A competitor of Kozar International, Inc. has begun marketing a new instant-developing film project. Kozar has had a similar product under study in its R&D department but has not yet been able to begin production. Because of the competitor's action, top managers have asked for a speedup of R&D activities so that Kozar can produce and market instant film at the earliest possible date. The predecessor information and activity time estimates in months are shown in the following columns. Activity A a. Choose the correct project network. The correct network is -Select- BU C D EF G Immediate Predecessor(s) A A B, C B C, D, E E Optimistic Time 1 3 1 3.5 4 6.5 5 Most Probable Time 1.5 4 2 5 5 7.5 9 Pessimistic Time 5 5 3 6.5 12 11.5 13

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

c. What is the probability of completion in 20, 21, and 22 weeks? Use Appendix A to answer the question. Do not round intermediate calculations. Round your answers to four decimal places.

Probability of completion in 20 weeks: 

Probability of completion in 21 weeks: 

Probability of completion in 22 weeks: 

Compute expected times and variances for each activity. Round your answers for the expected times to nearest whole number and for the variances to two decimal places.
Activity
A
B
с
D
E
F
G
Activity
A
b. Develop an activity schedule for this project using early and late start and finish times and compute activity slack time. If your answer is zero, enter "0". Round your
answers to the nearest whole number.
B
с
D
E
F
Mean
G
Immediate
Predecessor(s)
A
A
B, C
B
Variance
C, D, E
E
Time
(months)
Earliest
Start
Earliest
Finish
Latest
Start
Latest
Finish
Slack
Transcribed Image Text:Compute expected times and variances for each activity. Round your answers for the expected times to nearest whole number and for the variances to two decimal places. Activity A B с D E F G Activity A b. Develop an activity schedule for this project using early and late start and finish times and compute activity slack time. If your answer is zero, enter "0". Round your answers to the nearest whole number. B с D E F Mean G Immediate Predecessor(s) A A B, C B Variance C, D, E E Time (months) Earliest Start Earliest Finish Latest Start Latest Finish Slack
A competitor of Kozar International, Inc. has begun marketing a new instant-developing film project. Kozar has had a similar product under study in
its R&D department but has not yet been able to begin production. Because of the competitor's action, top managers have asked for a speedup of
R&D activities so that Kozar can produce and market instant film at the earliest possible date. The predecessor information and activity time
estimates in months are shown in the following columns.
Activity
A
a. Choose the correct project network.
The correct network is -Select-
CD
B
с
DEFG
Immediate
Predecessor(s)
A
A
B, C
B
C, D, E
E
Optimistic
Time
1
3
1
3.5
4
6.5
5
Most Probable
Time
1.5
4
2
5
5
7.5
9
Pessimistic
Time
5
5
3
6.5
12
11.5
13
Transcribed Image Text:A competitor of Kozar International, Inc. has begun marketing a new instant-developing film project. Kozar has had a similar product under study in its R&D department but has not yet been able to begin production. Because of the competitor's action, top managers have asked for a speedup of R&D activities so that Kozar can produce and market instant film at the earliest possible date. The predecessor information and activity time estimates in months are shown in the following columns. Activity A a. Choose the correct project network. The correct network is -Select- CD B с DEFG Immediate Predecessor(s) A A B, C B C, D, E E Optimistic Time 1 3 1 3.5 4 6.5 5 Most Probable Time 1.5 4 2 5 5 7.5 9 Pessimistic Time 5 5 3 6.5 12 11.5 13
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 35 images

Blurred answer
Follow-up Questions
Read through expert solutions to related follow-up questions below.
Follow-up Question

Attached is Appendix A for question C. 

Solution
Bartleby Expert
SEE SOLUTION
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.