POLE BARN - SCHEDULING ACTIVITY 1 1) For the pole barn, sketch a network diagram and determine the activity predecessors for each activity in the table below. Activity Activity Description Duration (days) Predecessors Float Times A Mobilize 3 B Order Poles 12 A C Clear Site 2 A D Order Lumber 16 B E Order Roofing Materials 22 B F Grade Site 15 C G Set Poles 2 B,F H Trench for Gas Lines 2 G | Trench for Water Lines 2 G J Set Joists 5 G K Install Gas Lines 12 H L Install Water Lines 18 M Install Roofing 15 D,E N Install Siding 21 M ° Set Doors 1 J P Install Electrical Wiring and 10 Fixtures N,O Q Paint 5 P R Clean-up 2 Q S Demobilize 2 R 2) Determine the critical path and activity float times for each activity. 3) Prepare a mitigation plan for your determined critical path.

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
POLE BARN - SCHEDULING ACTIVITY 1
1) For the pole barn, sketch a network diagram and determine the activity predecessors for
each activity in the table below.
Activity
Activity Description
Duration (days)
Predecessors
Float Times
A
Mobilize
3
B
Order Poles
12
A
C
Clear Site
2
A
D
Order Lumber
16
B
E
Order Roofing Materials
22
B
F
Grade Site
15
C
G
Set Poles
2
B,F
H
Trench for Gas Lines
2
G
|
Trench for Water Lines
2
G
J
Set Joists
5
G
K
Install Gas Lines
12
H
L
Install Water Lines
18
M
Install Roofing
15
D,E
N
Install Siding
21
M
°
Set Doors
1
J
P
Install Electrical Wiring and
10
Fixtures
N,O
Q
Paint
5
P
R
Clean-up
2
Q
S
Demobilize
2
R
2) Determine the critical path and activity float times for each activity.
3) Prepare a mitigation plan for your determined critical path.
Transcribed Image Text:POLE BARN - SCHEDULING ACTIVITY 1 1) For the pole barn, sketch a network diagram and determine the activity predecessors for each activity in the table below. Activity Activity Description Duration (days) Predecessors Float Times A Mobilize 3 B Order Poles 12 A C Clear Site 2 A D Order Lumber 16 B E Order Roofing Materials 22 B F Grade Site 15 C G Set Poles 2 B,F H Trench for Gas Lines 2 G | Trench for Water Lines 2 G J Set Joists 5 G K Install Gas Lines 12 H L Install Water Lines 18 M Install Roofing 15 D,E N Install Siding 21 M ° Set Doors 1 J P Install Electrical Wiring and 10 Fixtures N,O Q Paint 5 P R Clean-up 2 Q S Demobilize 2 R 2) Determine the critical path and activity float times for each activity. 3) Prepare a mitigation plan for your determined critical path.
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning