Master Production Schedule for X1 PERIOD 7 8. 9 10 11 12 Subassembly X1 Gross requirements 50 20 100 B11) B22) LEAD ON LEAD ON ITEM TIME HAND ITEM TIME HAND E) Ca D X1 1 50 C 1 B1 20 D 1 B2 20 E 3. 10 A1 5 Figure 14.12 Information for Problem 14.10 ON-HAND ON-HAND ITEM INVENTORY ITEM INVENTORY 20 W 30 T 20 25 U 40 Y 240 V 30 40

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Refer again to Problem ( Using the information in Problem (The demand for subassembly Sis 100 units in week 7. Each unit ofS requires 1 unit ofT and 2 units ofU. Each unit of
T requires I unit ofY, 2 units ofW, and 1 unit of X. Finally, each
unit of U requires 2 units of Y and 3 units of Z. One firm manufactures
all items. It takes 2 weeks to make S, 1 week to make T,                                                                                                                                                                                                                                2 weeks to make U, 2 weeks to make Y, 3 weeks to make W,
I week to make X, 2 weeks to make Y, and I week to make Z.
a) Construct a product structure. Identify all levels, parents, and components.
b) Prepare a time-phased product structure. ), construct a net
material requirements plan using the following on-hand inventory.  ) In addition to
100 units of S, there is also a demand for 20 units of U, which is
a component of S. The 20 units of U are needed for maintenance
purposes. These units are needed in week 6. Modify the gross
material requirements plan to reflect this change.
Master Production Schedule for X1
PERIOD
7
8.
9
10
11
12
Subassembly
X1
Gross requirements
50
20
100
B11)
B22)
LEAD
ON
LEAD
ON
ITEM
TIME
HAND
ITEM
TIME
HAND
E)
Ca D
X1
1
50
C
1
B1
20
D
1
B2
20
E
3.
10
A1
5
Figure 14.12
Information for Problem 14.10
Transcribed Image Text:Master Production Schedule for X1 PERIOD 7 8. 9 10 11 12 Subassembly X1 Gross requirements 50 20 100 B11) B22) LEAD ON LEAD ON ITEM TIME HAND ITEM TIME HAND E) Ca D X1 1 50 C 1 B1 20 D 1 B2 20 E 3. 10 A1 5 Figure 14.12 Information for Problem 14.10
ON-HAND
ON-HAND
ITEM
INVENTORY
ITEM
INVENTORY
20
W
30
T
20
25
U
40
Y
240
V
30
40
Transcribed Image Text:ON-HAND ON-HAND ITEM INVENTORY ITEM INVENTORY 20 W 30 T 20 25 U 40 Y 240 V 30 40
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.