The activities necessary for the completion of this project are listed in the following table: Normal Crash Time Time Normal Crash Immediate Predecessor(S) Activity (Weeks) (Weeks) Cost Cost 6 3 $2,100 $2,700 -- 1 1,900 2,400 3 400 800 6 1,950 2,500 с 3 1,100 1,200 A, B 1 3,100 4,000 D, E a. What is the project completion date? [Select] weeks b. What is the total cost required for completing this project on normal time? [Select] c. If you wish to reduce the time required to complete this project by 2 weeks, which activity(s) should be crashed? [Select] V and how much will this increase the total cost by? $ [Select] d. If you required an additional week reduction, what activity would you crash? [Select] and how much is the total 3 week cost of 7 crashing? $ [Select] ABCDEF 2003 12 4 8 4
The activities necessary for the completion of this project are listed in the following table: Normal Crash Time Time Normal Crash Immediate Predecessor(S) Activity (Weeks) (Weeks) Cost Cost 6 3 $2,100 $2,700 -- 1 1,900 2,400 3 400 800 6 1,950 2,500 с 3 1,100 1,200 A, B 1 3,100 4,000 D, E a. What is the project completion date? [Select] weeks b. What is the total cost required for completing this project on normal time? [Select] c. If you wish to reduce the time required to complete this project by 2 weeks, which activity(s) should be crashed? [Select] V and how much will this increase the total cost by? $ [Select] d. If you required an additional week reduction, what activity would you crash? [Select] and how much is the total 3 week cost of 7 crashing? $ [Select] ABCDEF 2003 12 4 8 4
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
![The activities necessary for the completion of this project are listed in the
following table:
Normal
Crash
Time
Time
Normal Crash
Immediate
Predecessor(S)
Activity (Weeks)
(Weeks)
Cost
Cost
6
3
$2,100
$2,700
--
1
1,900
2,400
--
3
400
800
6
1,950
2,500
с
3
1,100
1,200
A, B
1
3,100
4,000
D, E
a. What is the project completion date? [Select]
weeks
b. What is the total cost required for completing this project on normal time?
[Select]
c. If you wish to reduce the time required to complete this project by 2 weeks,
which activity(s) should be crashed? [Select]
V
and how
much will this increase the total cost by? $ [Select]
d. If you required an additional week reduction, what activity would you crash?
[Select]
and how much is the total 3 week cost of
"
crashing? $ [Select]
ABCDEF
2003
12
4
8
4](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F1516f125-856f-4026-8d08-7de3645b541e%2F45ab8517-8f33-48fc-b023-d6ef885bbeb1%2Fi5dx6we_processed.jpeg&w=3840&q=75)
Transcribed Image Text:The activities necessary for the completion of this project are listed in the
following table:
Normal
Crash
Time
Time
Normal Crash
Immediate
Predecessor(S)
Activity (Weeks)
(Weeks)
Cost
Cost
6
3
$2,100
$2,700
--
1
1,900
2,400
--
3
400
800
6
1,950
2,500
с
3
1,100
1,200
A, B
1
3,100
4,000
D, E
a. What is the project completion date? [Select]
weeks
b. What is the total cost required for completing this project on normal time?
[Select]
c. If you wish to reduce the time required to complete this project by 2 weeks,
which activity(s) should be crashed? [Select]
V
and how
much will this increase the total cost by? $ [Select]
d. If you required an additional week reduction, what activity would you crash?
[Select]
and how much is the total 3 week cost of
"
crashing? $ [Select]
ABCDEF
2003
12
4
8
4
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 5 steps with 3 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.