Problem 2-2 (Algo) The manager of a crew that installs carpeting has tracked the crew’s output over the past several weeks, obtaining these figures:    Week Crew Size Yards Installed 1 2 95   2 3 70   3 6 100   4 7 50   5 5 70   6 4 55          Click here for the Excel Data File a. Compute the labor productivity for each of the weeks. (Round your answers to 2 decimal places.)     b. Which crew size works best?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Problem 2-2 (Algo)

The manager of a crew that installs carpeting has tracked the crew’s output over the past several weeks, obtaining these figures: 

 
Week Crew Size Yards Installed
1 2 95  
2 3 70  
3 6 100  
4 7 50  
5 5 70  
6 4 55  
 

    

Click here for the Excel Data File


a. Compute the labor productivity for each of the weeks. (Round your answers to 2 decimal places.)

 
 


b. Which crew size works best?
 

 
The manager of a crew that installs carpeting has tracked the crew's output over the past several weeks, obtaining these figures:
Crew Size
Yards Installed
2
95
70
3
6
7
5
4
Week
1
HAMASn 10
2
3
4
5
6
Week
Click here for the Excel Data File
a. Compute the labor productivity for each of the weeks. (Round your answers to 2 decimal places.)
1
2
3
4
5
6
Crew size
A crew of
2
3
6
7
5
4
100
50
b. Which crew size works best?
70
55
Labor productivity
(Yards/Person)
seems to work best.
Transcribed Image Text:The manager of a crew that installs carpeting has tracked the crew's output over the past several weeks, obtaining these figures: Crew Size Yards Installed 2 95 70 3 6 7 5 4 Week 1 HAMASn 10 2 3 4 5 6 Week Click here for the Excel Data File a. Compute the labor productivity for each of the weeks. (Round your answers to 2 decimal places.) 1 2 3 4 5 6 Crew size A crew of 2 3 6 7 5 4 100 50 b. Which crew size works best? 70 55 Labor productivity (Yards/Person) seems to work best.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.