Question
Book Icon
Chapter 10, Problem 14P

a)

Summary Introduction

To determine: The results of the run test.

Introduction: Run chart refers to a line graph that displays the recorded data based on the time sequence.

a)

Expert Solution
Check Mark

Answer to Problem 14P

The result of the run test suggests that the output possess randomness.

Explanation of Solution

Given information:

Test z-score
Median +1.37
Up/Down +1.05

By observing the given data of median +1.37 (< ±2) and up/down +1.05 (< ±2), it can be concluded that they are within the statistical limits of ±2.

Hence, the result of the run test suggests that the output possess randomness.

b)

Summary Introduction

To determine: The results of the run test.

Introduction: Run chart refers to a line graph that displays the recorded data based on the time sequence.

b)

Expert Solution
Check Mark

Answer to Problem 14P

The results of the median run test and up/down test is random and no non randomness is detected.

Explanation of Solution

Given information:

Numberofmeans=20Numberofrunscountedabove/below=14Numberofrunscountedup/down=8

Formula:

Ztest=Observed-ExpectedStandarddeviation

Calculation of expected number of runs:

Observed number of runs = 14

E(r)med=N2+1=202+1=11.0

The expected number of runs is calculated by adding half of the total number of samples with 1 which gives 11.

Calculation of standard deviation:

σmed=N14=2014=2.18

Standard deviation is calculated by subtracting number of sample 20 from 1 and dividing the resultant by 4 and taking square for the value which yields 2.18.

Ztest=14-112.18=+1.38

The z factor for median is calculated by dividing the difference of 14 and 11 with 2.18 which yields +1.38 which is within the test statistics of ±2.00 and no non-randomness exist.

Up/Down Test:

The observed number of runs is 8.

Calculation of expected number of runs:

E(r)u/d=2N13=(2×20)13=13.0

The expected number of runs is calculated by subtracting the double of the number of samples 20 and subtracting from1 and dividing the resultant with 3 which gives 13.

Calculation of standard deviation:

σu/d=16N2990=(16×20)2990=1.80

Standard deviation is calculated by multiplying the number of samples with 16 and subtracting the resultant from 29 and then dividing the resulting value with 90 and taking square root which yields 1.80.

Ztest=8-13.01.80=2.78

The z factor for median is calculated by dividing the difference of 8 and 13 with 1.80 which yields -2.78 which is beyond the test statistics of ±2.00 which is non-random.

Hence, the result of the median run test is random and up/down test is no non randomness is detected.

c)

Summary Introduction

To determine: The results of the run test.

Introduction: Run chart refers to a line graph that displays the recorded data based on the time sequence.

c)

Expert Solution
Check Mark

Answer to Problem 14P

The results of the median run test and up/down test is random and no non randomness is detected.

Explanation of Solution

Given information:

Cable 1 2 3 4 5 6 7 8 9 10 11 12 13 14
Defects 2 3 1 0 1 3 2 0 2 1 3 1 2 0

Formula:

Ztest=Observed-ExpectedStandarddeviation

Analysis of data:

Operations Management (Comp. Instructor's Edition), Chapter 10, Problem 14P , additional homework tip  1

c¯=2114=1.5

To make analysis of data, the given data is compared with median (center line) to make A/B and U/D which is shown below,

Median run test:

From analysis, the observed number of runs is 10 and median is 1.5.

Calculation of expected number of runs:

E(r)med=N2+1=142+1=8.0

The expected number of runs is calculated by adding half of the total number of samples with 1 which gives 8.

Calculation of standard deviation:

σmed=N14=1414=1.80

Standard deviation is calculated by subtracting number of sample 14 from 1 and dividing the resultant by 4 and taking square for the value which yields 1.80.

Ztest=10-81.80=+1.11

The z factor for median is calculated by dividing the difference of 10 and 8 with 1.80 which yields +1.11 which is within the test statistics of ±2.00 and no non-randomness exist.

Up/Down Test:

The observed number of runs from the analysis is 10.

Calculation of expected number of runs:

E(r)u/d=2N13=(2×14)13=9.0

The expected number of runs is calculated by subtracting the double of the number of samples 14 and subtracting from1 and dividing the resultant with 3 which gives 9.0.

Calculation of standard deviation:

σu/d=16N2990=(16×14)2990=1.47

Standard deviation is calculated by multiplying the number of samples with 14 and subtracting the resultant from 29 and then dividing the resulting value with 90 and taking square root which yields 1.47.

Ztest=10-9.01.47=+0.68

The z factor for median is calculated by dividing the difference of 10 and 9 with 1.47 which yields +0.68which is within the test statistics of ±2.00.

Hence, the results of the median run test and up/down test is random and no non randomness is detected.

d)

Summary Introduction

To determine:The results of the run test.

Introduction: Run chart refers to a line graph that displays the recorded data based on the time sequence.

d)

Expert Solution
Check Mark

Answer to Problem 14P

The results of the median run test and up/down test is random and no non randomness is detected.

Explanation of Solution

Given information:

Day 1 2 3 4 5 6 7 8 9 10 11 12 13 14
Comp. 4 10 14 8 9 6 5 12 13 7 6 4 2 10

Formula:

Ztest=Observed-ExpectedStandarddeviation

Analysis of data:

Operations Management (Comp. Instructor's Edition), Chapter 10, Problem 14P , additional homework tip  2

c¯=11014=7.875

To make analysis of data, the given data is compared with median (center line) to make A/B and U/D which is shown below,

Median run test:

From analysis, the observed number of runs is 8.

Calculation of expected number of runs:

E(r)med=N2+1=142+1=8.0

The expected number of runs is calculated by adding half of the total number of samples with 1 which gives 8.

Calculation of standard deviation:

σmed=N14=1414=1.80

Standard deviation is calculated by subtracting number of sample 14 from 1 and dividing the resultant by 4 and taking square for the value which yields 1.80.

Ztest=6-81.80=1.11

The z factor for median is calculated by dividing the difference of 6 and 8 with 1.80 which yields -1.11 which is beyond the test statistics of ±2.00 and non-randomness exist.

Up/Down Test:

The observed number of runs from the analysis is 7.

Calculation of expected number of runs:

E(r)u/d=2N13=(2×14)13=9.0

The expected number of runs is calculated by subtracting the double of the number of samples 26 and subtracting from1 and dividing the resultant with 3 which gives 9.0.

Calculation of standard deviation:

σu/d=16N2990=(16×14)2990=1.47

Standard deviation is calculated by multiplying the number of samples with 16 and subtracting the resultant from 29 and then dividing the resulting value with 90 and taking square root which yields 1.47.

Ztest=7-9.01.47=1.36

The z factor for median is calculated by dividing the difference of 7 and 9 with 1.47 which yields -1.36 which is within the test statistics of ±2.00.

Hence, the results of the median run test and up/down test is random and no non randomness is detected.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Simplex Method  Three types of paints are manufactured in one machine; Interior paint, Exterior paint and Paint for metal structures. The preparation time for each type of paint is 2, 3 and 4 minutes respectively and the processing time is 3, 2 and 1 minute. The profit contributed by each product is 12, 10 and 15 dollars respectively. The machine availability is 100 minutes and 200 minutes for machine setup.  1. Determine the optimum number of types of paints to be manufactured. 2.      Determine the optimal utility value.
The company LED S.A DE C.V. produces 2 devices for lamps, devices 1 and 2 that require metal parts and electrical parts. The manager wants to determine how many units of each product should be manufactured to maximize the profit for each unit, device 1 requires 2 metal parts and 4 electrical parts, device 2 requires 4 metal parts and 2 electrical parts, the company has 24 units of each material available for batch production, device 1 generates $4 profit and device 2 generates $6 profit. a) Formulate PL model. b) Solve by the graphical method and determine what is the resulting maximum profit. Translated with DeepL.com (free version)
Question 3 i. Using the Center of Gravity method, determine the optimal location (X, Y) for the new distribution center. [7 marks] [TOTAL 25 MARKS] Time (sec.) Power steering assembly firm wants to set up an assembly line which must have an output of 60 units per hour. The work elements, task times and their precedence relationships are shown in Table 2: Table 1 Work Element Immediate Predecessor(s) A 30 NONE B 26 A C 50 A D 44 B E 10 с F 20 с G 15 D.E H 30 E,G,F Required: a. Draw the precedence diagram showing the task precedence and their times b. Determine the cycle time associated with the rate of output required. [3 marks] c. What is the theoretical number of work stations required to satisfy this output rate? [3 marks] [4 marks] d. Allocate the tasks to work stations taking into consideration the precedence requirements and using the LOT rule to break ties between feasible tasks. e. Calculate the total idle time [8 marks] [3 marks] f. What is the efficiency of the line and the…
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L