Crash the project to 25 days. а. b. What will the total crashing cost be? с. What activities will be crashed?
Q: WBS stands for which of the following project management tools? work break schedule O work breakdo
A: THE ANSWER IS AS BELOW:
Q: 1. Prepare the Activity Node Diagram and identify the Critical Path 2. Prepare Gantt Chart Thankss
A: Given data is
Q: QUESTION: "Business Project Development Cycle" and "Project Lifecyle". Is it the same or not? Please…
A: There is a conceptual difference between both the terms as per the nature of processes gets…
Q: Consider a project with the following activities. The normal duration and cost, crash duration and…
A:
Q: What is Project Scope Management? Discuss Project Scope and Product Scope. Why do you think…
A: It is a dream of every project manager that his project goes efficiently and smoothly from initial…
Q: Draw PDM of the above and calculate the Total and free float Q2. What is Fast Tracking and crashing…
A: The critical path method (CPM) is a project management technique used to determine the most…
Q: 5. List the critical path(s) and costs to reduce the duration by 2 days. (Show all steps to reduce…
A: Given data is
Q: immediate Latest Carlest Latest Activity Predecessor Optimistic Probable Pessimistic Activities…
A: A project schedule network diagram shows the sequence of the task that is performed to complete a…
Q: a) Activity that should be crashed first to reduce the project duration by 1 day is __ Part 3 b)…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: Which phase in the project life cycle involves evaluating expected costs, benefits, and risks?
A: Planning The expected cost ,benefits and risks are evaluated and identified on the planning stage.
Q: What is the probability that this project will be completed within 22 days? Group of answer…
A: A network diagram shows the link of each task with the duration taken by each activity with respect…
Q: QUESTION 1 Activity LP A B C D AUS BO Time (Days) 3-6 2514 44 17 AB339 CP3 6 15 DO Exp. Time…
A: ActivityampExpected timeVarianceA251464.0000B14741.0000C12320.1111D33941.0000E361574.0000
Q: RM375,000. From the above, estimate the costs of the project if the project team decided to complete…
A: Earned value analysis is a technique of project management that can measure and assess the…
Q: G H Activity A BCDEFG Normal Predecessor Duration 7 3 ABB А Crashing - Example Crash Duration 6 A…
A: Find the network diagram below: Duration:
Q: ID Immediate Time (weeks) Predecessor A 6 B. 4 3. D. A, B, C 7 4. F D 2 H. ID Cost by week (in…
A:
Q: Activity Description Preceded bDy Time (WKS) Feasibility Study Estimate production volumes Market…
A: i) the AOA format, the possible path activities would look like:
Q: Required i) The expected duration and variance for each activity. ii) The project network. iii) The…
A: Here, activities are identified by their beginning and ending note numbers. For each activity, I…
Q: The table below presents the information required in order to carry out a critical path analysis of…
A: Project management: Project management is the utilization of explicit information, abilities,…
Q: • Q1: Determine the critical path, the critical activities and the project completion time.…
A: A project network diagram is the visual representation of the project activities and their durations…
Q: Projects with very general scope definitions are at risk of expanding gradually, without specific…
A: NOTE: We are allowed to do one question only. Projects are also useful for learning new…
Q: The critical path through a network consists of activities A, B and C where each activity has an…
A: Duration of each critical activity = 10 weeks Total duration of critical path = Duration of A +…
Q: Q1. Based on the table below, solve the questions (1-4). Activity Predecessor Optimistic Duration…
A: Since you have submitted questions with multiple subparts, as per guideline we have answered the…
Q: Q3: Determine the time completion of project for the activities shown below: Activity ABCD E FGHI K…
A: given
Q: a. Calculate ALL the missing (?) data points. b. Draw the PERT network from the given data. c.…
A: NOTE: We are allowed to do the first three sub-parts only. PERT is a project management tool used…
Q: 1. Draw AOA network and Find the project duration.
A: project management is the main goal of an organization in completing tasks Project management…
Q: L. Consider a project whose activities are listed in the table below. What is the expected duration…
A: Here, for each activity, I have been given the immediate predecessors' data, and the duration data,…
Q: Act Immediate Predecessor Duration Activity Description Relationship Lag (weeks) ID (weeks) Planning…
A: The precedence relationship diagram is as follows: The possible paths are: 1) P1 - P3 - D3 - D4…
Q: Q4) Ch9: - Answer the questions for the below network: Activity Normal Crashed T.F. Slope Duration…
A: The critical path method (CPM), also called critical path analysis (CPA), is a scheduling procedure…
Q: 2 3 4 5 6 7 8 9 10 Task Mode - - C Task Name MANAGEMENT PLANS AND PERMITS Complete kitchen drawings…
A: The Gantt chart is a visual representation of the overall progress of the project. Knowledge of…
Q: 1.Forecast Completion •What is the Estimate at Completion? •New bottom up estimate is 575,000…
A: As the project progresses, the original budget may no longer be realistic because of the changed…
Q: a) What is the target completion week? b) How much would you save in total project costs with your…
A: First, I will prepare the precedence diagram using normal time data and immediate predecessor…
Q: QUESTION 2. The activities involved in the construction of a new shopping mall are given in Table…
A: Given data is
Q: The following Table 1 (below) contains a list of activities, with precedence requirements and crash…
A: Find the Given details below: Activity Predecessors Normal Time (NT) (Days) Normal cost (NC) ($)…
Q: Question 5 A project's requirement involves what the project is supposed to accomplish, and how it…
A: Project requirements are crucial to any project's success. They specify what the project is intended…
Q: Don't use Ai
A: I hope you find this helpful. If you have any question or clarification, do not hesitate to reach…
Q: Discuss the concept of Project Crashing
A: When abbreviate the duration of a project by lowering the time of one or more tasks, this is known…
Q: Question 4 When the objectives of a project meet, or exceed, the expectations of its stakeholders,…
A: Stakeholders are individuals or groups who have a vested interest in a project and can affect, or be…
Q: A E 10 Start B D Identify the critical path of the network above O A-E-G O B-D-E-G O C-F-G O C-F-G…
A: The critical path represents the longest path (in the given time) since Start to Finish; it means…
Q: Q.No.3. When we start a project how we know this project or program is feasible for our future?…
A: Before starting a project, its feasibility for the future is understood by the feasibility study.…
Q: Q1) Calculate with PERT Method for the following activities of Project : m b a النشاط الوقت المتفائل…
A: Q1) Calculate with PERT Method for the following activities of the Project:Activity | Optimistic…
Q: Question 4 a) ‘project success is imbedded in project manager’s soft skills’ explain? b) To what…
A: Answer - (a) As given in the question, 'project success is imbedded in project manager soft skills'…
Q: D Question 1 What is the earliest finish time for activity B? O 8 days O 32 days O 20 days O 12 days…
A: ES Task EF LS Time LF ES = Early Start EF = Early Finish LS = Late Start LF = Late Finish…
Q: Q1:Find the critical path, total permittivity, and time period required to complete the construction…
A: Answer is as below:
Q: agement studies at CPUT, he projected that e nated that the side will all need the same am plete the…
A: Given: Total project cost=R4000 70% of the project completes We have to calculate the earned value…
Step by step
Solved in 4 steps with 9 images
- QUESTION 3 VP Manufacturers is considering renovating their offices at their Durban head office. (40 Marks) 3.1 Use the generated information to calculate the NPV of the project, to decide whether to go ahead with the project. (20 Marks) Investment required Expected economic lifetime Minimum required rate of return R200 000 5 years. 10% Net annual cash inflows 1st year 2nd year 3rd year R40 000 R100 000 R90 000 R40 000 4th year 5th year R30 000 3.2 VP Manufacturers has decided to go ahead with the project. The following activities has been determined for the office renovation project. Construct a network diagram (AON) to create a graphical description of the operations and their relationship to each other. Identity the critical path for the project. Task/Number Duration (Days) Predecessors A 12 B 8 A C 4 A D 7 C E 6 B. D F 7 E (20 Marks) QUESTION 4 (20 Marks) There is a need for an organisation to manage its human, cost, and technological resources effectively. Therefore, project…i need the answer quicklyQ.1. Draw AOA diagram and find the critical path. Q.2. What will be the project duration?
- Question Duration of the project Form this schedule of activities, what is the expected time to complete the project? Activity Time Immediate predecessor A 4 В 2 A C 3 В D 12 C E 10 D,E D,E F 6 5Question 1. Answer the following question based on the data from the data of a project in Table-1 Table 1: Project activities and durations Description Predecessors Build internal components Modify roof and floor Construct collection stack Pour concrete and install frame Build high-temperature burner Install pollution control system Install air pollution device Commissioning Activity P Q R S T U V W P, Q Q R, S T b) What is the total duration of this project? The total duration of this project..... T U Duration (days) 4 c) Identify the Critical Activities and Non-Critical Activities for this project. Critical Activities of this project......... Non-Critical Activities of this project. 4 6 10 6 5 3 a) Draw AON Network Diagram of this project and calculate the ES, EF, LS, LF and SLACKS of each activity. 5Assignment 1 Activity Resources Duration (days) Precedence activity A Sub-con 10 Direct labour Material Supplier B 15 A A D B Consider the above activities, and answer the following questions a) Develop the CPM and Gantt Chart of the project b) Prepare the cost schedule, assuming the total cost of activity A = 5000, B = 6000, C = 4000 and D = 3500. Take the overhead cost as 10% and profit as 5% c) Prepare the production schedule d) Prepare the schedule of value e) Prepare the production value (Table) ) Prepare the cash income schedule (Table) 8) Prepare the cost incurred schedule (Table). Take the same condition as in the example in the notes h) Prepare the cash requirement (Table) i) Prepare the cash-flow schedule (Table
- Question 1 What is a unique, one-time event that is intended to achieve an objective in a given time period? Oa task Oan event Oan activity O a job Oa project MacBook Air 000 000 08 F5 DD F6 F8Qno 6. Write a note explaining your project and include all the functions used in your project?Question 1: Salalalh Methanol company management is considering three competing investment Projects A, B & C Year Initial Investment 1 2 3 4 Assume a discount Rate of 5.45 % Project A Project B 12000 4150 Project C 12000 5225 12000 1200 3100 3800 4600 5260 7360 9460 8250 9275 9300 Use the information above and help the management in choosing the most desirable Project using Payback period, Discounted payback Net Present value and Profitability Index. Out of the four methods which is considered to be the most desirable. Explain
- No. Activity Duration Successor Relationship Lag (week) (week) 1 A В, С, D A-B (S-S) A-C (F-S) A-D (F-S) B-E (F-S) c-F (F-S) c-G (F-S) D-H (F-S) E-F (F-S) E-G (F-S) F-1 (F-S) G-I (F-S) H-1(F-S) 5 1 7 E 3 C F, G 4 D 4 H E 7 F, G F 7 G 8 H 2 3 1. Estimate the total project duration. 2. Calculate the total float for each activity in the project. 3. State the critical path.W AutoSave Off H PGDPM AA Calendar JULY 2022 Final No Label ✓ File Home Insert Draw Design Layout 5 X U Undo Page 28 of 32 ■ Paste Clipboard 5103 words Q Search Arial BI U U ab 12 ab x₂ Font References x² A English (South Africa) A A Aa P₂ D✓ Av Mailings 6 Search Review View Help 0 ← 三三三三 ALT Paragraph Normal No Spacing Styles POSTGRADUATE DIPLOMA IN PROJECT MANAGEMENT - ACADEMIC AND ASSESSMENT CALENDAR QUESTION ONE NOTE: The following question requires research in order to be answered. Heading 1 W 1.1 Using an organization of your choice, list and explain the attributes of Project Quality Management. Your submission must include the attributes with reference to case study to display your understanding. G 1.2 With reference to the organization of your choice (your case study) explain the concept of cost of quality. T QUESTION TWO Toyota Motor Corporation is a Japanese car manufacturer that produces and sells motor vehicles all over the globe. In 2016, Toyota was the largest car…7