There are four critical paths in a network. A-B-C-D-E, A-F-E, A-B-H-J-K-E and A-S-T-E. Each activity in this network can be crashed by a maximum of 6 weeks. The crashing cost (per week), for the first week (crashing first time), for activity A is: $480, E is $495 and all other activities is : $120 (per week per activity). The crashing cost, second week and onwards(crashing second time), for activity A is $1200 per week, E is $1440 per week and for all other activities is $240 per activity per week. You have a maximum crashing budget of $3005. The maximum possible reduction in the project duration will be: a. 6 weeks b. 3 weeks c. 2 week d. 5 weeks e. 4 weeks
There are four critical paths in a network. A-B-C-D-E, A-F-E, A-B-H-J-K-E and A-S-T-E. Each activity in this network can be crashed by a maximum of 6 weeks. The crashing cost (per week), for the first week (crashing first time), for activity A is: $480, E is $495 and all other activities is : $120 (per week per activity). The crashing cost, second week and onwards(crashing second time), for activity A is $1200 per week, E is $1440 per week and for all other activities is $240 per activity per week. You have a maximum crashing budget of $3005. The maximum possible reduction in the project duration will be: a. 6 weeks b. 3 weeks c. 2 week d. 5 weeks e. 4 weeks
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
There are four critical paths in a network. A-B-C-D-E, A-F-E, A-B-H-J-K-E and A-S-T-E. Each activity in this network can be crashed by a maximum of 6 weeks. The crashing cost (per week), for the first week (crashing first time), for activity A is: $480, E is $495 and all other activities is : $120 (per week per activity). The crashing cost, second week and onwards(crashing second time), for activity A is $1200 per week, E is $1440 per week and for all other activities is $240 per activity per week. You have a maximum crashing budget of $3005. The maximum possible reduction in the project duration will be:
a. 6 weeks b. 3 weeks c. 2 week d. 5 weeks e. 4 weeks
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 2 images
Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.