Carbondale Casting produces cast bronze valves on a 12-person assembly line. On a recent day, 180 valves were produced during an 8-hour shift. a) Labor productivity of the line = valves/labor hour (round your response to two decimal places). b) John Goodale, the manager at Carbondale, changed the layout and was able to increase production to 220 units per 8-hour shift. The new labor productivity = valves/labor hour (round your response to two decimal places). c) The percentage of productivity increase = % (round your response to one decimal place).
Question content area
Part 1
Carbondale Casting produces cast bronze valves on a
12-person assembly line. On a recent day,
180 valves were produced during
an
8-hour shift.
Part 2
a) Labor productivity of the line =
enter your response here
valves/labor hour (round your response to two decimal places).
Part 3
b) John Goodale, the manager at Carbondale, changed the layout and was able to increase production to
220 units per
8-hour shift. The new labor productivity
=
enter your response here
valves/labor hour (round your response to two decimal places).
Part 4
c) The percentage of productivity increase
=
enter your response here
% (round your response to one decimal place).
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 3 images