The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 2 units of V, 1 unit of W, and 2 units of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 2 weeks to make X, 2 weeks to make Y, and 2 weeks to make Z. a) Choose the correct product structure. O A. ✅C. Level 0 U(2) 1 7 2 V(2) Y(2) Z(3) W(1) X(2) O A. Level 0 1 Y Z T(1) 2 V(2) W(1) X(2) Y(2) Z(3) V b) Choose the correct time-phased product structure. W T X S U S Time in weeks (1) Q Q Q Q U(2) Q O B. V w N < x < T U Time in weeks S O B. O D. O C. Level 0 V(2) 1 2 T(1) W(1) X(2) Y(2) Z(3) G Level 0 1 Y Z T(1) 2 Y(2) W(1) X(2) U(2) Z(3) V WT X U S Time in weeks S S U₁2) Q V(2) Q O D. -NE T X ▬>T VI Time in weeks

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 2 units of V, 1 unit of W, and 2 units
of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U,
2 weeks to make V, 3 weeks to make W, 2 weeks to make X, 2 weeks to make Y, and 2 weeks to make Z.
a) Choose the correct product structure.
OA.
Level
0
O A.
U(2)
1
2 V(2) Y(2) Z(3) W(1) X(2)
Level
0
1
> N
T(1)
2 V(2) W(1) X(2) Y(2) Z(3)
> X
V
W T
S
U
b) Choose the correct time-phased product structure.
S
S
1 2 3 4 5 6 7
Time in weeks
T(1)
U (2)
Q
Q
Q
Q
O B.
1
> ≤ x > N
2
W
X
Y
-NE
TI
U
3 4 5
Time in weeks
6
S
7
Q
✔
OB.
O D.
O C.
Level
0
V(2)
7
2 T(1) W(1) X(2) Y(2) Z(3)
1
Level
0
1
Y
Z
T(1)
2 Y(2) W(1) X(2) U(2) Z(3)
VI
W T
X
U
S
1 2 3 4 5 6
Time in weeks
S
S
U (2)
Q
V(2)
Q
Q
Q
O D.
S
1 2 3 4
U
T
X
V
5
Time in weeks
Z
Y
W
6 7
Q
Transcribed Image Text:The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 2 units of V, 1 unit of W, and 2 units of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 2 weeks to make X, 2 weeks to make Y, and 2 weeks to make Z. a) Choose the correct product structure. OA. Level 0 O A. U(2) 1 2 V(2) Y(2) Z(3) W(1) X(2) Level 0 1 > N T(1) 2 V(2) W(1) X(2) Y(2) Z(3) > X V W T S U b) Choose the correct time-phased product structure. S S 1 2 3 4 5 6 7 Time in weeks T(1) U (2) Q Q Q Q O B. 1 > ≤ x > N 2 W X Y -NE TI U 3 4 5 Time in weeks 6 S 7 Q ✔ OB. O D. O C. Level 0 V(2) 7 2 T(1) W(1) X(2) Y(2) Z(3) 1 Level 0 1 Y Z T(1) 2 Y(2) W(1) X(2) U(2) Z(3) VI W T X U S 1 2 3 4 5 6 Time in weeks S S U (2) Q V(2) Q Q Q O D. S 1 2 3 4 U T X V 5 Time in weeks Z Y W 6 7 Q
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.