Concept explainers
To determine: The impact on capability of the process if the problems are rectified and to compute the potential process capability using the second data set.
Introduction
Company TT is a division of company DM. It was about to launch a new product. Ms. MY, the
Table 1
Sample | Mean | Range |
1 | 45.01 | 0.85 |
2 | 44.99 | 0.89 |
3 | 45.02 | 0.86 |
4 | 45 | 0.91 |
5 | 45.04 | 0.87 |
6 | 44.98 | 0.9 |
7 | 44.91 | 0.86 |
8 | 45.04 | 0.89 |
9 | 45 | 0.85 |
10 | 44.97 | 0.91 |
11 | 45.11 | 0.84 |
12 | 44.96 | 0.87 |
13 | 45 | 0.86 |
14 | 44.92 | 0.89 |
15 | 45.06 | 0.87 |
16 | 44.94 | 0.86 |
17 | 45 | 0.85 |
18 | 45.03 | 0.88 |
Quiet disappointed with the end results, the manager was figuring out ways to improve the process and free the capital expenditure of $10,000. A former professor suggested going for more samples with less sample sizes. JM conducted the analysis on27 samples of 5 observations each and the results are tabulated below:
Table 2
Sample | Mean | Range |
1 | 44.96 | 0.42 |
2 | 44.98 | 0.39 |
3 | 44.96 | 0.41 |
4 | 44.97 | 0.37 |
5 | 45.02 | 0.39 |
6 | 45.03 | 0.4 |
7 | 45.04 | 0.39 |
8 | 45.02 | 0.42 |
9 | 45.08 | 0.38 |
10 | 45.12 | 0.4 |
11 | 45.07 | 0.41 |
12 | 45.02 | 0.38 |
13 | 45.01 | 0.41 |
14 | 44.98 | 0.4 |
15 | 45 | 0.39 |
16 | 44.95 | 0.41 |
17 | 44.94 | 0.43 |
18 | 44.94 | 0.4 |
19 | 44.87 | 0.38 |
20 | 44.95 | 0.41 |
21 | 44.93 | 0.39 |
22 | 44.96 | 0.41 |
23 | 44.99 | 0.4 |
24 | 45 | 0.44 |
25 | 45.03 | 0.42 |
26 | 45.04 | 0.38 |
27 | 45.03 | 0.4 |
Want to see the full answer?
Check out a sample textbook solutionChapter 10 Solutions
OPERATIONS MANAGEMENT (LL) W/CONNECT
- A process at Printwright, Inc.’s largest facility is used to make plastic gears for a computer printer. The data found in the worksheet Prob. 9-15 were gathered by a quality analyst. The gears were designed to be 3.57 ` 0.05 centimeters (cm) in diameter. Construct a histogram of the data. What can you observe about the shape of the dis- tribution? What would you recommend to the production manager based on your analysis?arrow_forwardA quality analyst wants to construct a sample mean chart for controlling a packaging process. Each day last week, he randomly selected four packages and weighed each. The raw data (in ounces) from that quality control activity appear below. Weight Day Package 1 Package 2 Package 3 Package 4 Monday 23 22 23 24 Tuesday 23 21 19 21 Wednesday 20 19 20 21 Thursday 18 19 20 19 Friday 18 20 22 20 What is the average of sample ranges in the random samples? Must compute each value in 2 dec pl.arrow_forward24. Each of the processes listed is non-centered with respect to the specifications for that process. Compute the appropri ate capability index for each, and decide if the process is capable. Process Mean Standard Deviation Lower Spec Upper Spec H 15.0 0.32 14.1 16.0 K 33.0 1.00 30.0 36.5 18.5 0.40 16.5 20.1 25. An appliance manufacturer wants to contract with a repair shop to handle authorized repairs in Indianapolis. The company has set an acceptable range of repair time of 50 minutes to 90 minutes. Two firms have submitted bids for the work. In test trials, one firm had a mean repair time of 74 minutes with a standard deviation of 4.0 minutes and the other firm had a mean repair time of 72 minutes with a standard deviation of 5.1 minutes. Which firm would you choose? Why?arrow_forward
- very 12 hours, 90 parts are randomly sampled and the # of defective parts (out of 90) is recorded. Results from 16 samples follow: Sample Defects 1 3 2 11 3 5 4 2 5 8 6 0 7 9 8 7 9 9 10 3 11 6 12 9 13 10 14 4 15 8 16 5 Total # of defects: 99 total # of observations=90*16 = 1440 What is the value of the statistic plotted for sample 2? [go out 4 decimal places] Same parts data. What is the process average (i.e. the midpoint of the control chart)? Same parts data. What is the Upper Control Limit (UCL) for the most appropriate control chart?arrow_forwardhelp me with Parts A and Barrow_forwardsniparrow_forward
- A process filling small bottles with baby formula hasa target of 3 ounces ± 0.150 ounce. Two hundred bottles fromthe process were sampled. The results showed the averageamount of formula placed in the bottles to be 3.042 ounces. Thestandard deviation of the amounts was 0.034 ounce. Determinethe value of Cpk· Roughly what proportion of bottles meetthe specifications?arrow_forwardHelp please A2 is 0.557 D3 is 0 2.115arrow_forwardEvery 12 hours, 90 parts are randomly sampled and the # of defective parts (out of 90) is recorded. Results from 16 samples follow: Sample Defects 1 3 2 11 3 5 4 2 5 8 6 0 7 9 8 7 9 9 10 3 11 6 12 9 13 10 14 4 15 8 16 5 Total # of defects: 99 total # of observations=90*16 = 1440 What is the value of the statistic plotted for sample 2? [go out 4 decimal places]arrow_forward
- Eagletrons are all-electric automobiles produced byMogul Motors, Inc. One of the concerns of Mogul Motors is thatthe Eagletrons be capable of achieving appropriate maximumspeeds. To monitor this, Mogul executives take samples of eight Eagletrons at a time. For each sample, they determine the aver-age maximum speed and the range of the maximum speeds within the sample. They repeat this with 35 samples to obtain 35 samplemeans and 35 ranges. They find that the average sample mean is88.50 miles per hour, and the average range is 3.25 miles per hour.Using these results, the executives decide to establish an R chart.They would like this chart to be established so that when it showsthat the range of a sample is not within the control limits, there isonly approximately a 0.0027 probability that this is due to naturalvariation. What will be the upper control limit (UCL) and thelower control limit (LCL) in this chart?arrow_forwardsniparrow_forward1. The data shown in Table 1 are x and R values for 20 samples of size n= 5 taken from a process producing bearings. The measurements are made on the inside diameter of the bearing, with only the last three decimals recorded (i.e., 31.6 should be 0.50316). Please show all your work for full credit. (a) Set up x and R charts on this process. Does the process seem to be in statistical control? If necessary, revise the trial control limits. (b) Assume that diameter is normally distributed. Estimate the process standard deviation. Sample R Sample R 1 31.6 4 11 29.8 4 33.0 3 12 34.0 4 35.0 4 13 33.0 10 4 32.2 4 14 34.8 4 5 33.8 38.4 31.6 15 35.6 7 3 16 30.8 7 4 17 33.0 5 8 36.8 10 18 31.6 3 9. 35.0 15 19 28.2 9 10 34.0 6 20 33.8 Table 1: Bearing Diameter Dataarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.