Textbook Question
Chapter 11, Problem 14P
Product A is made from components B and C. Item B, in turn, is made from D and E. Item C also is an intermediate item, made from F and H. Finally, intermediate item E is made from H and G. Note that item H has two parents. The following are item lead times:
- What lead time (in weeks) is needed to respond to a customer order for product A, assuming no existing inventories or
scheduled receipts? - What is the customer response time if all purchased items (i.e., D, F, G, and H) are in inventory?
- If you are allowed to keep just one purchased item in stock, which one would you choose?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The planned order receipt for item A is 200 in week 5 and the lead time is 3 weeks. Which week should the planned order release be?
A company produces skateboards. Each skateboard (A) consists of one unit of board (B), and two units of sub-assembly of roller-set (C). Roller-sets comprise of 2
components: 2 rollers (D) and one axle (E). The MPS is as follows:
Week
1
2
3
4
5
6
7
8
9
10
A
D
40
50
60
80
What are the planned order releases for item A? A has an on-hand inventory of 10, safety stock of 0. The lead time is 1 week and the ordering policy is Lot-for-Lot
(L4L).
Draw an approximate bill-of-materials (BOM) for a kid’s toy of your choice following these requirements: I would like to use the Jollibee plush Bee toy.
(a) clearly label the end item and each component,
(b) the BOM must contain no more than 20 items,
(c) the BOM must contain at least three levels (you may count the end-item level zero).
Chapter 11 Solutions
Operations Management: Processes and Supply Chains, Student Value Edition Plus MyLab Operations Management with Pearson eText -- Access Card Package (12th Edition)
Ch. 11 - Consider the master flight schedule of a major...Ch. 11 - For an organization of your choice, such as where...Ch. 11 - Consider a service provider that is in the...Ch. 11 - Complete the MPS record in Figure 11.29 for a...Ch. 11 - Complete the MPS record in Figure 11.30 for a...Ch. 11 - Prob. 3PCh. 11 - Figure 11.31 shows a partially completed MPS...Ch. 11 - Tabard Industries forecasted the following demand...Ch. 11 - Figure 11.32 shows a partially completed MPS...Ch. 11 - The forecasted requirements for an electric hand...
Ch. 11 - A forecast of 240 units in January, 320 units in...Ch. 11 - An end items demand forecasts for the next 6 weeks...Ch. 11 - An end items demand forecasts for the next 10...Ch. 11 - Consider the bill of materials (BOM) in Figure...Ch. 11 - Product A is made from components B, C, and D....Ch. 11 - What is the lead time (in weeks) to respond to a...Ch. 11 - Product A is made from components B and C. Item B,...Ch. 11 - Refer to Figure 11.23 and Solved Problem 1. If...Ch. 11 - The partially completed inventory record for the...Ch. 11 - The partially completed inventory record for the...Ch. 11 - The partially completed inventory record for the...Ch. 11 - Figure 11.38 shows a partially completed inventory...Ch. 11 - A partially completed inventory record for the...Ch. 11 - The BOM for product A is shown in Figure 11.40,...Ch. 11 - The BOMs for products A & B and data from the...Ch. 11 - Figure 11.42 illustrates the BOM for product A....Ch. 11 - The following information is available for three...Ch. 11 - Figure 11.44 shows the BOMs for two products, A...Ch. 11 - The BOM for product A is shown in Figure 11.45....Ch. 11 - Refer to Solved Problem 1 (Figure 11.23) for the...Ch. 11 - The bill of materials and the data from the...Ch. 11 - The bill of materials and the data from the...Ch. 11 - The McDuff Credit Union advertises their ability...Ch. 11 - Suppose that the POQ for item B is changed from 3...Ch. 11 - As the on-hand inventory for item C increases from...Ch. 11 - As the fixed order quantity (FOQ) for item D...Ch. 11 - As the lead time for item C changes, what happens...
Additional Business Textbook Solutions
Find more solutions based on key concepts
Many companies including Company OM tried to implement dynamic pricing in their ticketing system. The dynamic p...
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
What are the three major business functions, and how are they related to one another? Give specific examples.
Operations Management, Binder Ready Version: An Integrated Approach
The flowchart for the process at the local car wash. Introduction: Flowchart: A flowchart is a visualrepresenta...
Principles Of Operations Management
2. Identify four people who have contributed to the theory and techniques of operations management.
Operations Management: Sustainability and Supply Chain Management (12th Edition)
What is precedent, and how does it affect common law?
Business in Action
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Assume you are the manager of a shop that assembles power tools. You have just received an order for 55 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws follows: Item Lead Time (weeks) On Hand Saw A B C D E F 2 1 2 2 1 1 2 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipt Planned order release Ĉ E(3) & E(2) LT = 1 week Lot size: Lot-for-Lot 15 10 5 65 20 10 30 Skip Extension Tip: Double click to open in new tab Show Transcribed Text Develop the material requirements plan for component E using lot-for-lot ordering for all items. (Leave no cells blank - be certain to enter "0" wherever required.) Components A(2), B(1), C(4) E(3), D(1) D (2), F(3) E(2), D (2) Beg. Inv. 1 2 3 190 5 210 6arrow_forwardFor the Toy Car table above, what are the Planned Order Receipts in the week of 8/31? For the Toy Car table above, what are the Planned Order Releases in the week of 9/21? For the Wheel Assembly table above, what are the Gross Requirements in the week of 9/7? For the Wheel Assembly table above, what is the Projected On-Hand Inventory in the week of 8/31? For the Wheel Assembly table above, what are the Net Requirements in the week of 8/24? For the Axle table above, what are the Gross Requirements in the week of 9/7? For the Axle table above, what are the Gross Requirements in the week of 9/14? For the Axle table above, what are the Planned Order Releases in the week of 8/17?arrow_forwardOne unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is used for Items A, B, and F; lots of size 50, 50, and 175 are used for Items C, D, and E, respectively. Items C, E, and F have on-hand (beginning) inventories of 10, 50, and 160, respectively; all other items have zero beginning inventory. We are scheduled to receive 10 units of A in Week 2, 50 units of E in Week 1, and also 40 units of F in Week 1. There are no other scheduled receipts. If 30 units of A are required in Week 8: a. Develop an MRP table in excel.arrow_forward
- One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is used for Items A, B, and F; lots of size 55, 55, and 200 are used for Items C, D, and E, respectively. Items C, E, and F have on-hand (beginning) inventories of 10, 50, and 160, respectively; all other items have zero beginning inventory. We are scheduled to receive 10 units of A in Week 2, 60 units of E in Week 1, and also 50 units of F in Week 1. There are no other scheduled receipts. If 32 units of A are required in Week 8, use the low-level-coded bill of materials to find the necessary planned order releases for all componentsarrow_forwardOne unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is used for items A, B, and F; lots of size 50, 50, and 200 are used for Items C, D, and E, respectively. Items C, E, and F have on-hand (beginning) inventories of 10, 50, and 150, respectively; all other items have zero beginning inventory. We are scheduled to receive 10 units of A in week 2, 50 units of E in week 1, and also 50 units of F in week 1. There are no other scheduled receipts. If 30 units ofA are required in week 8, use the low-level-coded bill-of-materials to find the necessaryplanned-order releases for all components.arrow_forwardAs the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs, and 4 clamps. The base is assembled from 2 clamps and 1 housing. Each clamp has 1handle and 1 casting. Each housing has 2 bearings and 2 shafts. There is no inventory on hand. c) Compute the net quantities needed if there are 25 of the base and 100 of the clamp in stock. Base: units (enter your response as a whole number). Spring: units Clamp: units Housing: units Handle units Casting: units Bearing: units Shaft: unitsarrow_forward
- As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs, and 4 clamps. The base is assembled from 1 clamp and\ 1 housing. Each clamp has 1 handle and 2 castings.Each housing has 1 bearing and 2 shafts.There is no inventory on hand. C) Compute the net quantities needed if there are 25 of the base and 75 of the clamp in stock. (Product structure picture attached) Base = (?) units Spring = (?) units Clamp = (?) units Housing = (?) units Handle = (?) units Casting = (?) units Bearing = (?) units Shaft = (?) unitsarrow_forwardThe Alpha Beta Company produces two products; A and B, that are made from components C and D. Given the follow-ing product structures, master scheduling requirements, and inventory information, determine when orders shouldbe released for A, B, C, and D and the size of those orders.arrow_forwardHelp me with this practice problem. Please provide pictures of you doing the problem so I can better understand how to complete it. Please show equations and be clear. Thank you so much,arrow_forward
- Product A is an end item and is made from two units of B and four of C. B is made ofthree units of D and two of E. C is made of two units of F and two of E.A has a lead time of one week. B, C, and E have lead times of two weeks, and D andF have lead times of three weeks.a. Show the bill-of-materials (product structure tree).b. If 100 units of A are required in Week 10, develop the MRP planning schedule, specifyingwhen items are to be ordered and received. There are currently no units of inventoryon hand.arrow_forwardGreen Gardens' owner has asked your advice about a possible problem at his business. Over the last 6 months the large-sized lawn and garden inventory (ie, tables, chairs, planters, etc.) has appeared to be short. The inventory records that employees use to determine what is on hand show that more inventory is available than can actually be located. This has cause frustration and mis-trust in the inventory records for the sales employees. The owner realizes that the problem is bigger than just frustrated employees. He is afraid that inventory is being stolen, a problem he didn't think possible given that these are large items that are not easily moved. Requirements: Provide the owner with two internal controls that he could implement to reduce the likelihood of theft of the lawn and garden inventory.arrow_forwardMpho is an avid seamstress and want to sew and sell high quality, reusable designer face masks during the current Covid-19 pandemic. She will design and sew the masks herself and use her automatic embroidery machine to put her logo on each mask sold. With the help of her son, deliveries will be made all over Gauteng within 3 days of placing the order. Every mask will have a unique three-layer design with adjustable straps to ensure comfort and it. Mpho’s only expenseis the material needed to sew the masks and delivery costs. At this stage, Mpho’starget market is limited to Gauteng. Draw a diagram to illustrate the transformation process of Mpho’s new business. Be sure to include all relevant elements, headings and arrows to indicate the flow of products/ services. Question: 1. Draw a diagram to illustrate the transformation process of Mpho’s new business. Be sure to include all relevant elements, headings and arrows to indicate the flow of products/ services.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY