Ronald Lau, chief engineer at South Dakota Electronics, has to decide whether to build a new state-of-the-art processing facility. If the new facility works, the company could realize a profit of $200,000. If it fails, South Dakota Electronics could lose $180,000. At this time, Lau estimates a 60% chance that the new process will fail. The other option is to build a pilot plant and then decide whether to build a complete facility. The pilot plant would cost $10,000 to build. Lau estimates a 50 - 50 chance that the pilot plant will work. If the pilot plant works, there is a 90% probability that the complete plant, if it is built, will also work. If the pilot plant does not work, there is only a 20% chance that the complete project (if it is constructed) will work. Lau faces a dilemma. Should he build the plant? Should he build the pilot project and then make a decision? Help Lau by analyzing this problem. Px

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter9: Decision Making Under Uncertainty
Section: Chapter Questions
Problem 30P
icon
Related questions
Question
Ronald Lau, chief engineer at South Dakota Electronics, has to decide whether to
build a new state-of-the-art processing facility. If the new facility works, the
company could realize a profit of $200,000. If it fails, South Dakota Electronics could
lose $180,000. At this time, Lau estimates a 60% chance that the new process will
fail.
The other option is to build a pilot plant and then decide whether to build a
complete facility. The pilot plant would cost $10,000 to build. Lau estimates a 50 -
50 chance that the pilot plant will work. If the pilot plant works, there is a 90%
probability that the complete plant, if it is built, will also work. If the pilot plant does
not work, there is only a 20% chance that the complete project (if it is constructed)
will work. Lau faces a dilemma. Should he build the plant? Should he build the pilot
project and then make a decision? Help Lau by analyzing this problem. Px
Transcribed Image Text:Ronald Lau, chief engineer at South Dakota Electronics, has to decide whether to build a new state-of-the-art processing facility. If the new facility works, the company could realize a profit of $200,000. If it fails, South Dakota Electronics could lose $180,000. At this time, Lau estimates a 60% chance that the new process will fail. The other option is to build a pilot plant and then decide whether to build a complete facility. The pilot plant would cost $10,000 to build. Lau estimates a 50 - 50 chance that the pilot plant will work. If the pilot plant works, there is a 90% probability that the complete plant, if it is built, will also work. If the pilot plant does not work, there is only a 20% chance that the complete project (if it is constructed) will work. Lau faces a dilemma. Should he build the plant? Should he build the pilot project and then make a decision? Help Lau by analyzing this problem. Px
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning