Operations Management: Processes and Supply Chains, Student Value Edition Plus MyLab Operations Management with Pearson eText -- Access Card Package (12th Edition)
12th Edition
ISBN: 9780134855424
Author: Lee J. Krajewski, Manoj K. Malhotra, Larry P. Ritzman
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 11, Problem 1AME
Suppose that the POQ for item B is changed from 3 weeks to 2 weeks. How does this change affect the order releases for items B, C, and D?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The planned order receipt for item A is 200 in week 5 and the lead time is 3 weeks. Which week should the planned order release be?
What will be projected on hand inventory of item S in week6?
Complete the following table. Lead time for the part is 2 weeks, and the order quantity is 50. What action should be taken?
Chapter 11 Solutions
Operations Management: Processes and Supply Chains, Student Value Edition Plus MyLab Operations Management with Pearson eText -- Access Card Package (12th Edition)
Ch. 11 - Consider the master flight schedule of a major...Ch. 11 - For an organization of your choice, such as where...Ch. 11 - Consider a service provider that is in the...Ch. 11 - Complete the MPS record in Figure 11.29 for a...Ch. 11 - Complete the MPS record in Figure 11.30 for a...Ch. 11 - Prob. 3PCh. 11 - Figure 11.31 shows a partially completed MPS...Ch. 11 - Tabard Industries forecasted the following demand...Ch. 11 - Figure 11.32 shows a partially completed MPS...Ch. 11 - The forecasted requirements for an electric hand...
Ch. 11 - A forecast of 240 units in January, 320 units in...Ch. 11 - An end items demand forecasts for the next 6 weeks...Ch. 11 - An end items demand forecasts for the next 10...Ch. 11 - Consider the bill of materials (BOM) in Figure...Ch. 11 - Product A is made from components B, C, and D....Ch. 11 - What is the lead time (in weeks) to respond to a...Ch. 11 - Product A is made from components B and C. Item B,...Ch. 11 - Refer to Figure 11.23 and Solved Problem 1. If...Ch. 11 - The partially completed inventory record for the...Ch. 11 - The partially completed inventory record for the...Ch. 11 - The partially completed inventory record for the...Ch. 11 - Figure 11.38 shows a partially completed inventory...Ch. 11 - A partially completed inventory record for the...Ch. 11 - The BOM for product A is shown in Figure 11.40,...Ch. 11 - The BOMs for products A & B and data from the...Ch. 11 - Figure 11.42 illustrates the BOM for product A....Ch. 11 - The following information is available for three...Ch. 11 - Figure 11.44 shows the BOMs for two products, A...Ch. 11 - The BOM for product A is shown in Figure 11.45....Ch. 11 - Refer to Solved Problem 1 (Figure 11.23) for the...Ch. 11 - The bill of materials and the data from the...Ch. 11 - The bill of materials and the data from the...Ch. 11 - The McDuff Credit Union advertises their ability...Ch. 11 - Suppose that the POQ for item B is changed from 3...Ch. 11 - As the on-hand inventory for item C increases from...Ch. 11 - As the fixed order quantity (FOQ) for item D...Ch. 11 - As the lead time for item C changes, what happens...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Figure shows a partially completed MPS record for 2 inch pneumatic control valves. Suppose that you receive the following orders at right for the valves (shown in the order of their arrival). As they arrive, you must decide whether to accept or reject them. Which orders would you accept for shipment?Order Amount (Units) Week Requested1 15 22 30 53 25 34 75 7arrow_forwardDescribe the differences among planned orders, released orders, and firm planned orders. Whocontrols each?arrow_forwardOne unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is used for Items A, B, and F; lots of size 50, 50, and 175 are used for Items C, D, and E, respectively. Items C, E, and F have on-hand (beginning) inventories of 10, 50, and 160, respectively; all other items have zero beginning inventory. We are scheduled to receive 10 units of A in Week 2, 50 units of E in Week 1, and also 40 units of F in Week 1. There are no other scheduled receipts. If 30 units of A are required in Week 8: a. Develop an MRP table in excel.arrow_forward
- One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is used for Items A, B, and F; lots of size 55, 55, and 200 are used for Items C, D, and E, respectively. Items C, E, and F have on-hand (beginning) inventories of 10, 50, and 160, respectively; all other items have zero beginning inventory. We are scheduled to receive 10 units of A in Week 2, 60 units of E in Week 1, and also 50 units of F in Week 1. There are no other scheduled receipts. If 32 units of A are required in Week 8, use the low-level-coded bill of materials to find the necessary planned order releases for all componentsarrow_forwardOne unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is used for items A, B, and F; lots of size 50, 50, and 200 are used for Items C, D, and E, respectively. Items C, E, and F have on-hand (beginning) inventories of 10, 50, and 150, respectively; all other items have zero beginning inventory. We are scheduled to receive 10 units of A in week 2, 50 units of E in week 1, and also 50 units of F in week 1. There are no other scheduled receipts. If 30 units ofA are required in week 8, use the low-level-coded bill-of-materials to find the necessaryplanned-order releases for all components.arrow_forwardPrepare a master schedule based on the following information: Week 1 2 3 4 5 6 7 8 Forecast 1000 1000 1200 1200 1500 1500 1800 1800 Orders 1060 940 650 400 210 90 20 0 1. Currently there are 1450 units in inventory. Policy calls for a fixed order quantity of 2500 units. 2. Can you receive another order for 500 items in week 1? Why? 3. How many orders can be received in each period without altering the plan. 4. If there are 2500 items in stock, what would be the answer of questions 2 and 3?arrow_forward
- The gross requirements for item A are specified for the beginning of weeks 1 through 12 in the table that follows. Item A, Level 0 01 02 03 04 05 06 07 08 09 10 11 12 0 60 0 50 0 70 0 40 0 60 0 50 60 ? ? ? ? ? ? ? ? ? ? ? ???????????? Gross requirements. Projected on hand Planned order release The lead time is 2 weeks. The current on hand inventory, at the beginning of week 1 is 60 units. If the order cost is $80 per order and the inventory cost is $1 per unit per period, and the order quantity is the computed part period (or a multiple of the computed part period) when it is necessary to place an order, what is the total cost for the 12 week period? Answer:arrow_forwardWhat is the projected on-hand inventory amount in Week 2?arrow_forwardComplete the master productin schedule based on thefollowing information:Week 1 2 3 4 5 6 7 8 9Forecast 320 100 30 110 40 240 290 60 410Customer Orders 60 50 80 20 60 60 0 0 0Projected On-Hand Inventory 600MPS ReleasedMPS DueAvailable-to-promise (ATP) Scheduled production whenever projected on-had inventory drops below 30MPS lot size: 300Production lead time or lead time for MPS releases 1arrow_forward
- A company produces skateboards. Each skateboard (A) consists of one unit of board (B), and two units of sub-assembly of roller-set (C). Roller-sets comprise of 2 components: 2 rollers (D) and one axle (E). The MPS is as follows: Week 1 2 3 4 5 6 7 8 9 10 A D 40 50 60 80 What are the planned order releases for item A? A has an on-hand inventory of 10, safety stock of 0. The lead time is 1 week and the ordering policy is Lot-for-Lot (L4L).arrow_forwardA firm has the following gross requirements for Item F. If ordering costs are $60 per order and carrying costs are $0.50 per period. If Mult. 60 lot sizing is used, the planned order releases is Group of answer choices 60 in period 2 and 80 in period 3 120 in period 2 and 60 in period 3 80 in period 1 and 0 in period 3 0 in period 1 and 40 in period 3arrow_forwardCan you assist me with Problem 5arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY