Problem: For the information below, first draw the network diagram and determine how long the project will take and what the project will cost under normal conditions. Then, determine how much each additional day crashed will cost, down to the minimum completion time. Finally, fill in the table below with the total cost to complete the project depending on how many days it will take to complete. Activity Predecessor Normal Crash Time Normal Cost 2000 Cost/ Day Crash Time Cost 3600 1500 A 3 B 4 2 1000 A В 1500 3000 3000 7 6000 6000 4 В 4000 F C,D 4 1 3000 4800 Completion Days Cost 15 14 13 12 11 10 8. 7
Problem: For the information below, first draw the network diagram and determine how long the project will take and what the project will cost under normal conditions. Then, determine how much each additional day crashed will cost, down to the minimum completion time. Finally, fill in the table below with the total cost to complete the project depending on how many days it will take to complete. Activity Predecessor Normal Crash Time Normal Cost 2000 Cost/ Day Crash Time Cost 3600 1500 A 3 B 4 2 1000 A В 1500 3000 3000 7 6000 6000 4 В 4000 F C,D 4 1 3000 4800 Completion Days Cost 15 14 13 12 11 10 8. 7
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question

Transcribed Image Text:Problem:
For the information below, first draw the network diagram and determine how long the
project will take and what the project will cost under normal conditions. Then, determine
how much each additional day crashed will cost, down to the minimum completion time.
Finally, fill in the table below with the total cost to complete the project depending on how
many days it will take to complete.
Crash
Activity Predecessor Normal Crash
Time
Normal
Cost/
Time
Cost
Cost
Day
A
3
2000
3600
В
4
1000
1500
A
3
2
1500
3000
В
7
4
3000
6000
E
В
9
4000
6000
C,D
4
1
3000
4800
Completion
Days
Cost
15
14
13
12
11
10
9
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 1 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.