(a)
Interpretation:The maximum capacity of store per day needs to be calculated with the help of given data.
Concept Introduction: Capacity measurement is an important concept which helps companies to make long term and short-term decisions related to capacity and thus plan for contingencies.
(a)
Explanation of Solution
A.
Given Information:
There are 5 regular lines ad 1 express lines.
Average time a customer spends in a regular line = 11 min which means that one regular line can handle 5.45 customers per day.
Average time a customer spends in an express line = 4 min which means that one express line can handle 15 customers per day.
Shift duration = 12 hours per day
Thus,
The capacity of 5 regular lines =
The capacity of 1 express lines =
Therefore, the maximum capacity of store = (327 + 180) = 507 customers per day.
B.
Interpretation:The maximum capacity of store per day needs to be calculated with the help of given data.
Concept Introduction: Capacity measurement is an important concept which helps companies to make long term and short-term decisions related to capacity and thus plan for contingencies.
B.
Explanation of Solution
Given Information:
There are 5 regular lines ad 1 express lines.
Average time a customer spends in a regular line = 11 min which means that one regular line can handle 5.45 customers per day.
Average time a customer spends in an express line = 4 min which means that one express line can handle 15 customers per day.
Shift duration = 12 hours per day
The store’s capacity by day of the week is as follows:
Period | Monday | ||
Hours | No. of lines open | Capacity (customers per day) | |
9-12 noon | 3 | 1 | |
12-4 PM | 4 | 2 | |
4-6 PM | 2 | 3 | |
6-9 PM | 3 | 4 | |
Total Capacity of Regular Line (Customers per day) | 158.05 |
Since the express line is always open, and the capacity is 180 customers per day.
Therefore, the maximum capacity on Monday is 338 customers per day.
Also, the maximum capacity on Tuesday, Wednesday and Thursday will be 338 customers per day as same number of regular lines are open as on Monday.
Period | Friday | ||
Hours | No. of lines open | Capacity (customers per day) | |
9-12 noon | 3 | 3 | |
12-4 PM | 4 | 3 | |
4-6 PM | 2 | 5 | |
6-9 PM | 3 | 5 | |
Total Capacity of Regular Line (Customers per day) | 250.7 |
Since the express line is always open, and the capacity is 180 customers per day.
Therefore, the maximum capacity on Friday is 431 customers per day.
Period | Saturday | ||
Hours | No. of lines open | Capacity (customers per day) | |
9-12 noon | 3 | 5 | |
12-4 PM | 4 | 5 | |
4-6 PM | 2 | 3 | |
6-9 PM | 3 | 3 | |
Total Capacity of Regular Line (Customers per day) | 272.5 |
Since the express line is always open, and the capacity is 180 customers per day.
Therefore, the maximum capacity on Saturday is 452.5 customers per day.
Period | Sunday | ||
Hours | No. of lines open | Capacity (customers per day) | |
9-12 noon | 3 | 2 | |
12-4 PM | 4 | 4 | |
4-6 PM | 2 | 2 | |
6-9 PM | 3 | 1 | |
Total Capacity of Regular Line (Customers per day) | 158.05 |
Since the express line is always open, and the capacity is 180 customers per day.
Therefore, the maximum capacity on Sunday is 338.5 customers per day.
Want to see more full solutions like this?
- 130) please please help me with this! Owners of a local restaurant are concerned about their ability to provide quality service as they continue to grow and attract more customers. They have collected data from Friday and Saturday nights, their busiest times of the week. During these time periods, about 106 customers arrive per hour for service. Given the number of tables and chairs, and the typical time it takes to serve a customer, the owners estimate they can serve, on average, about 162 customers per hour. Use Exhibit 4.6. Furthermore, the owners anticipate that in one year their demand will double as long as they can provide good service to their customers. a. Currently, during these nights, are they in the zone of service, the critical zone, or the zone of nonservice? EXIBIT IS THE PICTURE ADDED O Critical zone O Zone of service O Zone of nonservice b. Next year, after demand doubles, what must the service capacity increase to (at minimum) to stay out of the critical zone?Note:…arrow_forwardThe company has the following information about its two service departments and two production departments, Cutting and Assembly: Departments SquareFeet Number ofEmployees Maintenance Department 500 20 Cafeteria Department 1,400 10 Cutting Department 1,500 60 Assembly Department 7,100 20 What is the percentage (proportional) usage of the Maintenance Department by the Cutting Department?arrow_forwardThe Holt Million Corporation’s plant manufactures two different products: X and Y. The plant has three different machines: A, B, and C. Each performs different tasks and can work on only one unit of material at a time. Details for each product are shown in the table below: Product X Y Demand Per Week 200 units 100 units Selling Price $150 $160 Machine Operation Required A, B, C B, B, C Operation Times in Minutes 20, 15, 15 15, 15, 15 Raw Materials Needed RM-1, RM-2 RM-2, RM-3 Raw Materials Costs RM-1 = $40/unit, RM-2 or RM-3 = $20/unit Each product uses raw materials with costs as shown in the above table where the processing times and the machine required for each operation are also shown. Each machine is available 4,800 minutes per week. There are no system foul-ups. Demand is deterministic (i. e., no uncertainty). Operating expenses, including labor (but excluding raw materials) total $12,000 per week. Assuming…arrow_forward
- Owners of a local restaurant are concerned about their ability to provide quality service as they continue to grow and attract more customers. They have collected data from Friday and Saturday nights, their busiest times of the week. During these time periods about 75 customers arrive per hour for service. Given the number of tables and chairs, and the typical time it takes to serve a customer, the owners estimate they can serve on average about 100 customers per hour. During these nights, are they in the zone of service, the critical zone, or the zone of nonservice?arrow_forwardHow does seasonal variability in demand affect the l ow and waiting time through a process? How might a company respond to reduce the effect of this variability?arrow_forwardA company receives parts from suppliers to be used in its manufacturing departments. The quality control department must perform two operation when shipments are received:i) Operation A-draw a random sample, package, and deliver to testing, andii) Operation B-test the materials and issue a disposition reportThere are currently six shipments waiting to be processed. The time estimates for processing these six shipments through quality control are:Shipment Operation A (hours) Operation B (hours)1 1.5 1.02 1.1 2.73 1.2 1.44 0.7…arrow_forward
- A call center has been serving 900 customers per day, with a 10% capacity cushion. There have been complaints about the length of time customers have to wait before their call is answered. If the manager of the call center wants to double the capacity cushion, how much extra capacity is needed?arrow_forwardTema Tire Services (TTS) decided to hire a new mechanic to handle all tire changes for customers ordering a new set of tires. Two mechanics have been shortlisted for the job. One mechanic has limited experience, can be hired for GH¢14 per hour, and can service an average of three customers per hour. The other mechanic has several years of experience, can service an average of four customers per hour, but must be paid GH¢20 per hour. Historical data shows that customers arrive at the TTS garage at the rate of two customers per hour. b) If the company assigns a customer waiting cost of GH¢30 per hour, which mechanic provides the lower operating total cost (TC)? c) With the aid of a sketch, show the economic relationship between service cost and waiting costs, and justify whether or not it is necessary for TTS to keep investing in better and/or additional mechanics until waiting time reduces to zearrow_forwardA fast-food restaurant has a drive-thru window and during peak lunch times can handle a maximum of 60 cars per hour with one person taking orders, assembling them, and acting as cashier. The average sale per order is $9.50. A proposal has been made to add two workers and divide the tasks among the three. One will take orders, the second will assemble them, and the third will act as a cashier. With this system, it is estimated that 85 cars per hour can be serviced.arrow_forward
- 1. Calculate the average customer arrival rate and service rate per hour. 2. Calculate the probability of zero patients in the system (P0), probability of one patient (P1), and probability of two or more patients simultaneously arriving during the night shift. 3. Using a criterion that if the probability is greater than 1 percent, a backup OR team should be employed, make a recommendation to hospital administration. I'm not sure how to find the answers to the empty boxes.arrow_forwardShouldice Hospital in Canada is widely known for one thing—hernia repair! In fact, that is the only operation it performs, and it performs a great many of them. Over the past two decades this small 90-bed hospital has averaged 7,000 operations annually. Last year, it had a record year and performed nearly 7,500 operations. A hernia repair operation at Shouldice Hospital is performed by one of the 12 full-time surgeons assisted by one of seven part-time assistant surgeons. The first operations begin at 7:30 AM each day, Monday through Friday. Surgeons generally take about one hour to prepare for and perform each hernia operation, and they operate on an average of at most four patients per day. This four patient per day limit on the average number of operations performed per surgeon has been found to be the best operating level for the hospital as it takes into account time the surgeons need for patient exams and consultations, updating medical charts, writing reports, traveling to…arrow_forwardShouldice Hospital in Canada is widely known for one thing—hernia repair! In fact, that is the only operation it performs, and it performs a great many of them. Over the past two decades this small 90-bed hospital has averaged 7,000 operations annually. Last year, it had a record year and performed nearly 7,500 operations. A hernia repair operation at Shouldice Hospital is performed by one of the 12 full-time surgeons assisted by one of seven part-time assistant surgeons. The first operations begin at 7:30 AM each day, Monday through Friday. Surgeons generally take about one hour to prepare for and perform each hernia operation, and they operate on an average of at most four patients per day. This four patient per day limit on the average number of operations performed per surgeon has been found to be the best operating level for the hospital as it takes into account time the surgeons need for patient exams and consultations, updating medical charts, writing reports, traveling to…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,