Activity normal durations, crash durations and cost Crash Normal Duration Duration Activity (weeks) (weeks) 4 A-B B-C B-D B-E C-F C-K D-G E-H F-G F-I F-K F-L F-N G-L H-K J-O K-N L-M M-O N-O 3263 2 3 NGMMNNNNNN 2 10 3 3 2 2 2 2 10 2 3 8 4 2 12 2 23752 3 1 5 2 2 218N 8 2 2 1 1 1 1 9 1 1 7 2 1 10 Normal Cost ($) 300,000.00 100,000.00 50,000.00 150,000.00 30,000.00 20,000.00 300,000.00 60,000.00 160,000.00 350,000.00 170,000.00 330,000.00 250,000.00 60,000.00 100,000.00 10,000.00 30,000.00 50,000.00 40,000.00 5,000.00 200,000.00 Crash Cost ($) 420,000.00 100,000.00 55,000.00 200,000.00 150,000.00 25,000.00 350,000.00 140,000.00 260,000.00 500,000.00 270,000.00 440,000.00 500,000.00 65,000.00 110,000.00 20,000.00 35,000.00 80,000.00 50,000.00 6,000.00 240,000.00 Note: The Crash duration represents the minimum duration where an activity is speeded up as much as possible. The crash cost represents the increased cost of the increased cost of the activity after it has been speeded up as much as possible. a) Draw a schedule showing the work package critical path and duration. b) Assume the work package has to be completed within 44weeks. Calculate the most cost effective way of completing the work package within this time, giving the cost increase associated with this crash sequence.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Activity normal durations, crash durations and cost

Activity Normal Duration (weeks)  Crash Duration (weeks) Normal Cost ($) Crash Cost ($)
A-B 4 2  300,000.00  420,000.00
B-C 3 3  100,000.00  100,000.00
B-D 2 1  50,000.00  55,000.00
B-E 6 5  150,000.00  200,000.00
C-F 3 2  30,000.00  150,000.00
C-K 3 2  20,000.00  25,000.00
D-G 2 1  300,000.00  350,000.00
E-H 10 8  60,000.00  140,000.00
F-G 3 2  160,000.00  260,000.00
F-I 3 2  350,000.00  500,000.00
F-K 2 1  170,000.00  270,000.00
F-L 2 1  330,000.00  440,000.00
F-N 2 1  250,000.00  500,000.00
G-L 2 1  60,000.00  65,000.00
H-K 10 9  100,000.00  110,000.00
I-J 2 1  10,000.00  20,000.00
J-O 3 1  30,000.00  35,000.00
K-N 8 7  50,000.00  80,000.00
L-M 4 2  40,000.00  50,000.00
M-O 2 1  5,000.00  6,000.00
N-O 12 10  200,000.00  240,000.00

 Note: The Crash duration represents the minimum duration where an activity is speeded up as much as possible. The crash cost represents the increased cost of the increased cost of the activity after it has been speeded up as much as possible.

a) Draw a schedule showing the work package critical path and duration.

b) Assume the work package has to be completed within 44weeks. Calculate the most cost effective way of completing the work package within this time, giving the cost increase associated with this crash sequence.

 

Activity normal durations, crash durations and cost
Crash
Normal
Duration
Activity (weeks)
A-B
B-C
B-D
B-E
C-F
C-K
D-G
E-H
F-G
F-I
F-K
F-L
F-N
G-L
H-K
I-J
J-O
K-N
L-M
M-O
N-O
4
3
2
NW w a
6
3
3
2
10
O N N N N W w ō
3
3
2
2
9
10
2384
2
12
Duration
(weeks)
2
3
1
5
ON N
2
2
1
00 N
8
2
2
1
1
1
1
9
HANN
1
1
7
2
1
10
Normal Cost
($)
300,000.00
100,000.00
50,000.00
150,000.00
30,000.00
20,000.00
300,000.00
60,000.00
160,000.00
350,000.00
170,000.00
330,000.00
250,000.00
60,000.00
100,000.00
10,000.00
30,000.00
50,000.00
40,000.00
5,000.00
200,000.00
Crash Cost ($)
420,000.00
100,000.00
55,000.00
200,000.00
150,000.00
25,000.00
350,000.00
140,000.00
260,000.00
500,000.00
270,000.00
440,000.00
500,000.00
65,000.00
110,000.00
20,000.00
35,000.00
80,000.00
50,000.00
6,000.00
240,000.00
Note: The Crash duration represents the minimum duration where an activity is speeded up as much
as possible.
The crash cost represents the increased cost of the increased cost of the activity after it has been
speeded up as much as possible.
a) Draw a schedule showing the work package critical path and duration.
b) Assume the work package has to be completed within 44weeks. Calculate the most cost effective
way of completing the work package within this time, giving the cost increase associated with this
crash sequence.
Transcribed Image Text:Activity normal durations, crash durations and cost Crash Normal Duration Activity (weeks) A-B B-C B-D B-E C-F C-K D-G E-H F-G F-I F-K F-L F-N G-L H-K I-J J-O K-N L-M M-O N-O 4 3 2 NW w a 6 3 3 2 10 O N N N N W w ō 3 3 2 2 9 10 2384 2 12 Duration (weeks) 2 3 1 5 ON N 2 2 1 00 N 8 2 2 1 1 1 1 9 HANN 1 1 7 2 1 10 Normal Cost ($) 300,000.00 100,000.00 50,000.00 150,000.00 30,000.00 20,000.00 300,000.00 60,000.00 160,000.00 350,000.00 170,000.00 330,000.00 250,000.00 60,000.00 100,000.00 10,000.00 30,000.00 50,000.00 40,000.00 5,000.00 200,000.00 Crash Cost ($) 420,000.00 100,000.00 55,000.00 200,000.00 150,000.00 25,000.00 350,000.00 140,000.00 260,000.00 500,000.00 270,000.00 440,000.00 500,000.00 65,000.00 110,000.00 20,000.00 35,000.00 80,000.00 50,000.00 6,000.00 240,000.00 Note: The Crash duration represents the minimum duration where an activity is speeded up as much as possible. The crash cost represents the increased cost of the increased cost of the activity after it has been speeded up as much as possible. a) Draw a schedule showing the work package critical path and duration. b) Assume the work package has to be completed within 44weeks. Calculate the most cost effective way of completing the work package within this time, giving the cost increase associated with this crash sequence.
Expert Solution
steps

Step by step

Solved in 5 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.