One unit of A is composed of two units of B and three units of C. Each B is composed of one unit of F. C is made of one unit of D, one unit of E, and two units of F. Items A, B, C, and D have 20, 50, 30, and 25 units of on-hand inventory. Items A, B, and C use lot-for-lot (L4L) as their lot-sizing technique, while D, E, and F require multiples of 50, 100, and 90, respectively, to be purchased. B has scheduled receipts of 20 units in Period 1. No other scheduled receipts exist. Lead times are one period for Items A, B, and D, and two periods for Items C, E, and F. Gross requirements for A are 20 units in Period 1, 10 units in Period 2, 55 units in Period 6, and 50 units in Period 8.   Find the planned order releases for all items. (Leave no cells blank - be certain to enter "0" wherever required.)

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

 

Problem 21-16 (Algo)

One unit of A is composed of two units of B and three units of C. Each B is composed of one unit of F. C is made of one unit of D, one unit of E, and two units of F. Items A, B, C, and D have 20, 50, 30, and 25 units of on-hand inventory. Items A, B, and C use lot-for-lot (L4L) as their lot-sizing technique, while D, E, and F require multiples of 50, 100, and 90, respectively, to be purchased. B has scheduled receipts of 20 units in Period 1. No other scheduled receipts exist. Lead times are one period for Items A, B, and D, and two periods for Items C, E, and F. Gross requirements for A are 20 units in Period 1, 10 units in Period 2, 55 units in Period 6, and 50 units in Period 8.

 

Find the planned order releases for all items. (Leave no cells blank - be certain to enter "0" wherever required.)

 

 
Hem A
OH-20
LT-1
SS-0
Q-LE
hem
CH-50
LT-1
SS-D
Q-LA
hem C
CH-30
LT=2
55.0
Q-LE
ham D
CH-25
LT=1
S5-D
Q-50
Period
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Gross requirements
Scheduled receipts
Projected available balance
Not requirements
Planned order receipts
Planned order releases
Gross requirements
Scheduled receipts
Projected available balance
Not requirements
Planned order receipts
Planned order releases
Gross regements
Scheduled receipts
Projected valable balance
Not requirements
Planned order recip
Planned order
Grossements
Transcribed Image Text:Hem A OH-20 LT-1 SS-0 Q-LE hem CH-50 LT-1 SS-D Q-LA hem C CH-30 LT=2 55.0 Q-LE ham D CH-25 LT=1 S5-D Q-50 Period Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Gross requirements Scheduled receipts Projected available balance Not requirements Planned order receipts Planned order releases Gross requirements Scheduled receipts Projected available balance Not requirements Planned order receipts Planned order releases Gross regements Scheduled receipts Projected valable balance Not requirements Planned order recip Planned order Grossements
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 7 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.