a) Draw the network diagram. What is the project completion time? What is the critical path? b) Crash activity B by one day. What is the new project completion time?
a) Draw the network diagram. What is the project completion time? What is the critical path? b) Crash activity B by one day. What is the new project completion time?
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question

Transcribed Image Text:Problem Solving: Project crashing
Given the following activity information:
NORMAL CRASH
CRASHING CRITICAL
COST / day
TIME
TIME
NORMAL
CRASH
ACTIVITY PREDECESSORS
(days)
(days)
COST ($) COST ($)
РАТН
A
4
3
125
250
В
8.
6
150
650
C
3
300
600
D
A
4
400
500
E
4
200
300
F
B,D,E
3
2
250
450
a) Draw the network diagram. What is the project completion time? What is the critical
path?
b) Crash activity B by one day. What is the new project completion time?
c) Crash the project by 4 days. What is the crashing cost?
d) What is the project total cost after crashing?
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 1 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.