The partially completed inventory record for the driveshaft subassembly in the table below shows gross requirements, scheduled receipts, lead time, and current on-hand inventory. a. Complete the last three rows of the record for an FOQ of 55 units. (Enter your responses as integers. A response of "0" is equivalent to being not applicable) Item: Driveshaft subassembly Gross requirements Scheduled receipts Projected on-hand inventory Planned receipts 10 30 70 20 3 20 4 20 Lot Size: FOQ-55 units Lead Time: 3 weeks Week 5 45 6 45 50 0000000 00000000

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
# Inventory Record Analysis for Driveshaft Subassembly

## Overview

This section analyzes the partially completed inventory record for a driveshaft subassembly. The table provided details the gross requirements, scheduled receipts, lead time, and current on-hand inventory. It helps in understanding materials requirement planning (MRP) for manufacturing processes.

## Instructions

Complete the last three rows (Projected on-hand inventory, Planned receipts, and Planned order releases) for a Fixed Order Quantity (FOQ) of 55 units. Enter your responses as integers, where '0' indicates that the particular action is not applicable.

### Item: Driveshaft Subassembly

#### Input Parameters:
- **Lot Size**: FOQ = 55 units
- **Lead Time**: 3 weeks

### Table

The table is structured across a span of 8 weeks to record the inventory data accurately.

| Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
|------|---|---|---|---|---|---|---|---|
| **Gross requirements** | 30 | 20 | 20 | 20 | 45 | 45 | 50 | 50 |
| **Scheduled receipts** | 70 | - | - | - | - | - | - | - |
| **Projected on-hand inventory** | 10 | - | - | - | - | - | - | - |
| **Planned receipts** | - | - | - | - | - | - | - | - |
| **Planned order releases** | - | - | - | - | - | - | - | - |

### Explanation

**Gross requirements** list the total demand for the driveshaft subassemblies each week. 
**Scheduled receipts** indicate any existing orders expected to be added to the inventory during that specific week.
**Projected on-hand inventory** tracks the expected inventory remaining at the end of each week after accounting for the gross requirements.
**Planned receipts** are the quantities expected to be delivered based on the planned order releases.
**Planned order releases** are the quantities to be ordered to meet future gross requirements considering the lot size and lead time.

### Objectives

1. Keep the projected on-hand inventory from going negative by planning orders.
2. Determine the correct timing and quantities to place orders to ensure there are sufficient materials for production.

To accomplish this, consider the FO
Transcribed Image Text:# Inventory Record Analysis for Driveshaft Subassembly ## Overview This section analyzes the partially completed inventory record for a driveshaft subassembly. The table provided details the gross requirements, scheduled receipts, lead time, and current on-hand inventory. It helps in understanding materials requirement planning (MRP) for manufacturing processes. ## Instructions Complete the last three rows (Projected on-hand inventory, Planned receipts, and Planned order releases) for a Fixed Order Quantity (FOQ) of 55 units. Enter your responses as integers, where '0' indicates that the particular action is not applicable. ### Item: Driveshaft Subassembly #### Input Parameters: - **Lot Size**: FOQ = 55 units - **Lead Time**: 3 weeks ### Table The table is structured across a span of 8 weeks to record the inventory data accurately. | Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |------|---|---|---|---|---|---|---|---| | **Gross requirements** | 30 | 20 | 20 | 20 | 45 | 45 | 50 | 50 | | **Scheduled receipts** | 70 | - | - | - | - | - | - | - | | **Projected on-hand inventory** | 10 | - | - | - | - | - | - | - | | **Planned receipts** | - | - | - | - | - | - | - | - | | **Planned order releases** | - | - | - | - | - | - | - | - | ### Explanation **Gross requirements** list the total demand for the driveshaft subassemblies each week. **Scheduled receipts** indicate any existing orders expected to be added to the inventory during that specific week. **Projected on-hand inventory** tracks the expected inventory remaining at the end of each week after accounting for the gross requirements. **Planned receipts** are the quantities expected to be delivered based on the planned order releases. **Planned order releases** are the quantities to be ordered to meet future gross requirements considering the lot size and lead time. ### Objectives 1. Keep the projected on-hand inventory from going negative by planning orders. 2. Determine the correct timing and quantities to place orders to ensure there are sufficient materials for production. To accomplish this, consider the FO
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.