Question
Chapter 10, Problem 10PA
Summary Introduction
Interpretation: Number of clerks and typists to be hired assuming 90% target utilization rate.
Concept Introduction: Utilization is the percentage of time a resource is engaged in a work to complete a task.
Target utilization is the desired utilization percentage which the management desires and assigns manpower according to that target.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
ABC Solutions is a traditional company in a textile industry with a combined workforce of 150 staff. Due to increased levels of competition, this company is now increasingly finding it difficult to compete – especially as the larger companies seem to be a little more innovative, agile and responsive to client requirements. Management have noticed that staff, especially the highly skilled ones, are now leaving the company to seek work elsewhere (in these larger companies). This has meant appointing new staff and undertaking a considerable amount of re-training to replace those that have left the company. Apart from impacting on core business operations, ABC Solutions has started witnessing a drop in its profit margin.
Given this position, senior management at ABC Solutions have decided to implement a performance measurement tool (PMT) that would allow them to align the strategic, management and operational requirements of the business. They are therefore considering the adoption of the…
Consider a law firm with 15 lawyers and 3 paralegals. The firm is struggling to keep up with the high demand for its services, particularly during the busy litigation seasons. It has been observed that the lawyers spend a significant amount of their time on administrative tasks that could potentially be handled by paralegals. After a careful study of the work distribution within the firm, it was determined that 35% of the activities carried out by the lawyers are administrative in nature. Given that each lawyer works 50 hours a week, please determine:
(a) How many additional paralegals should the firm hire to handle the administrative tasks currently performed by the lawyers?
(b) If the lawyers' time spent on administrative tasks is redirected to billable legal work, by what percentage could the firm potentially increase its billable hours?
Consider the following tasks that must be assigned to four workers on a conveyor-paced assembly line (i.e., a machine-paced line flow). Each worker must perform at least one task. There exists unlimited demand unless stated otherwise. Time to Complete Task (seconds): Task 1: 30 Task 2: 25 Task 3: 15 Task 4: 20 Task 5: 15 Task 6: 20 Task 7: 50 Task 8: 15 Task 9: 20 Task 10: 25 Task 11: 15 Task 12: 20 The current conveyor-paced assembly-line configuration assigns the workers in the following way: • Worker 1: Tasks 1, 2, 3 • Worker 2: Tasks 4, 5, 6 • Worker 3: Tasks 7, 8, 9 • Worker 4: Tasks 10, 11, 12 What is the direct labor content (in seconds per unit)?
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- ABC Solutions is a traditional company in textile industrywith a combined workforce of 150 staff. Due to increased levels of competition, this company is now increasingly finding it difficult to compete – especially as the larger companies seem to be a little more innovative, agile and responsive to client requirements. Management have noticed that staff, especially the highly skilled ones, are now leaving the company to seek work elsewhere (in these larger companies). This has meant appointing new staff and undertaking a considerable amount of re-training to replace those that have left the company. Apart from impacting on core business operations, ABC Solutions has started witnessing a drop in its profit margin. Given this position, senior management at ABC Solutions have decided to implement a performance measurement tool (PMT) that would allow them to align the strategic, management and operational requirements of the business. They are therefore considering the adoption of the…arrow_forwardThe manager of the Personnel Department at City Enterprises has been reading about time-driven ABC and wants to apply it to her department. She has identified four basic activities her employees spend most of the their time on: Interviewing, Hiring, Assessment, and Separation Processing. The department employs 5 staff who perform these activities. The manager provides the following estimates for the amount of time it takes to complete each of these activities: Interviewing: 45 minutes. Hiring: 60 minutes. Assessment: 75 minutes. Separation Processing: 90 minutes. Employees in Personnel work 35-hour weeks with four weeks for vacation. Of the 35 hours, five are reserved for administrative tasks, training, and so on. The costs of the Personnel Department, including any allocated costs from other staff functions, are $972,000. During the year, Personnel conducted 1,200 interviews, made 375 hires, made 3,000 assessments, and had 250 separations. The manager of the Personnel…arrow_forwardA call center facility is to house 175 female and 175 male employees. Using a 50% allowance for aides and clearances, how much space should be planned for restrooms.arrow_forward
- The National State Bank is trying to make sure that they have enough tellers to handle the Friday afternoon rush of workers wanting to cash their paychecks. They are only concerned with the last hour of the day from 4:00 to 5:00 P.M. It takes 5 minutes per customer to be processed by the tellers. The average customer arrivals are shown in the table below. TIME CUSTOMERSARRIVING 4:00 – 4:05 2 4:05 – 4:10 6 4:10 – 4:15 7 4:15 – 4:20 6 4:20 – 4:25 14 4:25 – 4:30 16 4:30 – 4:35 18 4:35 – 4:40 10 4:40 – 4:45 12 4:45 – 4:50 2 4:50 – 4:55 5 4:55 – 5:00 2 5:00 – 5:05 0 Total 100 The bank currently has 8 teller stations, and all are staffed during the Friday afternoon rush hour. a. What is the current maximum output at the bank during rush hour? b. Can the bank process all the customers by 5:00 P.M.? c. What is the maximum waiting time for customers, and what time period does it occur in? (Round your…arrow_forwardWhat is flow processing, and what are its advantages and disadvantages?arrow_forwardi need help creating a flow chart for my model in the attachmentarrow_forward
- As an analyst, we would like to perform a work sampling study on an assembly line. The jobs can bedifferentiated on the basis of the product size: A, B, and C. We perform a study over a five-week periodthat equals to 200 working hours. There are 12 workers to be examined. In total, we perform 1140observations. Yet, the worker absences lead to 15 worker-day deduction from the total working hourswhere workers work 8 hour each day. The study results are tabulated below. Q: For the C size product, construct a 96% confidence interval about the mean assembly time per productin terms of hours.a) (0,3702 0,4298)b) (0,4004 0,3996)c) (0,1805 0,1209)d) (0,3746 0,4254)e) (0,1253 0,1761)arrow_forwardAs an analyst, we would like to perform a work sampling study on an assembly line. The jobs can bedifferentiated on the basis of the product size: A, B, and C. We perform a study over a five-week periodthat equals to 200 working hours. There are 12 workers to be examined. In total, we perform 1140observations. Yet, the worker absences lead to 15 worker-day deduction from the total working hourswhere workers work 8 hour each day. The study results are tabulated below. Q: What is the mean assembly time per product unit for size C in terms of hour?a) 0,1136b) 0,0251c) 0,3015d) 0,7537e) 0,0661arrow_forwardb) A company receives parts from suppliers to be used in its manufacturing departments. The quality control department must perform two operations when shipments are received: Operation A – draw a random sample, package, and deliver to testing; and Operation B – test the materials and issue a disposition report. There are currently six shipments waiting to be processed. The time estimates for processing these six shipments through quality control are given in the table below. Shipment Operation A (hours) Operation B (hours) A 1.5 1.0 В 1.1 2.7 1.2 1.4 D 0.7 1.6 E 1.6 1.5 F 1.9 2.9 Use Johnson's Rule to set the sequence of processing the shipments through Quality Control. i. ii. How much total time is required to process all the six shipments through Quality Control? Show all times on a Gantt Chart. w luarrow_forward
- A work cell in a local manufacturer has a workstation with 4 machines that form a line (Machine 1-Machine 2-Machine 3-Machine 4). Each unit needs to pass through each machine in order to be completed. Each machine has a production capacity of four units per hour. What is the process time of the work cell in minutes per unit? 15 4 8 16arrow_forwardMedical Solutions, Inc. has the following claims it must complete in the next week (40 hours). The jobs are as follows: Claim Type Spinal injury Number of Claims Setup (Changeover) to Process (Work Time per Claim Type (hours) Cancer treatment 15 Hip replacement Order Quantity) 14 10 SI Claims Workload: hours Processing Time per Claim (hours) HR Claims Workload: hours 3.0 1.1 2.5 0.9 1.5 All claims of the same type are processed together. Is 40 hours enough capacity? (Hint: use Equation 10.3.) Round your answers to one decimal place. CT Claims Workload: hours 0.5 Total workload is hours while capacity is 40 hours. The work -Select-cancannotItem 5 be completed using regular time hours.arrow_forwardA production line is a set of sequential operations established in a factory plant where components are assembled to make a finished product or where materials are put through a refining process to produce an end-product that is suitable for onward consumption. Ford have seven production lines in their manufacturing plant for their automotive parts where each production line produces 120, 100, 80, 116, 77, 94, 112 output per day. (a) As the Production Manager at Ford, you are required to submit the daily report of the production plant. Calculate the mean, median, and mode from the data based on the output that has been provided. (b) Also calculate the three critical parameters for measuring spread in the following ways: Range Variance Standard Deviationarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY