Introduction: A routing planning chart consisting of a matrix is called a from-to chart. Various operations are written across the top and along the left side of the form.

(b)

Summary Introduction

Interpretation: A machine shop located on the outskirts of Los Angeles accepts custom orders from a number of high-tech forms in southern California. The machine shop consists of four departments: A(lathes), B(drills), C(grinders), and D(sanders). The from-to chart showing distances in feet between department centers is given.

    To Department
     ABCD
    A456332
    From DepartmentB292746
    C637568
    D403068

The shop has accepted orders for production of four products: P1, P2, P3 and P4. The routing for production of these products and the weekly production rates are

    ProductRoutingWeekly Production
    P1A-B-C-D200
    P2A-C-D600
    P3B-D400
    P4B-C-D500

Assuming that products are produced in batches of size 25, and assuming that the cost of transportation of one batch 1 foot is estimated to be $1.50; from the from-to chart derived from part (a), a from-to chart giving the materials handling cost per week between departments, needs to given.

Concept Introduction: A routing planning chart consisting of a matrix is called a from-to chart. Various operations are written across the top and along the left side of the form.

(c)

Summary Introduction

Interpretation: A machine shop located on the outskirts of Los Angeles accepts custom orders from a number of high-tech forms in southern California. The machine shop consists of four departments: A(lathes), B(drills), C(grinders), and D(sanders). The from-to chart showing distances in feet between department centers is given.

    To Department
     ABCD
    A456332
    From DepartmentB292746
    C637568
    D403068

The shop has accepted orders for production of four products: P1, P2, P3 and P4. The routing for production of these products and the weekly production rates are

    ProductRoutingWeekly Production
    P1A-B-C-D200
    P2A-C-D600
    P3B-D400
    P4B-C-D500

Assuming that products are produced in batches of size 25, based on the results of part (b) and assuming that A is assigned to the highest cost and O to the least, with rankings E and I assigned to the costs falling in between the extremes, an activity relationship chart for the four departments needs to be developed.

Concept Introduction: A routing planning chart consisting of a matrix is called a from-to chart. Various operations are written across the top and along the left side of the form.

(d)

Summary Introduction

Interpretation: A machine shop located on the outskirts of Los Angeles accepts custom orders from a number of high-tech forms in southern California. The machine shop consists of four departments: A(lathes), B(drills), C(grinders), and D(sanders). The from-to chart showing distances in feet between department centers is given.

    To Department
     ABCD
    A456332
    From DepartmentB292746
    C637568
    D403068

The shop has accepted orders for production of four products: P1, P2, P3 and P4. The routing for production of these products and the weekly production rates are

    ProductRoutingWeekly Production
    P1A-B-C-D200
    P2A-C-D600
    P3B-D400
    P4B-C-D500

Assuming that products are produced in batches of size 25, supposing that the machine shop is located in a building that is 60 feet by 80 feet and that departments are rectangularly shaped, with the shape of facility as in Figure 10-32, a layout consistent with the relationship chart obtained from part (c) needs to be sketched.

Concept Introduction: A routing planning chart consisting of a matrix is called a from-to chart. Various operations are written across the top and along the left side of the form.

Blurred answer
Students have asked these similar questions
What should leaders do after conducting an employee survey?   take immediate action on results   take at least 6 months to review the results to make sure the leader understands them   review them immediately, but do not take action right away   keep results confidential from employees
One of the best ways to encourage teamwork is to:   continually promote from outside of the department   recognize employees who focus on their personal performance goals only   reward employees who complete their own tasks and also assist with problems outside of their department   discuss individual performance issues at staff meetings
What can happen if a leader doesn't encourage teamwork?   team members will support each other more    the environment can become overly competitive and hostile   turnover will descrease   team members become more motivated
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    Practical Management Science
    Operations Management
    ISBN:9781337406659
    Author:WINSTON, Wayne L.
    Publisher:Cengage,
    Text book image
    Purchasing and Supply Chain Management
    Operations Management
    ISBN:9781285869681
    Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
    Publisher:Cengage Learning
    Text book image
    Marketing
    Marketing
    ISBN:9780357033791
    Author:Pride, William M
    Publisher:South Western Educational Publishing
  • Text book image
    MARKETING 2018
    Marketing
    ISBN:9780357033753
    Author:Pride
    Publisher:CENGAGE L
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L