Independent requirements (demand) for product AGBI1000 are given below: Period Independent Requirements Week 49/Current year 15 Week 50/Current year 10 Week 51/Current year 20 Week 52/Current year 25 Some Relevant Material Master Data Material Lot Size Lead time Procurement Material type type In-house Finished AGBI1### 7 days LFL prođuction Product In-house Semi-finished LFL 7 đays BGBI1### production Product In-house Semi-finished CGBI1### LFL 14 days production Product Fixed Lot of External DGBI1### 300 7 days Raw Material Procurement Fixed Lot of External EGBI1### 7 days Raw Material 500 Procurement
Prepare an MRP
MRP CALCULATIONS
|
Step by step
Solved in 2 steps with 2 images