make the project start date 3 Jan 2022 Level the following multi-project operation. Work package Description Duration (weeks) Predecessors Resources A1 Analysis & design – Proj 1 4 - SAD B1 Production – Proj 1 7 A1 PROD C1 Testing – Proj 1 3 B1 TEST D1 Install – Proj 1 2 C1 INSTALL A2 Analysis & design – Proj 2 4 A1 SAD B2 Production – Proj 2 5 A2 PROD C2 Testing – Proj 2 3 B2 TEST D2 Install – Proj 2 1 C2 INSTALL A3 Analysis & design – Proj 3 8 A2 SAD B3 Production – Proj 3 12 A3 PROD C3 Testing – Proj 3 5 B3 TEST D3 Install – Proj 3 3 C3 INSTALL A4 Analysis & design – Proj 4 8 A3 SAD B4 Production – Proj 4 10 A4 PROD C4 Testing – Proj 4 4 B4 TEST D4 Install – Proj 4 2 C4 INSTALL show the schedual before the leveling show the schedual of the project after leveling 3.If all work was to be done by the deadline of the end of week 40, what resources are causing delay?
make the project start date 3 Jan 2022
Level the following multi-project operation.
Work package |
Description |
Duration (weeks) |
Predecessors |
Resources |
A1 |
Analysis & design – Proj 1 |
4 |
- |
SAD |
B1 |
Production – Proj 1 |
7 |
A1 |
PROD |
C1 |
Testing – Proj 1 |
3 |
B1 |
TEST |
D1 |
Install – Proj 1 |
2 |
C1 |
INSTALL |
A2 |
Analysis & design – Proj 2 |
4 |
A1 |
SAD |
B2 |
Production – Proj 2 |
5 |
A2 |
PROD |
C2 |
Testing – Proj 2 |
3 |
B2 |
TEST |
D2 |
Install – Proj 2 |
1 |
C2 |
INSTALL |
A3 |
Analysis & design – Proj 3 |
8 |
A2 |
SAD |
B3 |
Production – Proj 3 |
12 |
A3 |
PROD |
C3 |
Testing – Proj 3 |
5 |
B3 |
TEST |
D3 |
Install – Proj 3 |
3 |
C3 |
INSTALL |
A4 |
Analysis & design – Proj 4 |
8 |
A3 |
SAD |
B4 |
Production – Proj 4 |
10 |
A4 |
PROD |
C4 |
Testing – Proj 4 |
4 |
B4 |
TEST |
D4 |
Install – Proj 4 |
2 |
C4 |
INSTALL |
- show the schedual before the leveling
- show the schedual of the project after leveling
3.If all work was to be done by the deadline of the end of week 40, what resources are causing delay?