WSS company makes weatherproof surveillance systems for parking lots. Demand estimates for the next four quarters are 25, 9, 13, and 17 units. Prepare an aggregate plan that uses inventory, regular time and overtime and back orders. Subcontracting is not allowed. Regular time capacity is 15 units for quarters 1 and 2, 18 units for quarters 3 and 4. Overtime capacity is 3 units per quarter. Regular time cost is $2000 per unit, while overtime cost is $3000 per unit. Back order cost is $300 per unit per quarter; inventory holding cost is $100 per unit per quarter. Beginning inventory is zero. Questions At the end of quarter 3, what is the ending inventory of finished systems? Answer: No ending Inventory =0 What is the total cost? 15*2000 + 6*2300 +4*2600 + 9*2000 + 13*2000 + 17*2000 =$132, 200 What is the average cost per unit? Answer 132200 / 64 = $2,066.
Critical Path Method
The critical path is the longest succession of tasks that has to be successfully completed to conclude a project entirely. The tasks involved in the sequence are called critical activities, as any task getting delayed will result in the whole project getting delayed. To determine the time duration of a project, the critical path has to be identified. The critical path method or CPM is used by project managers to evaluate the least amount of time required to finish each task with the least amount of delay.
Cost Analysis
The entire idea of cost of production or definition of production cost is applied corresponding or we can say that it is related to investment or money cost. Money cost or investment refers to any money expenditure which the firm or supplier or producer undertakes in purchasing or hiring factor of production or factor services.
Inventory Management
Inventory management is the process or system of handling all the goods that an organization owns. In simpler terms, inventory management deals with how a company orders, stores, and uses its goods.
Project Management
Project Management is all about management and optimum utilization of the resources in the best possible manner to develop the software as per the requirement of the client. Here the Project refers to the development of software to meet the end objective of the client by providing the required product or service within a specified Period of time and ensuring high quality. This can be done by managing all the available resources. In short, it can be defined as an application of knowledge, skills, tools, and techniques to meet the objective of the Project. It is the duty of a Project Manager to achieve the objective of the Project as per the specifications given by the client.
- WSS company makes weatherproof surveillance systems for parking lots. Demand estimates for the next four quarters are 25, 9, 13, and 17 units. Prepare an aggregate plan that uses inventory, regular time and overtime and back orders. Subcontracting is not allowed. Regular time capacity is 15 units for quarters 1 and 2, 18 units for quarters 3 and 4. Overtime capacity is 3 units per quarter. Regular time cost is $2000 per unit, while overtime cost is $3000 per unit. Back order cost is $300 per unit per quarter; inventory holding cost is $100 per unit per quarter. Beginning inventory is zero.
Questions
- At the end of quarter 3, what is the ending inventory of finished systems? Answer: No ending Inventory =0
- What is the total cost? 15*2000 + 6*2300 +4*2600 + 9*2000 + 13*2000 + 17*2000 =$132, 200
- What is the average cost per unit? Answer 132200 / 64 = $2,066.