CASE STUDY In September 2020, ACME Fabricators advised its staff that their new factory and offices out in semi-rural Angle Vale would be ready for completion by the end of April 2022. ACME was a responsible company and liked to keep their premises clean and tidy and their staff happy. The new premises  were developed on a 4.5-hectare site, previously used for grain crops. Consequently, ACME decided that significant landscaping would be required to enhance the amenity of the otherwise bare land. The senior executive group pictured some land contouring with an attractive green lawn, and trees and shrubs to soften the impact of otherwise stark commercial buildings. Accordingly, they notionally allocated $232,000 for the project, and developed a tender document that called for the work to be completed by the time they moved to the new premises. They then invited proposals for landscaping and quotes for the work. A company called Arbor Industries submitted an artist's sketch for the ACME evaluation team to picture what the landscaping would look like. Arbor was selected with a bid of $175,000, substantially lower than any other submission. Arbor then prepared a detailed landscaping plan based on existing drawings of the site provided in the tender. Arbor met with the ACME senior executives to agree on a project start date, access and security of plant and equipment, and a fixed price contract. A contract was duly signed. The project was scoped and planned by Arbor, with specific milestones for site works, irrigation, turf laying, and tree and shrub planting. Arbor had undertaken many similar jobs on city sites in the past and based on the knowledge and skills of the project team, they did not think that a formal project management plan would be needed. All they wanted was agreement on the scope of the project and the key deliverable dates. From experience, they wanted to deal with only one person from ACME and it was agreed that the finance manager, a senior executive, would be responsible for the project. Arbor commenced work on the 16th of November 2020 with site preparation including weed eradication. Work progressed smoothly until 20th of January 2021, when heavy vehicles delivering machinery, plant and equipment to the site significantly damaged the newly prepared and leveled ground for the lawn. The Arbor project manager arranged his first meeting with the ACME finance manager to complain that he would have to re-do the site for the lawn which would take an extra 3-5 days. The finance manager agreed that it was not Arbor's fault and that work would have to be re-done, but as there was no more funding available he   the project manager make the savings somewhere else from within the project By the end of January the landscaping site works were finished and the irrigation system was installed. Planting was to be done in three phases – s Shrub planting would take approximately 4 days, trees 7 days and the lawn would be laid in three separate operations over 2 days. On the first day after the planting commenced, some of the project team noticed a few small plants seemed to be missing or broken off. These were quickly replaced. Within the first 3 days after the last planting, however, it was noted that around 35% of the plantings had been destroyed by rabbits or hares (as it was later determined. Remember, this is in Australia.) The Project Manager was very concerned and called another meeting with the ACME finance manager. Although sympathetic, the finance manager agreed that tree guards needed to be placed around trees but that was a contingency that the Arbor Company should have considered. The Arbor project manager indicated that pests were ACME's problem and again the finance manager indicated that Arbor should make savings elsewhere within its contract. The Arbor project manager reviewed his budget and costs and determined that the only way to re -coup the losses from having to replant the shrubs and protect them, was to plant fewer plants and smaller trees which came at a much lower cost. Another way to make some savings was to try and re -design the irrigation system using fewer sprinklers. Instant lawn was tentatively ordered for around the middle of March 2021 so that delivery would miss the hottest part of the year. Unfortunately, the commercial lawn growers had heavy demand at that time and advised that the last shipment could only be made by mid -February 2021. This was necessary to allow them time to plant new lawn ready for winter and spring clients. Arbor had no choice but to accept delivery in mid-February 2021. As it turned out, it was particularly hot when the lawn delivery was made over the 2 days, with hot gusty northerly winds. QUESTION  In reference to the events highlighted in the case study, critically discuss the impacts of project risks, and provide relevant recommendations to the ACME Fabricators Board of Directors on how they should conduct risk management in their future projects. Your response should refer to relevant examples.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

CASE STUDY

In September 2020, ACME Fabricators advised its staff that their new factory and offices out in semi-rural Angle Vale would be ready for completion by the end of April
2022. ACME was a responsible company and liked to keep their premises clean and tidy and their staff
happy. The new premises  were developed on a 4.5-hectare site, previously used for grain
crops. Consequently, ACME decided that significant landscaping would be required to enhance the amenity
of the otherwise bare land. The senior executive group pictured some land contouring with an attractive
green lawn, and trees and shrubs to soften the impact of otherwise stark commercial buildings. Accordingly,
they notionally allocated $232,000 for the project, and developed a tender document that called for the work
to be completed by the time they moved to the new premises. They then invited proposals for landscaping
and quotes for the work.
A company called Arbor Industries submitted an artist's sketch for the ACME evaluation team to picture
what the landscaping would look like. Arbor was selected with a bid of $175,000, substantially lower than
any other submission. Arbor then prepared a detailed landscaping plan based on existing drawings of the
site provided in the tender. Arbor met with the ACME senior executives to agree on a project start date,
access and security of plant and equipment, and a fixed price contract. A contract was duly signed. The
project was scoped and planned by Arbor, with specific milestones for site works, irrigation, turf laying, and
tree and shrub planting. Arbor had undertaken many similar jobs on city sites in the past and based on the
knowledge and skills of the project team, they did not think that a formal project management plan would
be needed. All they wanted was agreement on the scope of the project and the key deliverable dates. From
experience, they wanted to deal with only one person from ACME and it was agreed that the finance
manager, a senior executive, would be responsible for the project.
Arbor commenced work on the 16th of November 2020 with site preparation including weed eradication.
Work progressed smoothly until 20th of January 2021, when heavy vehicles delivering machinery, plant and
equipment to the site significantly damaged the newly prepared and leveled ground for the lawn. The Arbor
project manager arranged his first meeting with the ACME finance manager to complain that he would have
to re-do the site for the lawn which would take an extra 3-5 days. The finance manager agreed that it was
not Arbor's fault and that work would have to be re-done, but as there was no more funding available he 

 the project manager make the savings somewhere else from within the project
By the end of January the landscaping site works were finished and the irrigation system was installed.
Planting was to be done in three phases – s Shrub planting would take approximately 4 days, trees 7 days and the lawn would be laid in three separate operations over 2 days. On the first day after the planting commenced, some of the project team
noticed a few small plants seemed to be missing or broken off. These were quickly replaced. Within the first
3 days after the last planting, however, it was noted that around 35% of the plantings had been destroyed
by rabbits or hares (as it was later determined. Remember, this is in Australia.) The Project Manager was
very concerned and called another meeting with the ACME finance manager. Although sympathetic, the
finance manager agreed that tree guards needed to be placed around trees but that was a contingency that
the Arbor Company should have considered. The Arbor project manager indicated that pests were ACME's
problem and again the finance manager indicated that Arbor should make savings elsewhere within its
contract.
The Arbor project manager reviewed his budget and costs and determined that the only way to re -coup the
losses from having to replant the shrubs and protect them, was to plant fewer plants and smaller trees which
came at a much lower cost. Another way to make some savings was to try and re -design the irrigation
system using fewer sprinklers. Instant lawn was tentatively ordered for around the middle of March 2021 so
that delivery would miss the hottest part of the year. Unfortunately, the commercial lawn growers had heavy
demand at that time and advised that the last shipment could only be made by mid -February 2021. This
was necessary to allow them time to plant new lawn ready for winter and spring clients. Arbor had no choice
but to accept delivery in mid-February 2021. As it turned out, it was particularly hot when the lawn delivery
was made over the 2 days, with hot gusty northerly winds.

QUESTION
 In reference to the events highlighted in the case study, critically discuss the impacts of project risks,
and provide relevant recommendations to the ACME Fabricators Board of Directors on how they
should conduct risk management in their future projects. Your response should refer to relevant
examples. 

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Productivity
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.