The demand for subassembly S is 90 units in week 7 Each unit of S requires 1 unit of T and 1 unit of U. Each unit of T requires 1 unit of V, 1 unit of W, and 2 units of X. Finally, each unit of U requires 1 unit of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 2 weeks to make T, 2 weeks to make U, 2 weeks to make V, 2 weeks to make W, 1 week to make X, 2 weeks to make Y, and 2 weeks to make Z Click the icon to view the product structure and the time-phased product structure In addition to 90 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are needed for maintenance purposes These units are needed in week 6 Modify the gross material requirements plan to reflect this change (type 0 if the input box is not used) Item S T Gross req Order release Gross req Order release 1 2 3 Week 4 5 6 7 Lead Time (weeks) 2 2
The demand for subassembly S is 90 units in week 7 Each unit of S requires 1 unit of T and 1 unit of U. Each unit of T requires 1 unit of V, 1 unit of W, and 2 units of X. Finally, each unit of U requires 1 unit of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 2 weeks to make T, 2 weeks to make U, 2 weeks to make V, 2 weeks to make W, 1 week to make X, 2 weeks to make Y, and 2 weeks to make Z Click the icon to view the product structure and the time-phased product structure In addition to 90 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are needed for maintenance purposes These units are needed in week 6 Modify the gross material requirements plan to reflect this change (type 0 if the input box is not used) Item S T Gross req Order release Gross req Order release 1 2 3 Week 4 5 6 7 Lead Time (weeks) 2 2
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question

Transcribed Image Text:The demand for subassembly S is 90 units in week 7 Each unit of 5 requires 1 unit of T and 1 unit of U. Each unit of T requires 1 unit of V, 1 unit of W, and 2
units of X. Finally, each unit of U requires 1 unit of Y and 3 units of Z. One firm manufactures all dems. It takes 2 weeks to make S, 2 weeks to make T, 2 weeks
to make U, 2 weeks to make V, 2 weeks to make W, 1 week to make X 2 weeks to make Y, and 2 weeks to make Z
Click the icon to view the product structure and the time-phased product structure
In addition to 90 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are needed for maintenance purposes
These units are needed in week 6. Modify the gross material requirements plan to reflect this change (type 0 if the input box is not used)
Item
S
T
U
V
W
X
Y
Gross req
Order release
Gross req
Order release
Gross req
Order release
Gross roq
Order release
Gross req
Order release
Gross req
Order release
Gross req
Order release
E
2
T
P
3
BE
Week
4
5 6
7
Lead Time
(weeks)
2
2
12
2
2
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 6 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.