Activities/Assessments: Activity 12: Individual Given the activities of a project; their optimistic (t.), most likely (tm) and pessimistic (t,) time estimates; and their immediate predecessors shown below: 1. When is the earliest project completion? 2. Which activities are critical (should not be delayed)? 3. Which activities are noncritical (can be delayed)? 4. How long can cach of the activities be delayed without delaying the whole project (maximum slack)? Maximum Slack, months Immediate Activity Times, months Activities Predecessors to tm t te A B 4 13 7 2 6. 4 16 2 C D A 2 4 1 3 7 14 E F G 3 5 13 13 14 E 10 G В, D F, H, I 13 16 25

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
please answer number 4 only. complete the table thank you
Activities/Assessments:
Activity 12: Individual
Given the activities of a project; their optimistic (t.), most likely (tm) and pessimistic
(t,) time estimates; and their immediate predecessors shown below:
1. When is the earliest project completion?
2. Which activities are critical (should not be delayed)?
3. Which activities are noncritical (can be delayed)?
4. How long can each of the activities be delayed without delaying the whole
project (maximum slack)?
Activity Times, months
te
13
16
Immediate
Maximum Slack,
months
Activities
Predecessors
tm
4
в
2
D
E
E
10
13
G
В, D
F, H, I
14
J
13
16
25
I x
Transcribed Image Text:Activities/Assessments: Activity 12: Individual Given the activities of a project; their optimistic (t.), most likely (tm) and pessimistic (t,) time estimates; and their immediate predecessors shown below: 1. When is the earliest project completion? 2. Which activities are critical (should not be delayed)? 3. Which activities are noncritical (can be delayed)? 4. How long can each of the activities be delayed without delaying the whole project (maximum slack)? Activity Times, months te 13 16 Immediate Maximum Slack, months Activities Predecessors tm 4 в 2 D E E 10 13 G В, D F, H, I 14 J 13 16 25 I x
Expert Solution
steps

Step by step

Solved in 4 steps with 5 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.