The gross requirements for Item X are specified for the beginning of weeks 1 through 8 in the table that follows. The product structure for the item is given in the figure: The lead time of each item is specified within square brackets. F example, the lead time for Item X is 1 week. The number of units required for each lower level part is specified withi parentheses. For example, each unit of Item B requires 1 unit of Part C and 2 units of Part D. Product Structure for Item X Level 0 Level 1 Level 2 7 Level 3 C (1) [LT 1] H (1) [LT 1] K (1) [LT 3] B (1) [LT 1] Gross Requirement On-hand Inventory Planned Order Release D (2) [LT 2] M (2) [LT 1] X [LT 1] Z (2) [LT 1] N (1) [LT 1] C (4) [LT 1] What is planned order release for Item M in Week 1? 0 Specify the number of units. H (1) [LT 1] Item X Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 0 0 0 0 0 85 120 90 What is planned order release for Item M in Week 2? 450 Specify the number of units. What is planned order release for Item M in Week 3? K (1) [LT 3] The projected on hand inventory at the beginning of Week 1 (end of Week 0) for Item X is 65 units and for Item B is units. There are no scheduled receipts.
The gross requirements for Item X are specified for the beginning of weeks 1 through 8 in the table that follows. The product structure for the item is given in the figure: The lead time of each item is specified within square brackets. F example, the lead time for Item X is 1 week. The number of units required for each lower level part is specified withi parentheses. For example, each unit of Item B requires 1 unit of Part C and 2 units of Part D. Product Structure for Item X Level 0 Level 1 Level 2 7 Level 3 C (1) [LT 1] H (1) [LT 1] K (1) [LT 3] B (1) [LT 1] Gross Requirement On-hand Inventory Planned Order Release D (2) [LT 2] M (2) [LT 1] X [LT 1] Z (2) [LT 1] N (1) [LT 1] C (4) [LT 1] What is planned order release for Item M in Week 1? 0 Specify the number of units. H (1) [LT 1] Item X Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 0 0 0 0 0 85 120 90 What is planned order release for Item M in Week 2? 450 Specify the number of units. What is planned order release for Item M in Week 3? K (1) [LT 3] The projected on hand inventory at the beginning of Week 1 (end of Week 0) for Item X is 65 units and for Item B is units. There are no scheduled receipts.
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
![The gross requirements for Item X are specified for the beginning of weeks 1 through 8 in the table that follows. The
product structure for the item is given in the figure: The lead time of each item is specified within square brackets. For
example, the lead time for Item X is 1 week. The number of units required for each lower level part is specified within
parentheses. For example, each unit of Item B requires 1 unit of Part C and 2 units of Part D.
Product Structure for Item X
4
Level 0
Level 1
+
4
Level 2
+
4
Level 3
C (1)
[LT 1]
H (1)
[LT 1]
K (1)
[LT 3]
B (1)
[LT 1]
Gross Requirement
On-hand Inventory
Planned Order Release
D (2)
[LT 2]
M (2)
[LT 1]
X
[LT 1]
Z (2)
[LT 1]
N (1)
[LT 1]
What is planned order release for Item M in Week 1?
0
Specify the number of units.
C (4)
[LT 1]
Item X
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8
0
0
0
0
0
85
120
90
What is planned order release for Item M in Week 2?
450 Specify the number of units.
H (1)
[LT 1]
The projected on hand inventory at the beginning of Week 1 (end of Week 0) for Item X is 65 units and for Item B is 30
units. There are no scheduled receipts.
What is planned order release for Item M in Week 3?
360 Specify the number of units.
K (1)
[LT 3]](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F85f38bab-db3f-4cdd-9980-1e08b3f6d2d1%2F8c3de1e2-fd28-42c1-9051-ca1404944d3e%2Fmva083o_processed.png&w=3840&q=75)
Transcribed Image Text:The gross requirements for Item X are specified for the beginning of weeks 1 through 8 in the table that follows. The
product structure for the item is given in the figure: The lead time of each item is specified within square brackets. For
example, the lead time for Item X is 1 week. The number of units required for each lower level part is specified within
parentheses. For example, each unit of Item B requires 1 unit of Part C and 2 units of Part D.
Product Structure for Item X
4
Level 0
Level 1
+
4
Level 2
+
4
Level 3
C (1)
[LT 1]
H (1)
[LT 1]
K (1)
[LT 3]
B (1)
[LT 1]
Gross Requirement
On-hand Inventory
Planned Order Release
D (2)
[LT 2]
M (2)
[LT 1]
X
[LT 1]
Z (2)
[LT 1]
N (1)
[LT 1]
What is planned order release for Item M in Week 1?
0
Specify the number of units.
C (4)
[LT 1]
Item X
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8
0
0
0
0
0
85
120
90
What is planned order release for Item M in Week 2?
450 Specify the number of units.
H (1)
[LT 1]
The projected on hand inventory at the beginning of Week 1 (end of Week 0) for Item X is 65 units and for Item B is 30
units. There are no scheduled receipts.
What is planned order release for Item M in Week 3?
360 Specify the number of units.
K (1)
[LT 3]
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 2 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.