make the project start date 3 Jan 2022 Level the following multi-project operation. Work package Description Duration (weeks) Predecessors Resources A1 Analysis & design – Proj 1 4 - SAD B1 Production – Proj 1 7 A1 PROD C1 Testing – Proj 1 3 B1 TEST D1 Install – Proj 1 2 C1 INSTALL A2 Analysis & design – Proj 2 4 A1 SAD B2 Production – Proj 2 5 A2 PROD C2 Testing – Proj 2 3 B2 TEST D2 Install – Proj 2 1 C2 INSTALL A3 Analysis & design – Proj 3 8 A2 SAD B3 Production – Proj 3 12 A3 PROD C3 Testing – Proj 3 5 B3 TEST D3 Install – Proj 3 3 C3 INSTALL A4 Analysis & design – Proj 4 8 A3 SAD B4 Production – Proj 4 10 A4 PROD C4 Testing – Proj 4 4 B4 TEST D4 Install – Proj 4 2 C4 INSTALL show the schedual before the leveling show the schedual of the project after leveling 3.If all work was to be done by the deadline of the end of week 40, what resources are causing delay?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

make the project start date 3 Jan 2022

Level the following multi-project operation.

Work package

Description

Duration (weeks)

Predecessors

Resources

A1

Analysis & design – Proj 1

4

-

SAD

B1

Production – Proj 1

7

A1

PROD

C1

Testing – Proj 1

3

B1

TEST

D1

Install – Proj 1

2

C1

INSTALL

A2

Analysis & design – Proj 2

4

A1

SAD

B2

Production – Proj 2

5

A2

PROD

C2

Testing – Proj 2

3

B2

TEST

D2

Install – Proj 2

1

C2

INSTALL

A3

Analysis & design – Proj 3

8

A2

SAD

B3

Production – Proj 3

12

A3

PROD

C3

Testing – Proj 3

5

B3

TEST

D3

Install – Proj 3

3

C3

INSTALL

A4

Analysis & design – Proj 4

8

A3

SAD

B4

Production – Proj 4

10

A4

PROD

C4

Testing – Proj 4

4

B4

TEST

D4

Install – Proj 4

2

C4

INSTALL

  1. show the schedual before the leveling
  2. show the schedual of the project after leveling

3.If all work was to be done by the deadline of the end of week 40, what resources are causing delay?

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 4 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.