i. Draw the network diagram linking all the activities in a way that it shows if there exist any preceding activity/activities before starting each of the mentioned activities in the above table Showing the earliest start time, the earliest finish time, the latest start time and the latest finish time of each of the activities in the project determine the completion time of the i. project and the critical path. Find the slack time (delay time) of each of the activities, the critical and the non-critical iii. activities.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Crashed Cost per
Preceding
Activity
Normal Completion
Time (week)
Crashed Completion
time (week)
6.
Activity
week
$500
$400
$500
$700
$600
$500
$800
A
A
6.
10
8.
В, С
9.
8.
E
D
5.
4
F
E
7
6.
D
10
i.
Draw the network diagram linking all the activities in a way that it shows if there exist any
preceding activity/activities before starting each of the mentioned activities in the above
table
ii.
Showing the earliest start time, the earliest finish time, the latest start time and the latest
finish time of each of the activities in the project determine the completion time of the
project and the critical path.
ii.
Find the slack time (delay time) of each of the activities, the critical and the non-critical
activities.
iv.
Find the minimum possible completion time of the project by considering the crashed
completion times and the minimal total cost of that crashing the project.
V.
Highlight the critical and non-critical activities of the finally completed project by taking into
account the crashed times of activities.
Transcribed Image Text:Crashed Cost per Preceding Activity Normal Completion Time (week) Crashed Completion time (week) 6. Activity week $500 $400 $500 $700 $600 $500 $800 A A 6. 10 8. В, С 9. 8. E D 5. 4 F E 7 6. D 10 i. Draw the network diagram linking all the activities in a way that it shows if there exist any preceding activity/activities before starting each of the mentioned activities in the above table ii. Showing the earliest start time, the earliest finish time, the latest start time and the latest finish time of each of the activities in the project determine the completion time of the project and the critical path. ii. Find the slack time (delay time) of each of the activities, the critical and the non-critical activities. iv. Find the minimum possible completion time of the project by considering the crashed completion times and the minimal total cost of that crashing the project. V. Highlight the critical and non-critical activities of the finally completed project by taking into account the crashed times of activities.
Expert Solution
steps

Step by step

Solved in 2 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.