Activities, preceding activities, normal and crashed completion times of each of the activities and crashed costs of activities per week of a project are given in the following table. Activity Preceding Activity Normal Crashed Completion time (week) Crashed Cost Completion Time (week) 7 per week A B 6 $500 3 $700 $600 $800 A 4 А, С В. D D, E D 9. 7 E F 10 9 8 $400 i. Draw the network diagram linking all the activities in a way that it shows if there exist any preceding activity/activities before starting each of the mentioned activities in the above table. ii. Find the earliest start time, the earliest finish time, the latest start time and the latest finish time of each of the activities in the drawn diagram of the project and hence the completion time of the project and the critical path.
Activities, preceding activities, normal and crashed completion times of each of the activities and crashed costs of activities per week of a project are given in the following table. Activity Preceding Activity Normal Crashed Completion time (week) Crashed Cost Completion Time (week) 7 per week A B 6 $500 3 $700 $600 $800 A 4 А, С В. D D, E D 9. 7 E F 10 9 8 $400 i. Draw the network diagram linking all the activities in a way that it shows if there exist any preceding activity/activities before starting each of the mentioned activities in the above table. ii. Find the earliest start time, the earliest finish time, the latest start time and the latest finish time of each of the activities in the drawn diagram of the project and hence the completion time of the project and the critical path.
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
100%
![Activities, preceding activities, normal and crashed completion times of each of the activities and
crashed costs of activities per week of a project are given in the following table.
Activity Preceding
Activity
Normal
Crashed Completion
time (week)
Crashed Cost
Completion Time
(week)
7
per week
A
7
B
$500
C
4
3
$700
$600
A
A, C
В, D
D, E
D
7
E
F
10
9.
$800
9
8
$400
i.
Draw the network diagram linking all the activities in a way that it shows if there exist any
preceding activity/activities before starting each of the mentioned activities in the above
table.
ii.
Find the earliest start time, the earliest finish time, the latest start time and the latest finish
time of each of the activities in the drawn diagram of the project and hence the completion
time of the project and the critical path.](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F5b368cdf-4379-40a1-b80a-f91566568c1a%2F91b810ce-2fab-41b8-b0bb-747c00d89b3e%2Fuwmfnj_processed.png&w=3840&q=75)
Transcribed Image Text:Activities, preceding activities, normal and crashed completion times of each of the activities and
crashed costs of activities per week of a project are given in the following table.
Activity Preceding
Activity
Normal
Crashed Completion
time (week)
Crashed Cost
Completion Time
(week)
7
per week
A
7
B
$500
C
4
3
$700
$600
A
A, C
В, D
D, E
D
7
E
F
10
9.
$800
9
8
$400
i.
Draw the network diagram linking all the activities in a way that it shows if there exist any
preceding activity/activities before starting each of the mentioned activities in the above
table.
ii.
Find the earliest start time, the earliest finish time, the latest start time and the latest finish
time of each of the activities in the drawn diagram of the project and hence the completion
time of the project and the critical path.
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 2 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Recommended textbooks for you
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Business in Action](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
![Production and Operations Analysis, Seventh Editi…](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.